TOWER 3 – 29TH FLOOR, AREA 1 ROUGHING INS FOR ELECTRICAL AND AUXILIARY (DONE)

June 22, 2023


• COMPLETED CONCRETE POURING
TOWER 3 – 29TH FLOOR, AREA 3 ROUGHING INS FOR ELECTRICAL AND AUXILIARY (DONE)

June 26, 2023


• COMPLETED CONCRETE POURING
TOWER 3 – 29TH FLOOR, AREA 2 ROUGHING INS FOR ELECTRICAL AND AUXILIARY (ONGOING)

July 1, 2023
• COMPLETED CONCRETE POURING
TOWER 3 – VERTICAL LAYOUTS UPDATE (19TH FLOOR, AREA 1) ONGOING
TOWER 3 – ELEVATOR LOBBY ANNUNCIATOR (15TH FLOOR) (DONE)
TOWER 3 – FDAS MONITORING
TOWER 3 – FDAS MONITORING
TOWER 3 – FDAS MONITORING
TOWER 3 – CCTV MONITORING
TOWER 3 – PABGM SYSTEM MONITORING
TOWER 3 – DMS MONITORING
TOWER 3 – RECTIFICATION OF MOCK UP (6TH FLOOR, UNIT 27) DONE

BEFORE AFTER

RECTIFICATION
TOWER 3 – RECTIFICATION OF MOCK UP (6TH FLOOR, UNIT 27) DONE
BEFORE AFTER

RECTIFICATION