Job safety analysis Electrical Distribution Board Maintenance (DB)

L-FRM-065

Date: 02/04/2023 Job safety analysis


Electrical Distribution Board Maintenance People In Danger Number:
Contractor,.
Title: J S A
(DB) Task Routine  Non-Routine

Risk Rating Residual Risk


Activity Hazard(s) Consequence (s) Control Measure(s) (H/M/L)
(H/M/L)

 Non – compliance of
KOC F & S  Follow Lock- Out/ Tag- Out procedure
Regulations and HSE  Obtain PTW
MS Procedures  Electrician with LOTO training
 Planning  Insulated tools to be used
 Electricity  Tools to be inspected before use/ do not use
 Defective Measuring defective tools. Use only for purpose they intended
tools  Electrocution  Measuring equipment to be calibrated
 Electric hazards from  Serious injuries/  Power tools to be periodically PAT Tested and
 Inspect cable insulations exposed wirings/ faulty fatality serviced
for signs of overheating/ powered tools  Arc Flash High  Powered tools must be inspected on daily basis prior Low
Conduit /equipment /electrics. to its use to ensure free from casing /electric faults.
 Slip & Trip Damaged cords, plugs, moving and rotatory parts
 must be equipped with appropriate guards. All
powered must be double insulated.
 Method statement, risk assessment to covered in
task briefing
 Emergency procedures in place, and HSE induction
for staff.

L-FRM-065 07/2018, Rev. 01 Page


1 of 4
Job safety analysis Electrical Distribution Board Maintenance (DB)
L-FRM-065

 Ensure access /egress is clear without any


obstructions
Ensure the isolation of
 Materials & tools not to be let unattended whilst
 Inspect cable gland electrical power before
Electric Shock maintenance.
Scattered material replacing the fuse. High Low
 Adequate level of lighting.
Use insulated hand  Provision of appropriate type of Fire extinguishers
gloves & safety shoe. (i.e Co2 and DCP) with valid inspection records.
Safety shoes, Safety Glass and safety gloves.

 Check burs and visible signs of overheating and


loose connection.
Overheating and loose  Uninsulated cable
 terminations for
connection and signs of  Check MCB for damage and free operation of
tightness HIGH switching mechanism.
 Clearing DB Damage MCB and overheating.
switches

 Do not stand close to the live electrical parts.


 The distance should be maintained so that only the
hands can reach to the equipment.
 Electrocution  Risk assessment and method statement to be briefed
 Electricity  Serious injuries/ to the technicians
Test RCD function HIGH
Defective Equipment fatality  Manufactures instruction of RCD tester to be made
Arc Flash available for reference.
 Only Technically competent electrician.
 RCD tester to be calibrated.
 Electrical gloves, safety shoes and eye protection to
be used.
Windup & Housekeeping Scattered Material SLIP TRIP AND FALL LOW  Ensure proper wind up & housekeeping at
worksite.

L-FRM-065 07/2018, Rev. 01 Page


2 of 4
Job safety analysis Electrical Distribution Board Maintenance (DB)
L-FRM-065

 Normalize safety override after evaluating the


risk.
Close the permit & associated permits / certificates.

Personal Protective Equipment to be Used (insert Picture(s))

Number: KFM/LE/EL/01

Assessed By Reviewed By Approved By


Name ASLAM MULANI Name MOHAMMAD ZAFAR IQBAL Name Name
Designation Designation Designatio Designation
n
Signature Signature Signature Signature
Date Date Date Date
Declaration by employee involved in the activity detailed above - I fully understand the activity outlined above and the risk control measures that I must implement,
use, or wear. I have received sufficient information, instruction and training so as to enable me to conduct this activity with the minimum of risk to myself, or others.

Operative Name: Signature: Supervisors Name: Date: Operative Name: Signature: Supervisors Name: Date:

L-FRM-065 07/2018, Rev. 01 Page


3 of 4
Job safety analysis Electrical Distribution Board Maintenance (DB)
L-FRM-065

L-FRM-065 07/2018, Rev. 01 Page


4 of 4