ABSTRACT OF ESTIMATE

[ As per Unified Schedule of Rates of C.G. Public Works Department 2015]


S.No PARTICULAR OF ITEMS QUANTITY UNIT RATE/UNIT AMOUNT Unit
1 Earthwork in excavation 191.84 Cum. 185.00 35489.80 Rs.

2 Base concrete P.C.C. 1:4:8 11.13 Cum. 2659.00 29600.97 Rs.

3 9" K.B.M. in C.M. 95.15 Cum. 3635.00 345881.38 Rs.

4 R.C.C work. 65.65 Cum. 4231.00 277751.12 Rs.

5 Shuttering. 442.31 Sqm. 202.00 89346.51 Rs.

6 M.S. reinforcement. 78.78 Qui. 5450.00 429329.31 Rs.

7 Cement plastering. 499.54 Sqm. 120.00 59944.24 Rs.

8 Sal wood work 0.70 Cum. 61051.00 42881.06 Rs.

9 Flush doors 13.80 Sqm. 2467.00 34047.35 Rs.

10 Biza wood work for windows 9.29 Sqm. 1885.00 17518.59 Rs.

11 Vitrified tile flooring. 58.55 Sqm. 1151.00 67391.26 Rs.

12 Moorum filling 166.95 Cum. 371.00 61938.49 Rs.

13 Grill work. 257.90 Kg. 66.00 17021.38 Rs.

14 Wall painting 499.54 Sqm. 107.50 53700.05 Rs.

15 Wood & grill painting 35.08 Sqm. 78.50 2754.07 Rs.

Total :- 1,564,595.57 Rs.


Add 15% for sanitary, water supply and electrical 234,689.34 Rs.
Add 3% architectural and structural
consultancy fee L.S 46,937.87 Rs.
add for borewell & pumpset L.S 180,000.00 Rs.
Total :- 2,026,222.77 Rs.
Say :- 2,026,220.00 Rs.

IN WORDS -Rupees Twenty Lakh Twenty Six Thousand Two Hundred and Twenty Only