Professional Documents
Culture Documents
DESIGNATION SIGNATURE
Reviewed By HR Head
Issue Status:
S.No Page # Revision Description Reviewed By Approved By
EPCT (PVT) Ltd
WASTE MANAGEMENT
Doc code: EPCT-WMS-001 Page2 of 10 Rev No. 00 Issue Date:30-06-2020
1.0 PURPOSE:
The purpose of this procedure to define the method of waste handling, segregation
and final disposal of waste.
2.0 SCOPE:
3.0 RESPONSIBILITY:
(Reference towards LWG-protocol Section-10, Q# 1-B)
3.1 HODs:
To ensure proper usage of provided wastebins for the purpose.
To maintain the records related to Solid waste on regular basis.
5.0 PROCEDURE:
(Reference towards LWG-protocol Section-10, Q# 1-A)
5.1.5 Calculating the two waste streams on monthly basis according to the
production.
5.2 REDUCTION:
`
5.2.1 Everyone tries to reduce the amount of materials they use, for example, if
double sided photocopying is done, less paper will have to purchase. The
same principles apply to the other material.
5.3 REUSE:
5.3.1 All department / sections try to reuse paper and other material; the volume
of waste to be handled later will be reduced.
5.3.2 If the material cannot be reused for the original purpose because of
quality reasons, perhaps it can be used in some other way. For example, it
may not be possible to reuse a paper tube to ship new product to a
customer. By reusing materials to the maximum extent possible, the
organization is saving resources; cost and valuable land fill space.
5.3.3 Drums which are re-used with in the facility are thoroughly washed in a
designated area in chemical store. The designated area has drainage which
continues towards WWTP.
5.4.1 All section Incharge ensures that all other wastages like electric item,
empty container etc are collected and submitted to Store department.
5.4.2 Sections Incharge ensures that all other wastage is collected and dumped
in the drums / bins available in the department.
Waste Drums:
Waste Godown In charge segregates the all waste drums into different category as mentioned
below) received from the departments with the help of workers and laced in designated waste go
down and prepare the Waste Drum Stock Report.
Scrap:
Waste Go down concern person received all scrap from departments and placed in Scrap yard
and prepares the Scrap Stock Report.
Waste Sale:
Waste Go down In charge prepares the stock report of waste material and provided to the Local Sale
Manager for sale.Local Sale Manager contact with and make the contract of waste of one year or
depending upon the nature of waste.Local Sale Manager maintains the contract of waste.
Record:
Management Representative with the help of departmental Incharge will maintain
the following records.
Inventory of waste
Contracts Record
Waste Quantity
Royal Leather Industries monitors and measures all the specific aspects regarding its
activities like air emission, noise, solid non-hazardous and hazardous waste as
described in the legal and other requirement procedure.
The monitoring is being used for calculating waste streams so the waste cannot
exceed its normal value.
This monitoring is done on major waste streams e.g. Fleshing, trimmings, etc
If any of these waste streams get anomaly (decrease or increase) from its
normal average value, the change should be documented.
EPCT (PVT) Ltd
WASTE MANAGEMENT
Doc code: EPCT-WMS-001 Page6 of 10 Rev No. 00 Issue Date:30-06-2020
The major waste streams which will be used for the calculation of waste generation are;
Wet Blue Trimmings
Crust trimmings
Finished Leather Trims
6.4.1 The data / result are stored with Management Representative who
manages them properly.
The collected data is used to adjust objectives and targets to improve processes and
systems. This requires adjustment based upon the data. The data is recorded in order to
show compliance. The summary of data and actions taken are reported to Management
Representative.
Management Representative will be responsible for taking actions in case of waste and
pollution incidents.
Management Representative will take immediately take action if any kind of incident
happens regarding waste and pollution.
To chemical producing
Chemical Drums Rehmat Ali
3 Industries