L-FRM-065
Non – compliance of
KOC F & S Follow Lock- Out/ Tag- Out procedure
Regulations and HSE Obtain PTW
MS Procedures Electrician with LOTO training
Planning Insulated tools to be used
Electricity Tools to be inspected before use/ do not use
Defective Measuring defective tools. Use only for purpose they intended
tools Electrocution Measuring equipment to be calibrated
Electric hazards from Serious injuries/ Power tools to be periodically PAT Tested and
Inspect cable insulations exposed wirings/ faulty fatality serviced
for signs of overheating/ powered tools Arc Flash High Powered tools must be inspected on daily basis prior Low
Conduit /equipment /electrics. to its use to ensure free from casing /electric faults.
Slip & Trip Damaged cords, plugs, moving and rotatory parts
must be equipped with appropriate guards. All
powered must be double insulated.
Method statement, risk assessment to covered in
task briefing
Emergency procedures in place, and HSE induction
for staff.
Number: KFM/LE/EL/01