You are on page 1of 2

[Format 7-1]Table IBI PM T&C Prepare by

PIPE LEAK TEST RECORD


DATE ########
T.T.E. ENGINEERING(M) SDN.BHD
REPORT by SHAKIRIN

1.LINE NAME PCW (S/R) Area PRODUCTION B1


2.SYSTEM NAME 6 Axis Drill Machine #32 (Machine #92) (Refer to the attached Drawings)
3.PIPE SIZE 25 A

4.MATERIAL GI
5.TESTING CONDITION
DI water/City Water/ Nitrogen / Others (         )
1) Test with
Compressed Air (Oil Free / Untreated )
2) Working Pressure 0.80 MPa
3) Testing Pressure 1.00 MPa
4) Pressure holding Time 60 minutes
5) Testing points All connection / Partial (see the attached drawings)
6.TESTING RESULT
1) Testing Date & time Start 4/10/2022 1.20PM
End 4/10/2022 2.25PM
2) Conducted by TTE Person name SHAKIRIN
3) Witness IBIDEN/TTE Person name SYAHIR
4) Before Testing 1.05 MPa(S) 1.06 MPa (R)
5) After Testing 1.05 MPa (S) 1.06 MPa (R)
6) Result Accept ・Reject Person name/sign
7.TESTING INSTRUMENT
Instrument Name Measurement Range Model Brand Remark
1) Pressure Gauge 0 ~ 2 MPa Unijin
2) ~
3) ~
8.REMARKS
[Format 7-1]Table
9.Reference documents.
  1)Piping schematic shop drawing show testing line
  2)Testing record photo.
  3)Others

Initial Water Leak Testing Pressure (S) = 1.05MPa Initial Water Leak Testing Pressure(S) = 1.05MPa
Initial Water Leak Testing Pressure (R) = 1.06MPa Initial Water Leak Testing Pressure (R) = 1.06MPa

After Water leak Testing Reading(S) = 1.05MPa After Water leak Testing Reading(R) = 1.05MPa
After Water leak Testing Reading(R) = 1.06MPa After Water leak Testing Reading(R) = 1.06MPa