Surveying A Tile Field


Total Hours: 17 Hours

Date Hours Task/Description


Wednesday 7am-4pm ● Training with Mike Tweeten(Mentor)
November 7th, 2022 9 Hours ● Locating old tiles in trenches
● Placing flags

Friday 9am-3pm ● Mapped out the old tile lines


November 9th, 2022 6 Hours ● Dug up old tile
● Layed out new tile map

Monday 3pm-5pm ● Programed and laid out the new map


March 6th, 2023 2 Hours ● Put the old map lines onto the new
map
● Put the new map layout into the
system