Professional Documents
Culture Documents
GT2018-75313
Tore Naess
Consultant
Kongsberg, Norway
The first sale was made in 1968 to the Norwegian Water & 1. Speed/vibration pick ups
Electricity Board (NVE) for the island of Røst in Lofoten, 2. Hirth coupling
almost before the initial testing was completed. The normal 3. Heat shield
electricity supply to Røst was an underwater cable to the 4. Compressor diffuser
nearest island and this was frequently damaged in storms. They 5. Nozzle guide vanes
6. Volute (spiral housing)
were therefore in need of a stand-by generator set which could
7. Fuel nozzles (6 off)
be brought online quickly. 8. Exhaust diffuser
1. Forward journal bearing/thrust bearing The team had not forgotten its first customer NVE either. In
2. Aft journal bearing 1970 there were several small fishing communities in Northern
3. Labyrinth seal Norway which had inadequate power supply. The introduction
4. Compressor inducer of refrigeration plants made the situation difficult and
5. Compressor impeller potentially very costly in case of a power failure. NVE wanted
6. Turbine impeller a unit that they could have stand-by for several of these
7. Turbine exducer communities and the first mobile unit, Fig. 3 was developed
and ready in 1971. NVE bought three of these initially and later
The compressor inducer was investment cast and the
two more to be placed in fishing communities in Northern
impeller section with straight radial blades made from a
Norway as standby engines.
forging, both in a precipitation hardening stainless steel. The
turbine impeller was made from a Nimonic 90 forging whereas
the exducer was investment cast in 713LC. The two sections
were held together with a patented pre-stretched center
bolt/sleeve arrangement [5]. Differences in thermal growth
were allowed by a Hirth coupling (radial tooth coupling). The
turbine wheel and the exducer was also centered with a Hirth
coupling and held together with a sleeve arrangement. The tip
speed of the turbine wheel was in the excess of 500 m/s which
required a material with an optimum combination of creep and
tensile strength.
It did not take long before the base load duty in the rough
North Sea environment revealed the first technical challenges.
In the most hectic period more than 500 change notices were
registered in one year and these had to be implemented in the
whole cycle from parts on order to engines in the field.
Engineers would work day and night trying to understand the
root cause of the various incidents and service people in the
other end would spend weeks offshore in implementing
modifications.
1
See Annex A for data on the various KG2 versions.
1. Air Inlet
2. Centrifugal Compressor, Inducer
3. Centrifugal Compressor, Impeller
4. Compressor Diffuser
5. Outer Casing
6. Combustor
7. Volute
8. Nozzle Guide Vanes FIGURE 6. THE KG5 GAS TURBINE
9. Radial Inflow Turbine & Exducer
10. Axial Turbine, single stage KG5 Key Data
11. Exhaust Diffuser 2-shaft design
All radial gas generator
The primary purpose of the KG5 engine development was to o Single stage centrifugal compressor pressure ratio: 6.5
o Radial inflow turbine
have more than one gas turbine model in the market to be able
o Max speed: 17400 rpm
to offer a wider power range. Due to the higher pressure ratio Single stage axial power turbine
and the 2-shaft configuration it would also have a better Power turbine speed: 12000 rpm
thermal efficiency than the KG2 and be suitable for mechanical Thermal efficiency: ~21.5 %
drive. Four engines were sold before the prototype was ready, ISO power: 3110 kW
but the development testing which started in August 1975, Single tangential can combustor (6 nozzles)
revealed a serious technical issue; exducer blades would break
off in certain test conditions [8]. It took many nights of testing
and analysis before one was finally able to conclude that there 4. PEAK YEARS FOR KG (1976-1979)
was a blade resonance phenomenon caused by excessive 4.1 Worldwide expansion
centrifugal stiffening of the exducer blade. A new casting tool The years from 1976 to 1979 later proved to the peak years in
and new parts had to be made before the development program terms of number of engines sold and delivered. In 1976
could continue. Kongsberg also for the first time became a packager of a gas
turbine from another company. Garrett AiResearch (now part of
The first ordinary shipment took place in 1977 and the KG5 Honeywell International) had developed an industrial gas
fleet had accumulated more than 100 000 hours when in 1982 turbine based on their successful turbo-prop engine TPE331.
another technical issue revealed itself. During witness testing in The engine was called IE831 and had a nominal rating of 500
Kongsberg one engine experienced a high cycle fatigue failure kW. In the Kongsberg product range it was named KG831.
of a single turbine blade. It took more than a year and two more
similar incidents in the field to determine the root cause and Annual number of engines, KG2 and KG831 combined, was
implement corrective actions [9]. It appeared that during between 100 and 120 in this period. In the first half of 1978
unloading the dampening joint between the turbine impeller orders for 109 engines had been received. Sales and Service
and the exducer would loosen due to thermal transients. This were represented “all over the world” ranging from the now
would allow a resonance with the NGV passing frequency to (since 1974) wholly owned subsidiary NATCO (North
become strong enough to cause failure. The corrective action American Turbine Company) in Houston Texas, via OEM
In the partner agreement with Dresser Industries (see below) DC-990 Key Data
they had reserved the right to stop the project if certain 2-shaft design
performance criteria were not met. [13] As described above the Gas generator
o 2-stage centrifugal compressor pressure ratio: ~6
achieved data were lower than specified. Dresser Industries
o 2-stage axial turbine
decided not to cancel the project right away, but reserved the o 12000-18000 rpm
right to do so later, dependent on how the government financing Power turbine
was resolved. This was not resolved to their satisfaction and the o 3-stage axial
project was finally shelved in 1987. o Nom. Speed: 7200 rpm
Thermal Eff. : ~30%
6. CHANGES IN OWNERSHIP (1985-1987) ISO power: 4400 kW
6.1 Partnering with Dresser Industries Annular combustor
KV’s administration was under a lot of pressure from the Board
of Directors when the search for a partner for the gas turbine A new package was developed for the DC-990 and the KG5
activities started in 1981/82. Some twenty different companies test cell was modified such that both DC-990 and KG5 could be
were contacted and with some further negotiations were started tested with only minor re-arrangements. There was an
without result. Dresser Industries (DI) had early been pointed immediate success with the DC-990 with several sales in
out as the most interesting candidate based on their newly Europe, mainly for industrial total energy processes or
acquired IE-990 gas turbine (see below) and their license to municipal district heating, and 1986 became the best year ever
package General Electric (GE) aero-derivative engines. for the sale of the DC-990 with twenty-three engines sold in
total from DI in Olean NY, Houston and Kongsberg.
In January 1985 KV and DI signed a letter of intent and the Unfortunately the DC-990 experienced serious technical issues
21st of June the final “Joint Venture Agreement” was signed. in base load operation to such an extent that Dresser-Rand (see
The new company, Kongsberg Dresser Power Inc. (KDP), was below) gave up and sold the product to Volvo Aero in 1997.
a 50/50 joint venture with equal representation in the Board of
Directors. It was legally headquartered in the former NATCO
office in Houston and had a sales office in Singapore, but the
main part was still in Kongsberg.
On the product side work had been started to upgrade the A project team was quickly established and as there was no
KG2 with a new compressor stage, Fig. 13. The new direct, previous experience with this size of packages they
compressor was to be based on DI compressor know-how, with could start with a blank sheet of paper. This was utilized to
higher pressure ratio and better efficiency. The new version was come up with some new and innovative solutions based on
called the KG2-3E and had a “backward curved” titanium basic gas turbine knowledge and extensive packaging
impeller in one piece. This design improved the surge margin, experience. Fundamental was employing the “torque tube” base
which had been marginal in the original design. It was also plate that IR in UK had developed [14] instead of a more
equipped with a channel diffuser instead of the original plate conventional multi point skid.
diffuser which was cast in bronze segments and had been less
durable than desired. The torque tube, a central tube along the axis of the
machinery, had several advantages. It is a well-known fact that
the cross section that can take the most torque with the smallest
cross section is a tube. In this case it gave a weight reduction of
almost 25% compared to the multipoint skid. It was also
designed as a 3-point mount and rigid enough to make
alignment independent of the platform deck. It also allowed the
auxiliary systems to be placed along the edges of the baseplate
underneath the base plate deck which allowed for easier
maintenance, Fig. 14.
1. Baseplate
2. Gas Generator Turbine (LM2500/LM2500+)
3. VECTRA Power Turbine
Model Year of Base load Efficiency Turbine Pressure Exhaust Turbine Exhaust
Introduction rating speed Ratio mass flow inlet temp. Temp.
(ISO - kW) (LHV- %) (rpm) (kg/s) (Deg. C) (Deg C)
KG2-3 1968 1200 15,4 17 100 3,5 11,4 780 535
KG2-3A 1972 1400 16,1 18 000 3,9 12,8 810 562
1)
KG2-3B - - - 18 000 - - - -
KG2-3C 1973 1530 16,4 18 000 3,9 12,8 830 575
KG2-3D2) ~1980 1890 16,9 18 800 - 13,7 - -
KG2-3E 1987 1950 17,4 18 880 4,5 14,9 830 550
3)
KG2-3F - 1930 28,0 18 880 4,5 14,9 830 550
KG2-3G4) 2013 2100 27,4 25 500 7,0 9,0 1000 580
Notes:
1): KG2-3B had a "wide exit" compressor - never introduced to the market
2): KG2-3D was later designated KG2-SL3 and was a stand-by engine only
3): KG2-3F was meant to be a recuperated version - development never completed
4): KG2-3G is a completely new machine from 2012
ANNEX B. ANNEX C.
KG2 ANNUAL SALES AND ACCUMULATED LARGE GAS TURBINE PACKAGES
ANNUAL SALES AND ACCUMULATED