Professional Documents
Culture Documents
Hazard Identification & Risk Assessment Sheet for Earthing and Bounding System
Project Design & Build Of 5 Nos. Of Warehouses Buildings Phase 06-A (TIP)
Page 1 of 10
HAZARD IDENTIFICATION AND RISK ASSESSMENT SHEET
Hazard Identification & Risk Assessment Sheet for Earthing and Bounding System
Project Design & Build Of 5 Nos. Of Warehouses Buildings Phase 06-A (TIP)
Page 2 of 10
HAZARD IDENTIFICATION AND RISK ASSESSMENT SHEET
Hazard Identification & Risk Assessment Sheet for Earthing and Bounding System
Project Design & Build Of 5 Nos. Of Warehouses Buildings Phase 06-A (TIP)
Page 3 of 10
HAZARD IDENTIFICATION AND RISK ASSESSMENT SHEET
Hazard Identification & Risk Assessment Sheet for Earthing and Bounding System
Project Design & Build Of 5 Nos. Of Warehouses Buildings Phase 06-A (TIP)
• Certified/competent operator.
• Certified earth auger machine,
• Underground services will be identified and
protect prior to start the drilling.
• Effective supervision throughout the task,
Untrained operator, • Prestart job briefing,
Injury to
Using of earth Machine/mechanic- • Appropriate PPE’s will be worn.
6 auger machine for al failure, personnel, 3 3 9 • PTW will be followed. 1 3 3
Property
pit Underground • Pre-start task detail inspection will be
services, damage
conducted by the competent person.
• Area will be barricaded and warning signs
will be placed.
• All lifting gears will be inspected and certified
by 3rd party if applicable.
•
Page 4 of 10
HAZARD IDENTIFICATION AND RISK ASSESSMENT SHEET
Hazard Identification & Risk Assessment Sheet for Earthing and Bounding System
Project Design & Build Of 5 Nos. Of Warehouses Buildings Phase 06-A (TIP)
Page 5 of 10
HAZARD IDENTIFICATION AND RISK ASSESSMENT SHEET
Hazard Identification & Risk Assessment Sheet for Earthing and Bounding System
Project Design & Build Of 5 Nos. Of Warehouses Buildings Phase 06-A (TIP)
Page 6 of 10
HAZARD IDENTIFICATION AND RISK ASSESSMENT SHEET
Hazard Identification & Risk Assessment Sheet for Earthing and Bounding System
Project Design & Build Of 5 Nos. Of Warehouses Buildings Phase 06-A (TIP)
Page 7 of 10
HAZARD IDENTIFICATION AND RISK ASSESSMENT SHEET
Hazard Identification & Risk Assessment Sheet for Earthing and Bounding System
Project Design & Build Of 5 Nos. Of Warehouses Buildings Phase 06-A (TIP)
Page 8 of 10
HAZARD IDENTIFICATION AND RISK ASSESSMENT SHEET
Hazard Identification & Risk Assessment Sheet for Earthing and Bounding System
Project Design & Build Of 5 Nos. Of Warehouses Buildings Phase 06-A (TIP)
When completing this Performa, you must take due consideration of local conditions, including adjacent operations and premises.
Page 9 of 10
HAZARD IDENTIFICATION AND RISK ASSESSMENT SHEET
Hazard Identification & Risk Assessment Sheet for Earthing and Bounding System
Project Design & Build Of 5 Nos. Of Warehouses Buildings Phase 06-A (TIP)
RISK MATRIX
Use the Risk Matrix to Determine the Risk Rating (Rank)
What is the PROBABILITY (P) of an occurrence? Hierarchy of Controls
What would the SEVERITY (S)
of an occurrence be? Almost
Very Unlikely Unlikely Possible Likely - Can the hazard be Eliminated or removed from the work
Certain
place?
Very High
- Can the product or process be Substituted for a less
Fatalities/Perm Total Disability
5 5 10 15 20 25 hazardous alternative?
Irreversible significant environmental impact
- Can the hazard be Engineered away with guards or barriers?
Loss more than AED 10M
- Can Administrative Controls be adopted
High
(Safe Work Procedure, job rotation, warning devices, etc.)
Perm partial disability
4 4 8 12 16 20 - Can Personal Protective Equipment & Clothing be worn to
Reversible significant environmental impact
safeguard against hazards?
Loss AED 5M - 10M
Medium
Injury / illness = more than 5 work day loss
3 3 6 9 12 15
Reversible moderate environmental impact
16 - 25 Very High Risk Unacceptable
Loss AED 1M – 5M
Low
9 - 15 High Risk Undesirable
Injury / illness = 1 or more day loss
2 2 4 6 8 10
Reversible moderate environmental impact
Loss AED100K – 1M 5-8 Medium Risk Caution
Very Low
3-4 Low Risk Tolerable
Injury / illness = no lost day
1 1 2 3 4 5
Nuisance release with no adverse impact
Loss less than AED100K 1-2 Very Low Risk Acceptable
1 2 3 4 5
Page 10 of 10