ITP FOR CONSOLE, INSTRUMENT JB, CONTROL BOX, LPBS, LCS AND FIELD PANELS
MD-216-1000-QD-IX-ITP-1078
PROPRIETARY & CONFIDENTIAL: This document and the information contained herein is Ma’aden and Outotec Oyj/Larsen & Toubro proprietary know-how. This document or any part thereof should not be reproduced,
stored in a retrieval system or transmitted by any means, electronic or otherwise, or divulged without prior written permission from Ma’aden and Outotec Oyj/Larsen & Toubro.
Inspection and Test Plan (ITP) No: Related requirements reference, when applicable
O19045_001_X_K_00501_701_R0 (Manufacturing/installation/specification/design):
MD-101-SMEM-EG-EL-SPC-0001-C01
MD-101-SMEM-EG-EL-SPC-0011-C01
MD-101-SMEM-EG-IN-SPC-0001-C01
QVD-E0001, E0047, E0048
Project: Mansourah Massarah Gold Project Contract No/ Title: 17-PME MM GP-0002 / DP-190009 Maaden gold
Sub-contractor Name/Contact Details: Equipment/ Work Package/ Activity Description:
SENDAN INTERNATIONAL COMPANY LTD. ITP FOR INSTALLATION OF CONSOLE, INSTRUMENT JB, CONTROL BOX, LPBS, LCS AND FIELD
PANELS
Remarks: P – Performance, Executing an activity
H – Hold Point, a point beyond which work shall not proceed without
inspection/approval of representative of indicated party
W – Witness Point, representative of indicated party must be notified, if not in
attendance at specified time, inspection may proceed
S – Surveillance, representative of indicated party may carry out surveillance of
work in progress
R – Review, representative of indicated party to review submitted documents,
result of tests etc.
Page: 1
MD-216-1000-QD-IX-ITP-1078-A01 Page 3 of 9
Sub- Contractor
Frequency of
Inspection /
Contractor
Employer
Acceptance Criteria /
Process Description
Test
S.N Responsible Inspection or Test Method Specification / QC Record Reference
or QC activity
Drawing
Page: 2
MD-216-1000-QD-IX-ITP-1078-A01 Page 4 of 9
Sub- Contractor
Frequency of
Inspection /
Contractor
Employer
Acceptance Criteria /
Process Description
Test
S.N Responsible Inspection or Test Method Specification / QC Record Reference
or QC activity
Drawing
L&T-MMGP-IRF-001 MATERIAL RECEIVING INSPECTION REQUEST FORM / WORK INSPECTION REQUEST FORM
Page: 3
MD-216-1000-QD-IX-ITP-1078-A01 Page 5 of 9
REFERENCE DOCUMENT
DRAWING No. :
SPECIFICATION No. :
Witness Hold
ADDITIONAL INFORMATION/COMMENTS:
QVD NO SEN-QVD-E0001
FINAL INSPECTION AND ACCEPTANCE
ITP NO MD-216-1000-QD-IX-ITP-1078_A01
Acceptable Criteria
Item Description of Check
YES NO N/A
01 All installation activities completed.
Review and Approval Status: Comments:
Approved
Approved with Comments
Disapproved
Name
Sign
Date
QVD NO QVD-E0047
INSTRUMENT PANELS INSTALLATION INSPECTION
CHECKLIST ITP NO MD-216-1000-QD-IX-ITP-1078_A01
Acceptable Criteria
Item Description of Check
YES NO N/A
Check all drawings and documents used for the installation are in
1
the final edition.
Check panel typical installation details in accordance with
2
approved design drawings.
Nameplate securely attached, readable not obscured and
3 nameplate data conforms to the information given on the data
sheet.
Check mounting location and clearances between the unit and
4
any equipment.
Check orientation and alignment of installed panel in reference
5
to approved IFC drawings.
Ensure that instrument panel installation is mounted on brackets
6 fixed to steel work or on a suitable stand that are not subject to
movement.
Ensure Panels have been properly secured to protect against
7
operational damage.
Check for damage / defects occurred during transportation,
8 storage, handling and installation. Ensure no damage to the
protective coating after installation
Ensure the Installed panel are neat and installed with a good
9
workmanship.
Check Panel does not obstruct maintenance access and
walkways
Review and Approval Status: Comments:
Approved
Approved with Comments
Disapproved
Name
Sign
Date
1|Page
MD-216-1000-QD-IX-ITP-1078-A01 Page 8 of 9
Acceptable Criteria
Item Description of Check
YES NO N/A
1 The construction drawings and documents are the final edition.
All equipment and materials supplied shall be new, free of flaws, and of
2
the highest quality.
The location and mounting height shall be selected so that the LPBS /
3
LCS is readily accessible for switching.
Check LPBS / LCS installation in accordance with approved design
4
drawings.
LPBS / LCS Mounting plates, and brackets are free of burrs and sharp
5 edges and have adequate space to attach equipment identification and
descriptor labels.
6 LPBS / LCS are Installed in a neat and workmanlike manner.
LPBS / LCS location is readily accessible and exposed to damage from
7
maintenance activities or passing traffic.
LPBS / LCS are located adjacent to, or within a prescribed distance from
8 the motor being controlled and in a position that provides a clear view
of the motor.
LPBS / LCS are located such that an Operator is not exposed to acidic,
9
corrosive or other spray from operating hazards.
LPBS / LCS are installed on solid foundations that are not subject to
10
movement.
11 LPBS / LCS are rated at IP65 minimum for all outdoor installations
LPBS / LCS are visually inspected for damage / defects occurred after
12 installation. Check no damage to the protective coating after
installation. Check Panel does not obstruct maintenance access and
Review and approval status: walkways Comments:
Approved
Approved with comments
Disapproved
Name
Signature
Date
1|Page
MD-216-1000-QD-IX-ITP-1078-A01 Page 9 of 9
REFERENCE DOCUMENTS
DRAWING NO.
SPECIFICATION NO.
TYPE OF INSPECTION
ACTIVITY TO BE INSPECTED LOCATION
(Tick as Applicable)
Witness Hold
EMPLOYER
(Print Name & Sign): Date:
NOTE:
1. This document shall not be used to specify acceptance of the aspects of test; this can only be achieved by sign off of appropriate inspection report
which shall be attached hereto.
2. L&T inspection shall occur only after the inspection report is signed off by Contractor Representative conforming acceptance of the work.
ADDITIONAL INFORMATION: COMMENTS:
DATE:
REVIEWED BY L&T QC (Print Name & Sign)
DATE:
EMPLOYER REPRESENTATIVE (Print Name & Sign)