Activity ID Activity Name Duration Start Date Finish Date 2023 2024 2025

May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul
514 17-Jun-23 11-Nov-24 Mandani Bay Quay Phase 2 Block 1
Mandani Bay Quay Phase 2 Block 1
Electrical Works Podium Master Schedule 514 17-Jun-23 11-Nov-24 Electrical Works Podium Master Schedule

Key Milestone 514 17-Jun-23 11-Nov-24 Key Milestone


Contractual Milestone 514 17-Jun-23 11-Nov-24 Contractual Milestone
KM-1000 Letter of Award/Notice to Proceed 0 17-Jun-23 Letter of Award/Notice to Proceed
KM-1010 Start Date of Construction 0 17-Jun-23 Start Date of Construction
KM-1020 Project Completion of Electrical Works Podium 0 11-Nov-24* Project Completion of Electrical Works Podium
Construction Milestone 135 14-Jun-24 27-Oct-24 Construction Milestone
KM-1030 Completion of Electrical 0 14-Jun-24 Completion of Electrical
KM-1040 Completion of Communications 0 29-Jul-24 Completion of Communications
KM-1050 Completion of Electronic Safety & Security 0 28-Aug-24 Completion of Electronic Safety & Security
KM-1060 Completion of Electrical Utilities 0 27-Oct-24 Completion of Electrical Utilities
Preliminaries 514 17-Jun-23 11-Nov-24 Preliminaries
PR-1070 Mobilization 41 17-Jun-23 27-Jul-23 Mobilization
PR-1080 Demobilization 1 11-Nov-24 11-Nov-24 Demobilization
PR-1090 Temporary Power and Light 514 17-Jun-23 11-Nov-24 Temporary Power and Light
PR-1100 Water for the Works 514 17-Jun-23 11-Nov-24 Water for the Works
PR-1110 Temporary Telecommunications 514 17-Jun-23 11-Nov-24 Temporary Telecommunications
PR-1120 Toilet Facilities 514 17-Jun-23 11-Nov-24 Toilet Facilities
PR-1130 Storage, Workshops and Offices 514 17-Jun-23 11-Nov-24 Storage, Workshops and Offices
PR-1140 Site Office Maintenance 514 17-Jun-23 11-Nov-24 Site Office Maintenance
PR-1150 Fabrication Sheds 514 17-Jun-23 11-Nov-24 Fabrication Sheds
PR-1160 Transport Vehicle and Expenses 514 17-Jun-23 11-Nov-24 Transport Vehicle and Expenses
PR-1170 Environmental Health and Safety (EHS) 514 17-Jun-23 11-Nov-24 Environmental Health and Safety (EHS)
PR-1180 Contractor's Staff 514 17-Jun-23 11-Nov-24 Contractor's Staff
PR-1190 Statutory Obligations 514 17-Jun-23 11-Nov-24 Statutory Obligations
PR-1200 Signals and Warnin gs 514 17-Jun-23 11-Nov-24 Signals and Wa rnin gs
PR-1210 Prevention of Mosquito Breeding/Pest Control 514 17-Jun-23 11-Nov-24 Prevention of Mosquito Breeding/Pest Control
PR-1220 Water Pollution Control & Flood Control 514 17-Jun-23 11-Nov-24 Water Po lution Control & Flood Control
PR-1230 Receipt, Acceptance, Transportation and Positioning of Owner 514
Supplied Equipment,
17-Jun-23 Goods
11-Nov-24
and Materials Receipt, Acceptance, Transportation and Positioning of Owner Supplied Equipment, Goods
PR-1240 Advance Payment, Performance and Guarantee Bond 514 17-Jun-23 11-Nov-24 Advance Payment, Performance and Guarantee Bond
PR-1250 Material Standards 514 17-Jun-23 11-Nov-24 Material Standards
PR-1260 Verification of Quality 514 17-Jun-23 11-Nov-24 Verification of Qualit y
PR-1270 As-built Drawings & Close-out reports 514 17-Jun-23 11-Nov-24 As-built Drawings & Close-out reports
PR-1280 Operation and Maintenance Manuals 514 17-Jun-23 11-Nov-24 Operation and Maintenance Manuals
PR-1290 Final Testing 514 17-Jun-23 11-Nov-24 Final Testin g
Construction 495 06-Jul-23 11-Nov-24 Construction
Electrical 345 06-Jul-23 14-Jun-24 Electrical
POD-ELEC-1300 Grounding and Bonding 20 15-Aug-23 03-Sep-23 Grounding and Bonding
POD-ELEC-1310 Roughing ins Embed 20 26-Jul-23 14-Aug-23 Roughing ins Embed
POD-ELEC-1320 Roughing ins Exposed 20 06-Jul-23 25-Jul-23 Roughing ins Exposed
POD-ELEC-1330 Pullboxes 20 04-Sep-23 23-Sep-23 Pullboxes
POD-ELEC-1340 Cable Trays for Electrical Systems 20 24-Sep-23 13-Oct-23 Cable Trays for Electrical Systems
POD-ELEC-1350 THHN/THWN 20 14-Oct-23 02-Nov-23 THHN/THWN
POD-ELEC-1360 Fire Rated Cable 20 03-Nov-23 22-Nov-23 Fire Rated Cable
POD-ELEC-1370 XLPE Cable 20 23-Nov-23 12-Dec-23 XLPE Cable
POD-ELEC-1380 Switchboards and Panelboards 20 13-Dec-23 01-Jan-24 Switchboards and Panelboards
POD-ELEC-1390 Low-Voltage Switchgear 15 02-Jan-24 16-Jan-24 Low-Voltage Switchgear
POD-ELEC-1400 Low-Voltage Transformers 15 17-Jan-24 31-Jan-24 Low-Voltage Transformers
POD-ELEC-1410 Medium-Voltage Switchgear 15 01-Feb-24 15-Feb-24 Medium-Voltage Switchgear
POD-ELEC-1420 Transfer Switches 15 16-Feb-24 01-Mar-24 Transfer Switches

Critical Remaning Milestone Bar Level of Effort Date Revis... Checked Approved
MANDANI BAY QUAY PHASE 2 BLOCK 1  
Non Crit ical Remaining Milestone Bar Summary Bar 04-Jun-... 0 Joel Naingue Kristofferson L. Ocho
F.E. ZUELLIG, MANDAUE CITY, CEBU, PHILIPPINES MSERV PIC MSERV PM 1 of 2
Critical Remaning Bar
Electrical Works Podium
Non Crit ical Remaining Bar
Activity ID Activity Name Duration Start Date Finish Date 2023 2024 2025
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul
POD-ELEC-1430 DP RES FOR T1, T2, T3 15 02-Mar-24 16-Mar-24 DP RES FOR T1, T2, T3
POD-ELEC-1440 Electricity Metering 15 17-Mar-24 31-Mar-24 Electricity Metering
POD-ELEC-1450 Flexible Droppings 15 01-Apr-24 15-Apr-24 Flexible Droppings
POD-ELEC-1460 Wiring Devices 15 16-Apr-24 30-Apr-24 Wiring Devices
POD-ELEC-1470 Interior Lighting 15 01-May-24 15-May-24 Interior Lighting
POD-ELEC-1480 Façade Lighting 15 16-May-24 30-May-24 Façade Lighting
POD-ELEC-1490 Landscape Lighting (SGS Design) 15 31-May-24 14-Jun-24 Landscape Lighting (SGS Design)
Communications (FTTH System) 150 15-Jun-24 11-Nov-24 Communications (FTTH System)
POD-COM-1500 Roughing ins Exposed 15 15-Jun-24 29-Jun-24 Roughing ins Exposed
POD-COM-1510 Cable Tray 15 30-Jun-24 14-Jul-24 Cable Tray
POD-COM-1520 Devices and Equipment 15 28-Oct-24 11-Nov-24 Devices and Equipment
POD-COM-1530 Wires / Cables 15 15-Jul-24 29-Jul-24 Wires / Cables
Electronic Safety & Security (Point of Sale System) 30 30-Jul-24 28-Aug-24 Electronic Safety & Security (Point of Sale System)
POD-ELECTRO-1540 Roughing ins Exposed # 1 15 30-Jul-24 13-Aug-24 Roughing ins Exposed # 1
POD-ELECTRO-1550 Roughing ins Exposed # 2 15 14-Aug-24 28-Aug-24 Roughing ins Exposed # 2
Electrical Utilities 60 29-Aug-24 27-Oct-24 Electrical Utilities
POD-ELEC-UT-1560 First Private Pole 15 29-Aug-24 12-Sep-24 First Private Pole
POD-ELEC-UT-1570 Cable Tray 15 13-Sep-24 27-Sep-24 Cable Tray
POD-ELEC-UT-1580 Duct Line 15 28-Sep-24 12-Oct-24 Duct Line
POD-ELEC-UT-1590 Wires / Cables for Electrical 15 13-Oct-24 27-Oct-24 Wires / Cables for Electrical

Critical Remaning Milestone Bar Level of Effort Date Revis... Checked Approved
MANDANI BAY QUAY PHASE 2 BLOCK 1  
Non Crit ical Remaining Milestone Bar Summary Bar 04-Jun-... 0 Joel Naingue Kristofferson L. Ocho
F.E. ZUELLIG, MANDAUE CITY, CEBU, PHILIPPINES MSERV PIC MSERV PM 2 of 2
Critical Remaning Bar
Electrical Works Podium
Non Crit ical Remaining Bar

You might also like