You are on page 1of 1

Slope Reinforcemell using Shotcrete

in Arizona 7,000 cubic yards of shotcrete


applied onto mountainsides
The articles published in the
Project Profile section are pro- W ith more th an 7,000 cubic
yards (5,350 m3) of shotcrete to be
used for slope reinforcement in the Mesa-
Garner said they prim arily use a
Putzmeister Katt-Kreter® pump, but they
occasionally switch to the smaller
vided by the manufacturers or
suppliers of the products men- Payson Highway expansion in Arizona, it Putzmeister Thom-Katt® TS 2040 trailer
tioned. They are provided for may be the biggest shotcrete application in the pump. "It depends on how long the run is,"
reader interest only, and do country. The project consists of shotcreting she said. "If we're pumping shotcrete for a
not constitute a sanction or thirteen freshly-cut mountainsides in the Kitty distance of200 to 300 feet (60 to 90 m) we' ll
endorsement of those prod- Joe Canyon of the Matazel Mountain Range use the Katt-Kreter because of its greater
ucts by the American on Highway 87 between the cities of Mesa and pumping power. In areas where the run is
Shotcrete Association. Payson. The total cost of the 17 -mile less than 200 feet (60 m) we' ll probably go
(27 km) road expansion is $55 million. with the Thom-Katt."
"The entire project will take more than The Putzmeister Katt-Kreter is powered
seven months to complete," said Mickey by a 101-horsepower engine and can pump
Garner, president of Shotcrete Specialties, up to 50 cubic yards (38m 3) an hour. Garner
the sub-contractor. "And we'd be done if it said the crews also like the Katt-Kreter be-
hadn't been for a freak snow last spring," cause of its twin-shifting cylinders, which
she continued. The area had about 3 feet allow the pump to cycle smoothly. "A smooth
(1 m) of snow just as the company was operation makes a long day shorter for
starting the project. the nozzleman."
She said another reason the project is Even though the shotcrete is precolored a
taking so long is that they have to follow reddish brown to match the rock, ADOT
other contractors who are doing the wanted it to look authentic. "We carve it
blasting and dirt removal. "The ter- using knives and trowels to give it the appear-
rain in that area is a mixture of loose ance of a natural rock surface," she said.
rock and dirt, which can cause un- While it only takes a crew of six to apply
stable conditions for the construction the shotcrete, it takes 12 people to carve it.
crews." She said they have had some "They have to do it when it's still moist and
dirt and rockslides already, and al- workable," said Garner, "and then still work
though no one was injured, it has fairly fast before the mixture sets." Shotcrete
slowed down the project. Specialties aimed to complete the enor-
After a mountainside is cut away, mous shotcrete job in November, 1999.
Shotcrete Specialties' crews place a ADOT said the entire divided four-lane
drainage fabric against the rock wall highway project would be completed in the
to prevent water pressure build-up. spring of 2001.
Then wire mesh is placed over the
Putzmeister America is the North American
surface which is held in place by
headquarters of one of the world's largest
anchor plates secured by soil nails.
manufacturers of concrete pumps and con-
The soil nails are usually bolts that
veyors. Putzmeister offers a complete line
can go into the soil or rock up to a depth
of truck-mounted concrete boom pumps,
of 3 feet (1 m). A 12-inch (300 mm)
separate placing booms, portable and truck-
coat of shotcrete is then placed onto
mounted telescopic conveyors, large-line
the wire mesh at the rate of 60 to 70
and high pressure trailer pumps as well as
cubic yards (46 to 54m3) a day. The
mortar, grout, shotcrete, plaster, and fire-
shotcrete mix used is 4,000 psi
proofing pumps and mixers . • .._
(28 MPa) strength, specified by the
Arizona Department of Transporta-
tion (ADOT), but there are no special
additives required.

26 Shotcrete Magazine • February 2000

You might also like