Electrical Works Podium
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul
514 17-Jun-23 11-Nov-24 Mandani Bay Quay Phase 2 Block 1
Mandani Bay Quay Phase 2 Block 1
Electrical Works Podium Master Schedule 514 17-Jun-23 11-Nov-24 Electrical Works Podium Master Schedule
Critical Remaning Milestone Bar Level of Effort Date Revis... Checked Approved
MANDANI BAY QUAY PHASE 2 BLOCK 1
Non Crit ical Remaining Milestone Bar Summary Bar 04-Jun-... 0 Joel Naingue Kristofferson L. Ocho
F.E. ZUELLIG, MANDAUE CITY, CEBU, PHILIPPINES MSERV PIC MSERV PM 1 of 2
Critical Remaning Bar
Electrical Works Podium
Non Crit ical Remaining Bar
Activity ID Activity Name Duration Start Date Finish Date 2023 2024 2025
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul
POD-ELEC-1430 DP RES FOR T1, T2, T3 15 02-Mar-24 16-Mar-24 DP RES FOR T1, T2, T3
POD-ELEC-1440 Electricity Metering 15 17-Mar-24 31-Mar-24 Electricity Metering
POD-ELEC-1450 Flexible Droppings 15 01-Apr-24 15-Apr-24 Flexible Droppings
POD-ELEC-1460 Wiring Devices 15 16-Apr-24 30-Apr-24 Wiring Devices
POD-ELEC-1470 Interior Lighting 15 01-May-24 15-May-24 Interior Lighting
POD-ELEC-1480 Façade Lighting 15 16-May-24 30-May-24 Façade Lighting
POD-ELEC-1490 Landscape Lighting (SGS Design) 15 31-May-24 14-Jun-24 Landscape Lighting (SGS Design)
Communications (FTTH System) 150 15-Jun-24 11-Nov-24 Communications (FTTH System)
POD-COM-1500 Roughing ins Exposed 15 15-Jun-24 29-Jun-24 Roughing ins Exposed
POD-COM-1510 Cable Tray 15 30-Jun-24 14-Jul-24 Cable Tray
POD-COM-1520 Devices and Equipment 15 28-Oct-24 11-Nov-24 Devices and Equipment
POD-COM-1530 Wires / Cables 15 15-Jul-24 29-Jul-24 Wires / Cables
Electronic Safety & Security (Point of Sale System) 30 30-Jul-24 28-Aug-24 Electronic Safety & Security (Point of Sale System)
POD-ELECTRO-1540 Roughing ins Exposed # 1 15 30-Jul-24 13-Aug-24 Roughing ins Exposed # 1
POD-ELECTRO-1550 Roughing ins Exposed # 2 15 14-Aug-24 28-Aug-24 Roughing ins Exposed # 2
Electrical Utilities 60 29-Aug-24 27-Oct-24 Electrical Utilities
POD-ELEC-UT-1560 First Private Pole 15 29-Aug-24 12-Sep-24 First Private Pole
POD-ELEC-UT-1570 Cable Tray 15 13-Sep-24 27-Sep-24 Cable Tray
POD-ELEC-UT-1580 Duct Line 15 28-Sep-24 12-Oct-24 Duct Line
POD-ELEC-UT-1590 Wires / Cables for Electrical 15 13-Oct-24 27-Oct-24 Wires / Cables for Electrical
Critical Remaning Milestone Bar Level of Effort Date Revis... Checked Approved
MANDANI BAY QUAY PHASE 2 BLOCK 1
Non Crit ical Remaining Milestone Bar Summary Bar 04-Jun-... 0 Joel Naingue Kristofferson L. Ocho
F.E. ZUELLIG, MANDAUE CITY, CEBU, PHILIPPINES MSERV PIC MSERV PM 2 of 2
Critical Remaning Bar
Electrical Works Podium
Non Crit ical Remaining Bar