You are on page 1of 9

INDICATIVE CABLE WAY ROUTE

“MSC MILA III”

MSC Ship Management


(Cyprus) Ltd

SHD 128735 01.06.22

SKP DN12278 08

TRK DN12278/5008 B
INDICATIVE CABLE WAY ROUTE MSC MILA III

REVISION HISTORY
UID REV DATE DESCRIPTION PRE CHK APR

114969 A 10.12.21 ISSUED FOR REVIEW SHD SKP TRK

128735 B 01.06.22 BWT SYSTEM CHANGED SHD SKP TRK

Notes:-
1. “W.T COAMING” location is to be verified before installation.
2. Yard to utilize the existing cable trays for routing cables. Wherever new routing is required yard
have to add new cable trays locally to suit to site.
3. Drawing provided with cable routing is indicative in nature which is only used for cable
estimation purpose
4. Refer cable schedule (Dwg.No: DN12278_5005_ELECTRICAL CABLE SCHEDULE) for cable
details.
5. Power & signal cables are to be segregated separately by minimum 50mm.
6. From MSB (ECR) to new BWTS equipment in Engine Room platform-I deck, the cable to be laid
with the existing cable tray routes and penetration. We presumed that existing cable tray &
penetration have sufficient spare space in order to accommodate new BWTS cable.
7. We proposed to use existing coaming for BWTS cable laying. If existing coaming is not sufficient
new coaming needs to be introduced inside the accommodation area and opening to be filled with
class approved type compound.
8. Proposing to lay cables between Transformer rectifier and electrolytic cell (cable size 1x95 mm2),
in such a way that that the cable length between the same equipments is not more than 25 meters
for individual cables.
9. All coaming to be filled with class approved type sealing compound.
10. The Erma supplied cable from flow switch (FSA-BWTS-01)to BWTS control panel to be arranged
in such a way that the cable length not exceeds more than 10 meters.

Reference Document:-
1. Document name :- GENERAL ARRANGEMENT
Drawing no :- 8111-DZ/0110-001
Date :- 94-12-01
2. Document name :- ENGINE ROOM ARRANGEMENT
Drawing no :- 8111-DZ/40400-001
Date :- 94-09-14
3. DN12278_2001_BWTS EQUIPMENT LAYOUT_ERMA FIRST 1x400M3/HR_REV.B
INDICATIVE CABLE WAY ROUTE MSC MILA III

Legend:-
BWTS EQUIPMENTS : -
COAMING : -
CABLE WAY : -
CABLE WAY UPWARD : -
CABLE WAY DOWNWARD : -
PROPOSING TO USE EXISTING COAMING
FOR CABLES FROM MAIN DECK TO POOP
DN DECK. SUITABLE CUTOUT TO BE
INTRODUCED AS SUIT AT SITE IF REQUIRED.

APPROXIMATE LOCATION
OF REPEATER PANEL

SHIP OFFICE
UP PROPOSING TO USE EXISTING COAMING
FOR CABLES FROM AND TO MAIN DECK.
SUITABLE CUTOUT TO BE INTRODUCED AS
SUIT AT SITE IF REQUIRED.
DN
PROPOSING TO USE EXISTING COAMING
FOR CABLES FROM PLATFORM-II DECK TO
TWEEN DECK. SUITABLE CUTOUT TO BE
INTRODUCED AS SUIT AT SITE IF
REQUIRED.
DN

BWTS CABLES FROM


TWEEN DECK TO MAIN
DECK UP
MAIN SWITCH BOARD
APPROXIMATE LOCATION

DN PROPOSING TO USE EXISTING COAMING FOR


CABLES FROM PLATFORM-II DECK TO
PLATFORM-I DECK. SUITABLE CUTOUT TO BE
INTRODUCED AS SUIT AT SITE IF REQUIRED.

BWTS CABLES FROM AND UP


TO PLATFORM-II DECK
DAP-3 ELECTROLYTIC CELL FILTER

BWTS CABLES FROM PLATFORM-I DECK


UP TO PLATFORM-II DECK. SUITABLE
CUTOUT TO BE INTRODUCED AS SUIT
AT SITE IF REQUIRED.
TROS-1

TROS-2
DAP-2

NEW PDB

DAP-1
NAT

CABLES FROM PLATFORM-I


DN DECK TO FLOOR.
FILTER STARTER
PANEL

TRANSFORMER
RECTIFIER

CONTROL
PANEL
SEA WATER
PUMP

CABLES FROM
AND TO FLOOR.

UP

SEA WATER PUMP


STARTER PANEL

You might also like