Professional Documents
Culture Documents
Method Statement of Revetment Works
Method Statement of Revetment Works
REVETMENT WORK
METHOD STATEMENT
1
PROPOSAL FOR RECLAMATION, REVETMENT, DRAINAGE AND
ASSOCIATED WORKS ON LAND PARCELS KNOWN AS LIDO
Doc No: CCCC-LIDO-MS-004
WATERFRONT IN DAERAH JOHOR BAHRU, JOHOR DARUL TAKZIM
Rev. 0
CONTENTS
1.0 INTRODUCTION ............................................................................................. 1
2.0 ALTERNATIVE DESIGN ................................................................................ 1
3.0 CONSTRUCTION SEQUENCE ..................................................................... 1
3.1 Cross-Section (thickness: 1.5~3m) ............................................................ 1
3.2 Cross-section (thickness: 8~9.5m) ............................................................. 3
4.0 RECLAMATION WORK WITHIN THE SCOPE OF REVETMENT ........... 4
4.1 Sand filling .................................................................................................. 4
4.2 Laying of geotextile .................................................................................... 6
4.3 Rock Installation......................................................................................... 7
4.4 PVD works .................................................................................................. 8
2
PROPOSAL FOR RECLAMATION, REVETMENT, DRAINAGE AND
ASSOCIATED WORKS ON LAND PARCELS KNOWN AS LIDO
Doc No: CCCC-LIDO-MS-004
WATERFRONT IN DAERAH JOHOR BAHRU, JOHOR DARUL TAKZIM
Rev. 0
1.0 INTRODUCTION
This method statement outlines the basic sequence of work to be carried out for the
proposed revetment work at LIDO Boulevard. It includes shop drawings, working
progress and working method statement.
According to the geological borehole report, some soft silt existed beneath the seabed
mainly along area of revetment works, of which thickness ranged 1.5~3m and 8~9.5m.
Two types of shop drawings as shown below.
1
PROPOSAL FOR RECLAMATION, REVETMENT, DRAINAGE AND
ASSOCIATED WORKS ON LAND PARCELS KNOWN AS LIDO
Doc No: CCCC-LIDO-MS-004
WATERFRONT IN DAERAH JOHOR BAHRU, JOHOR DARUL TAKZIM
Rev. 0
Step 1: Soft silt will be extruded from the bottom during the process of filling of sand bund to
+0m RL.
Step 2: Borehole work is executed to check the stability of sand bund, if factor of safety is below
1.2, PVD will be inserted at the slope with 1.1m spacing. Then following toe protection
work.
Step 3: Continuing to filling sand to +3.0m RL, then revetment work to be executed at the slope.
2
PROPOSAL FOR RECLAMATION, REVETMENT, DRAINAGE AND
ASSOCIATED WORKS ON LAND PARCELS KNOWN AS LIDO
Doc No: CCCC-LIDO-MS-004
WATERFRONT IN DAERAH JOHOR BAHRU, JOHOR DARUL TAKZIM
Rev. 0
3
PROPOSAL FOR RECLAMATION, REVETMENT, DRAINAGE AND
ASSOCIATED WORKS ON LAND PARCELS KNOWN AS LIDO
Doc No: CCCC-LIDO-MS-004
WATERFRONT IN DAERAH JOHOR BAHRU, JOHOR DARUL TAKZIM
Rev. 0
Non-woven fabrics adopted in this project, with the specifications of 400g/m2, shall
be spliced and sewed in accordance with the construction requirement and
manufacturer’s instruction.
After the splicing and sewing work is completed, fabrics shall be transported to the
construction site for laying. To avoid the shifting of fabric in water, the upper layer
should be covered by rocks timely during the laying process.
6
PROPOSAL FOR RECLAMATION, REVETMENT, DRAINAGE AND
ASSOCIATED WORKS ON LAND PARCELS KNOWN AS LIDO
Doc No: CCCC-LIDO-MS-004
WATERFRONT IN DAERAH JOHOR BAHRU, JOHOR DARUL TAKZIM
Rev. 0
Riprap construction include on land, water two parts. Which land on the ground with
a long arm digging digging machine construction; water riprap with long arm digging
machine with plum blossom, docked in the flat bar for construction.
(1) land construction
After the truck is transported to the construction site, the manager instructs the truck
to unload the material to the proposed construction site, and the digging machine
throws the stone on the slope.
refueling, by the positioning of the long arm digging machine to grab stone
construction.
8
PROPOSAL FOR RECLAMATION, REVETMENT, DRAINAGE AND
ASSOCIATED WORKS ON LAND PARCELS KNOWN AS LIDO
Doc No: CCCC-LIDO-MS-004
WATERFRONT IN DAERAH JOHOR BAHRU, JOHOR DARUL TAKZIM
Rev. 0