SUBJECT : DEDUCTION OF UNINSTALLED ITEMS BASED ON THE BILL OF QUANTITIES CONTRACT OF MONOCRETE
DATE : March 23, 2023
Room 601 Repaired floor drain and Shower drain stubout clog-up due to mortar inside the pvc pipe. Needs
repair for temporary ceiling opening & install cover for permanent ceiling opening.
Room 1012 Repaired kitchen sink stubout clog-up due to mortar inside the pvc pipe.
Room 2207 Repaired lavatory waterline leak due to installation of tiles hit by concrete nail.
23rd Floor Elevator lobby/ hallway Repaired floor drain and shower drain stubout clog-up due to mortar
inside the pvc pipe . Needs repair for temporary ceiling opening.
27th Floor Elevator lobby/ hallway Repaired water leak due to welded B.I pipe joint after testing of fire
protection. Needs repair for temporary ceiling opening.
28th Floor Elevator lobby/ hallway Repaired floor drain and shower drain stubout clog up due to mortar
inside the pvc pipe . Needs repair for temporary ceiling opening.
30th Floor Elevator lobby/ hallway Repaired water leak due to welded B.I pipe joint after testing of fire
protection. Needs repair for temporary ceiling opening.
Room 3001 Repaired Kitchen sink stubout clog-up due to mortar inside the pvc pipe.
Room 601 Repaired floor drain and Shower drain stubout clog-up due to mortar inside the pvc pipe. Needs Sq. M.
repair for ceiling opening. 1.00
Room 602 Repaired shower drain and kitchen sink stubout clog-up due to mortar inside the pvc pipe. 1.00 Sq. M.
Needs repair for ceiling opening.
Room 603 Repaired shower drain stubout clog-up due to mortar inside the pvc pipe. Needs repair for 1.00 Sq. M.
ceiling opening.
Room 604 Repaired floor drain stubout clog-up due to mortar inside the pvc pipe. Needs repair for ceiling 1.00 Sq. M.
opening.
Room 605 Repaired shower drain stubout clog-up due to mortar inside the pvc pipe. Needs repair for 1.00 Sq. M.
ceiling opening.
Room 606 Repaired floor drain and Shower drain stubout clog-up due to mortar inside the pvc pipe. Needs Sq. M.
repair for ceiling opening. 1.00
Room 607 Repaired floor drain and Shower drain stubout clog-up due to mortar inside the pvc pipe. Needs
repair for ceiling opening. 1.00 Sq. M.
Room 608 Repaired shower drain stubout clog-up due to mortar inside the pvc pipe. Needs repair for 1.00 Sq. M.
ceiling opening.
Room 609 Repaired floor drain and Shower drain stubout clog-up due to mortar inside the pvc pipe. Needs
repair for ceiling opening. 1.00 Sq. M.
Room 610 Repaired shower drain stubout clog-up due to mortar inside the pvc pipe. Needs repair for Sq. M.
ceiling opening. 1.00
Room 611 Repaired shower drain stubout clog-up due to mortar inside the pvc pipe. Needs repair for 1.00 Sq. M.
ceiling opening.
Room 612 Repaired floor drain and Shower drain stubout clog-up due to mortar inside the pvc pipe. Needs
repair for ceiling opening. 1.00 Sq. M.
Room 701 Repired kitchen sink stubout clog-up and water seepage due to mortar inside the pvc pipe. 1.00 Sq. M.
Needs repair for ceiling opening.
Room 704 Repaired shower drain stubout clog-up due to mortar inside the pvc pipe. Needs repair for 1.00 Sq. M.
ceiling opening.
Room 705 Repaired floor drain stubout clog-up due to mortar inside the pvc pipe. Needs repair for ceiling 1.00 Sq. M.
opening.
Room 706 Repaired floor drain and Shower drain stubout clog-up due to mortar inside the pvc pipe. Needs
repair for ceiling opening. 1.00 Sq. M.
Room 711 Repaired shower drain stubout clog-up due to mortar inside the pvc pipe. Needs repair for 1.00 Sq. M.
ceiling opening.
Room 712 Repaired shower drain stubout clog-up due to mortar inside the pvc pipe. Needs repair for 1.00 Sq. M.
ceiling opening.
Room 801 Repaired floor drain and Shower drain stubout clog-up due to mortar inside the pvc pipe. Needs
repair for ceiling opening. 1.00 Sq. M.
Room 802 Repaired kitchen sink stubout clog-up due to mortar inside the pvc pipe and waterline leak due
to wall angle hit by screw. Needs repair for ceiling opening.
1.00 Sq. M.
Room 805 Repaired waterline leak due to metal furring hit by screw. Needs repair for ceiling opening. 1.00 Sq. M.
Room 806 Repaired floor drain stubout clog-up due to mortar inside the pvc pipe. Needs repair for ceiling 1.00 Sq. M.
opening.
Room 809 Repaired floor drain stubout clog-up due to mortar inside the pvc pipe. Needs repair for ceiling 1.00 Sq. M.
opening.
Room 811 Repaired floor drain stubout clog-up due to mortar inside the pvc pipe. Needs repair for ceiling 1.00 Sq. M.
opening.
Room 812 Repaired kitchen sink waterline leak due to ceiling wall angle hit by screw. Needs repair for 1.00 Sq. M.
ceiling opening.
Room 901 Repaired shower drain stubout clog-up due to mortar inside the pvc pipe. Needs repair for 1.00 Sq. M.
ceiling opening.
Room 902 Repaired shower drain stubout clog-up due to mortar inside the pvc pipe. Needs repair for 1.00 Sq. M.
ceiling opening.
Room 904 Repaired shower drain stubout clog-up due to mortar inside the pvc pipe. Needs repair for 1.00 Sq. M.
ceiling opening.
Room 905 Repaired kitchen sink stubout clog-up due to mortar inside the pvc pipe. Needs repair for ceiling 1.00 Sq. M.
opening.
Room 906 Repaired shower drain stubout clog-up due to mortar inside the pvc pipe. Needs repair for 1.00 Sq. M.
ceiling opening.
Room 907 Repaired floor drain and shower drain stubout clog-up due to mortar inside the pvc pipe. Needs
repair for ceiling opening. 1.00 Sq. M.
Room 907 Repaired kitchen sink waterline leak due to installation of pvc conduit pipe hit during by
chipping works. Needs repair for ceiling opening.
1.00 Sq. M.
Room 908 Repaired floor drain stubout clog-up due to mortar inside the pvc pipe. Needs repair for ceiling 1.00 Sq. M.
opening.
Room 909 Repaired shower drain stubout clog-up due to mortar inside the pvc pipe and kitchen sink water
supply due to wall angle hit by screw. Needs repair for ceiling opening.
1.00 Sq. M.
Room 911 Repaired floor drain stubout clog-up due to mortar inside the pvc pipe. Needs repair for ceiling 1.00 Sq. M.
opening.
Room 1003 Repaired shower drain stubout clog-up due to mortar inside the pvc pipe. Needs repair for 1.00 Sq. M.
ceiling opening.
Room 1005 Repaired shower drain and kitchen sink stubout clog-up due to mortar inside the pvc pipe.
Needs repair for ceiling opening. 1.00 Sq. M.
Room 1006 Repaired floor drain stubout clog-up due to mortar inside the pvc pipe. Needs repair for ceiling 1.00 Sq. M.
opening.
Room 1007 Repaired floor drain stubout clog-up due to mortar inside the pvc pipe. Needs repair for ceiling 1.00 Sq. M.
opening.
Room 1008 Repaired floor drain stubout clog-up due to mortar inside the pvc pipe and lavatory water leak
hit by concrete nail after installation of tiles. Needs repair for ceiling opening.
1.00 Sq. M.
Room 1012 Repaired kitchen sink stubout clog-up due to mortar inside the pvc pipe. Needs repair for
ceiling opening. 1.00 Sq. M.
Room 1101 Repaired shower drain and kitchen sink stubout clog-up due to mortar inside the pvc pipe. 1.00 Sq. M.
Needs repair for ceiling opening.
Room 1103 Repaired shower drain stubout clog-up due to mortar inside the pvc pipe. Needs repair for 1.00 Sq. M.
ceiling opening.
Room 1105 Repaired shower drain stubout clog-up due to mortar inside the pvc pipe and kitchen sink
waterline leak due to metal furring hit by screw. Needs repair for ceiling opening.
1.00 Sq. M.
Room 1106 Repaired shower drain stubout clog-up due to mortar inside the pvc pipe and kitchen sink
water leak due to water proofing seepage. Needs repair for ceiling opening.
1.00 Sq. M.
Room 1107 Repaired floor drain and Shower drain stubout clog-up due to mortar inside the pvc pipe.
Needs repair for ceiling opening. 1.00 Sq. M.
Room 1108 Repaired floor drain stubout clog-up due to mortar inside the pvc pipe. Needs repair for ceiling 1.00 Sq. M.
opening.
Room 1109 Repaired shower drain stubout clog-up due to mortar inside the pvc pipe. Needs repair for 1.00 Sq. M.
ceiling opening.
Room 1112 Repaired shower drain stubout clog-up due to mortar inside the pvc pipe. Needs repair for 1.00 Sq. M.
ceiling opening.
Room 1206 Repaired watercloset waterline leak hit by concrete nail after installation of tiles. Tile repaired 1.00 Sq. M.
by Owner.
Room 1207 Repaired kitchen sink stubout clog-up due to mortar inside the pvc pipe and waterline leak
due to wall angle hit by screw. Needs repair for ceiling opening.
1.00 Sq. M.
Room 1209 Repaired kitchen sink stubout clog-up due to mortar inside the pvc pipe. Needs repair for 1.00 Sq. M.
ceiling opening.
Room 1210 Repaired floor drain stubout clog-up due to mortar inside the pvc pipe. Needs repair for ceiling 1.00 Sq. M.
opening.
Room 1212 Repaired shower drain stubout clog-up due to mortar inside the pvc pipe and kitchen sink
water leak due to water proofing seepage. Needs repair for ceiling opening.
1.00 Sq. M.
Room 1401 Repaired floor drain stubout clog-up due to mortar inside the pvc pipe. Needs repair for ceiling 1.00 Sq. M.
opening.
Room 1403 Repaired floor drain stubout clog-up due to mortar inside the pvc pipe. Needs repair for ceiling 1.00 Sq. M.
opening.
Room 1405 Repaired kitchen sink waterline leak due to metal furring hit by screw. Needs repair for ceiling 1.00 Sq. M.
opening.
Room 1407 Repaired shower drain stubout clog-up due to mortar inside the pvc pipe. Needs repair for 1.00 Sq. M.
ceiling opening.
Room 1409 Repaired shower drain and kitchen sink stubout clog-up due to mortar inside the pvc pipe.
Needs repair for ceiling opening. 1.00 Sq. M.
Room 1410 Repaired kitchen sink stubout clog-up due to mortar inside the pvc pipe and water leak due to
water proofing seepage. Needs repair for ceiling opening.
1.00 Sq. M.
Room 1411 Repaired floor drain stubout clog-up due to mortar inside the pvc pipe and kitchen sink area of
water proofing seepage. Needs repair for ceiling opening.
1.00 Sq. M.
Romm 1412 Repaired kitchen sink stubout clog-up due to mortar inside the pvc pipe and water leak due to
water proofing seepage. Needs repair for ceiling opening.
1.00 Sq. M.
Room 1501 Repaired floor drain stubout clog-up due to mortar inside the pvc pipe. Needs repair for ceiling
opening. 1.00 Sq. M.
Room 1504 Repaired kitchen sink stubout clog-up due to mortar inside the pvc pipe. Needs repair for
ceiling opening. 1.00 Sq. M.
Room 1507 Repaired kitchen sink stubout clog-up due to mortar inside the pvc pipe. Needs repair for
ceiling opening. 1.00 Sq. M.
Room 1508 Repaired kitchen sink stubout clog-up due to mortar inside the pvc pipe. Needs repair for
ceiling opening. 1.00 Sq. M.
Room 1509 Repaired watercloset waterline leak hit by concrete nail after installation of tiles. Tile repaired
by Owner. 1.00 Sq. M.
Room 1602 Repaired floor drain stubout clog-up due to mortar inside the pvc pipe. 1.00 Sq. M.
Needs repair for ceiling opening.
Room 1603 Repaired kitchen sink waterline leak due to metal furring hit by screw. Needs repair for ceiling
opening. 1.00 Sq. M.
Room 1606 Repaired shower drain stubout clog-up due to mortar inside the pvc pipe. Needs repair for 1.00 Sq. M.
ceiling opening.
Room 1607 Repaired shower drain and kitchen sink stubout clog-up due to mortar inside the pvc pipe and
water proofing seepage. Needs repair for ceiling opening.
1.00 Sq. M.
Room 1608 Repaired shower drain stubout clog-up due to mortar inside the pvc pipe and water proofing
seepage. Needs repair for ceiling opening.
1.00 Sq. M.
Room 1611 Repaired kitchen sink stubout clog-up due to mortar inside the pvc pipe.Needs repair for
ceiling opening. 1.00 Sq. M.
Room 1702 Repaired kitchen sink waterline leak due to metal furring hit by screw. Needs repair for ceiling
opening. 1.00 Sq. M.
Room 1703 Repaired shower drain and kitchen sink stubout clog-up due to mortar inside the pvc pipe.
Needs repair for ceiling opening. 1.00 Sq. M.
Room 1705 Repaired floor drain and kitchen sink stubout clog-up due to mortar inside the pvc pipe. Needs
repair for ceiling opening. 1.00 Sq. M.
Room 1707 Repaired shower drain stubout clog-up due to mortar inside the pvc pipe. Needs repair for
ceiling opening. 1.00 Sq. M.
Room 1708 Repaired floor drain stubout clog-up due to mortar inside the pvc pipe. Needs repair for ceiling
opening. 1.00 Sq. M.
Room 1709 Repaired kitchen sink stubout clog-up due to mortar inside the pvc pipe and water leak due to
water proofing seepage. Needs repair for ceiling opening.
1.00 Sq. M.
Room 1710 Repaired floor drain stubout clog-up due to mortar inside the pvc pipe. Needs repair for ceiling Sq. M.
opening. 1.00
Room 1712 Repaired kitchen sink stubout clog-up due to mortar inside the pvc pipe. Needs repair for
ceiling opening. 1.00 Sq. M.
Room 1802 Repaired kitchen sink stubout clog-up due to mortar inside the pvc pipe. Needs repair for
ceiling opening. 1.00 Sq. M.
Room 1805 Repaired floor drain and Shower drain stubout clog-up due to mortar inside the pvc
pipe.Needs repair for ceiling opening. 1.00 Sq. M.
Room 1809 Repaired floor drain stubout clog-up due to mortar inside the pvc pipe and water leak due to
water proofing seepage. Needs repair for ceiling opening.
1.00 Sq. M.
Room 1812 Repaired kitchen sink stubout clog-up due to mortar inside the pvc pipe and water leak due to
water proofing seepage, and lavatory waterline leak due to installation of tiles hit by concrete nail. Needs
repair for ceiling opening.
1.00 Sq. M.
Room 1901 Repaired floor drain stubout clog-up due to mortar inside the pvc pipe. Needs repair for ceiling
opening. 1.00 Sq. M.
Room 1903 Repaired of Shower hot and cold waterline supply due to installation of ppr pipe clog-up. Need
for chipping works, Plaster and re-installation of wall tile.
1.00 Sq.m
Room 1907 Repaired floor drain stubout clog-up due to mortar inside the pvc pipe. Needs repair for ceiling
opening. 1.00 Sq. M.
Room 1908 Repaired floor drain stubout clog-up due to mortar inside the pvc pipe and water leak due to
water proofing seepage. Needs repair for ceiling opening.
1.00 Sq. M.
Room 1911 Repaired floor drain and shower drain stubout clog-up due to mortar inside the pvc pipe.
Needs repair for ceiling opening. 1.00 Sq. M.
Room 1912 Repaired floor drain stubout clog-up due to mortar inside the pvc pipe and water leak due to
water proofing seepage. Needs repair for ceiling opening.
1.00 Sq. M.
Room 2001 Repaired floor drain stubout clog-up due to mortar inside the pvc pipe, water leak due to
water proofing seepage and Repaired kitchen sink stubout clog-up due to mortar inside the pvc pipe.
Needs repair for ceiling opening.
1.00 Sq. M.
Room 2003 Repaired floor drain stubout clog-up due to mortar inside the pvc pipe. Needs repair for ceiling
opening. 1.00 Sq. M.
Room 2010 Repaired floor drain and shower drain stubout clog-up due to mortar inside the pvc pipe and
water leak due to water proofing seepage. Needs repair for ceiling opening.
1.00 Sq. M.
Room 2011 Repaired floor drain and shower drain stubout clog-up due to mortar inside the pvc pipe.
Needs repair for ceiling opening. 1.00 Sq. M.
Room 2102 Repaired floor drain stubout clog-up due to mortar inside the pvc pipe and water leak due to
water proofing seepage. Needs repair for ceiling opening.
1.00 Sq. M.
Room 2104 Repaired Kitchen sink stubout clog-up due to mortar inside the pvc pipe. Needs repair for
ceiling opening. 1.00 Sq. M.
Room 2105 Repaired Kitchen sink stubout clog-up due to mortar inside the pvc pipe. Needs repair for Sq. M.
ceiling opening. 1.00
Room 2106 Repaired Kitchen sink stubout clog-up due to mortar inside the pvc pipe. Needs repair for
ceiling opening. 1.00 Sq. M.
Room 2108 Repaired floor drain and shower drain stubout clog-up due to mortar inside the pvc pipe and
kitchen sink waterline leak due to installation of wall angle hit by screw Needs repair for ceiling opening.
1.00 Sq. M.
23rd Floor Elevator lobby/ hallway Repaired floor drain and shower drain stubout clog-up due to mortar
inside the pvc pipe . Needs repair for ceiling opening.
1.00 Sq. M.
24th Floor Elevator lobby/ hallway Repaired floor drain and shower drain stubout clog up due to mortar 1.00 Sq. M.
inside the pvc pipe . Needs repair for ceiling opening.
25th Floor Elevator lobby/ hallway Repaired floor drain and shower drain stubout clog up due to mortar
inside the pvc pipe . Needs repair for ceiling opening.
1.00 Sq. M.
26th Floor Elevator lobby/ hallway Repaired floor drain and shower drain stubout clog up due to mortar
inside the pvc pipe . Needs repair for ceiling opening.
1.00 Sq. M.
27th Floor Elevator lobby/ hallway Repaired water leak due to welded B.I pipe joint after testing of fire 1.00 Sq. M.
protection. Needs repair for ceiling opening.
28th Floor Elevator lobby/ hallway Repaired floor drain and shower drain stubout clog up due to mortar
inside the pvc pipe . Needs repair for ceiling opening. 1.00 Sq. M.
29th Floor Elevator lobby/ hallway Repaired water leak due to welded B.I pipe joint after testing of fire
protection. Needs repair for ceiling opening.
1.00 Sq. M.
30th Floor Elevator lobby/ hallway Repaired water leak due to welded B.I pipe joint after testing of fire
protection. Needs repair for ceiling opening.
1.00 Sq. M.
31st Floor Elevator lobby/ hallway Repaired water leak due to welded B.I pipe joint after testing of fire
protection. Needs repair for ceiling opening.
1.00 Sq. M.
32nd Floor Elevator lobby/ hallway Repaired water leak due to welded B.I pipe joint after testing of fire
protection. Needs repair for ceiling opening.
1.00 Sq. M.
16.50 20mm x 300mm Solid Accoya wood spaced at 25mm 106.70 Sq. M. 1,232.00 131,456.39
16.60 50mm x 150mm Solid Accoya Wood 246.52 Sq. M. 1,064.00 262,294.65
16.70 Rubbed Ceiling 1,235.04 Sq. M. 50.00 55.00 129,679.26
17.0 WATERPROOFING 7,844,442.00
17.01 Vandex Capillary 5,311.83 Sq. M. 410.31 2,179,498.44
Basement Domestic Water Tank 212.45 Sq. M.
Basement Fire Reserve Water Tank 224.11 Sq. M.
Basement STP 207.00 Sq. M.
Basement Retaining Wall 614.07 Sq. M.
1,257.62
17.02 3.0 Kg. Waterproofing 1,693.61 Sq. M. 418.00 707,929.18
5th Floor Ledge above Genset Room & LVSG Room 76.44 Sq. M.
Rm. 2201 Balcony 5.01 Sq. M.
Rm. 2202 Balcony 4.95 Sq. M.
Rm. 2203 Balcony 4.62 Sq. M.
Rm. 2204 Balcony 4.91 Sq. M.
Rm. 2205 Balcony 4.91 Sq. M.
Rm. 2206 Balcony 4.58 Sq. M.
Rm. 2207 Balcony 4.62 Sq. M.
Rm. 2208 Balcony 4.62 Sq. M.
Rm. 2301 Balcony 5.01 Sq. M.
Rm. 2302 Balcony 4.95 Sq. M.
Rm. 2303 Balcony 4.62 Sq. M.
Rm. 2304 Balcony 4.91 Sq. M.
Rm. 2305 Balcony 4.91 Sq. M.
Rm. 2306 Balcony 4.58 Sq. M.
Rm. 2307 Balcony 4.62 Sq. M.
Rm. 2308 Balcony 4.62 Sq. M.
Rm. 2401 Balcony 6.72 Sq. M.
Rm. 2402 Balcony 5.10 Sq. M.
Rm. 2403 Balcony 7.82 Sq. M.
Rm. 2501 Balcony 6.66 Sq. M.
Rm. 2502 Balcony 5.10 Sq. M.
Rm. 2503 Balcony 7.78 Sq. M.
Rm. 2601 Balcony 6.66 Sq. M.
Rm. 2602 Balcony 5.10 Sq. M.
Rm. 2603 Balcony 7.78 Sq. M.
Rm. 2701 Balcony 6.66 Sq. M.
Rm. 2702 Balcony 5.10 Sq. M.
Rm. 2703 Balcony 7.78 Sq. M.
Rm. 2801 Balcony 6.66 Sq. M.
Rm. 2802 Balcony 5.10 Sq. M.
Rm. 2803 Balcony 7.78 Sq. M.
Rm. 2901 Balcony 6.66 Sq. M.
Rm. 2902 Balcony 5.10 Sq. M.
Rm. 2903 Balcony 7.78 Sq. M.
Rm. 3001 Balcony 6.66 Sq. M.
Rm. 3002 Balcony 5.10 Sq. M.
Rm. 3003 Balcony 7.78 Sq. M.
Rm. 3101 Balcony 6.66 Sq. M.
Rm. 3102 Balcony 5.10 Sq. M.
Rm. 3103 Balcony 7.78 Sq. M.
Rm. 3201 Balcony 6.66 Sq. M.
Rm. 3202 Balcony 5.10 Sq. M.
Rm. 3203 Balcony 7.78 Sq. M.
328.81
17.03 4.5 Kg. Waterproofing 4,755.00 Sq. M. 479.33 2,279,212.64
Rm. 601 T&B 4.82 Sq. M.
Rm. 602 T&B 4.82 Sq. M.
Rm. 603 T&B 4.82 Sq. M.
Rm. 604 T&B 4.82 Sq. M.
Rm. 605 T&B 4.82 Sq. M.
Rm. 606 T&B 4.82 Sq. M.
Rm. 607 T&B 4.82 Sq. M.
Rm. 608 T&B Sanitary piping Slab water leak due to waterproofing seepage. Need for waterproofing. 4.82 Sq. M.
Rm. 806 T&B Sanitary piping Slab water leak due to water proofing seepage. Need for water proofing 4.82 Sq. M.
Rm. 1608 T&B Sanitary piping Slab water leak due to water proofing seepage. Need for water proofing. 4.82 Sq. M.
Rm. 2001 T&B Sanitary piping Slab water leak due to water proofing seepage. Need for water proofing. 4.82 Sq. M.
Rm. 2603 Common CR, Slab water leak due to water proofing seepage. Need for water proofing. 6.67 Sq. M.
Rm. 3003 Common CR, Slab water leak due to water proofing seepage. Need for water proofing. 6.67 Sq. M.
Rm. 3103 Common CR, Slab water leak due to water proofing seepage. Need for water proofing. 6.67 Sq. M.
22F - 23F Lower Loft Room Unit Bedroom Door 2.00 set
22F - 23F Lower Loft Room Unit T&B Door 18.00 set
22F - 23F Lower Loft Room Unit Storage Room Door 4.00 set
22F - 23F Upper Loft Room Unit Bedroom Door 18.00 set
22F - 23F Upper Loft Room Unit T&B Door 22.00 set
223.00
20.0 MISC. METAL WORKS 19,610,117.74
Steel Louver 763.00 Sq. M. 8,946.25 Included 6,825,991.04
Aircon Enclosure 6th Flr. - 21st Flr. 758.76 Sq. M.
Aircon Enclosure Room 612 4.24 Sq. M.
Machine Room wall louver 8.80 Sq. M.
771.80
Misc. Nosing
Angle Bar Nosing 1,523.00 L.M. 2,083.90 Included 3,173,779.70
Misc. Railing
Steel Railing (38mm Ø B.I. Pipe Automative Laquer Paint) 1,048.00 L.M. 4,100.00 Included 4,296,800.00
Fire Exit Stair 1 Ground Floor to Roof Deck 516.62 L.M.
Fire Exit Stair 2 5th Floor to 32nd Floor 428.06 L.M.
Fire Exit Stair 3 Basement to 5th Floor 103.32 L.M.
Helipad leftside & rearside rail damaged 52.57 L.M.
1,100.57
Roof deck to Machine room stair
I-beam 100mm.x200mm.x9mm.-thick (include paint) 8.68 L.M.
Angle bar 11/2"x11/2"x6mm.-thick (include paint) 82.20 L.M.
Flat bar 11/2"x6mm.-thick (include paint) 72.00 L.M.
Steel Railing (38mm Ø B.I. Pipe Automative Laquer Paint) 8.42 L.M.
COMPUTATION FOR DEDUCTION
AMOUNT PROGRESS BALANCES / DEDUCTIVE NOTES / STATUS
ACCOMP. %
% AMOUNT
635,015.00
2,151,311.28
480,410.00
686,300.00 30.00% 70.00% 480,410.00 epoxy not applied.
88,528.50
354,114.00 75.00% 25.00% 88,528.50 Ground Floor - 32nd Floor Elevator lobby granite wall
joint needs epoxy application & buffing.
10,110,746.00
100.00% 1,202.98
1,202.98 0.00% Needs repair for ceiling opening
100.00% 1,202.98
1,202.98 0.00% Needs repair for ceiling opening
100.00% 1,202.98
1,202.98 0.00% Needs repair for ceiling opening
100.00% 1,202.98
1,202.98 0.00% Needs repair for ceiling opening
7,680.00 0.00% 100.00% 7,680.00 Needs for wall re-pair and re-installation of wall tiles
100.00% 1,202.98
1,202.98 0.00% Needs repair for ceiling opening
1,575,480.29
1,680,198.00
3,790,300.00
4,500.00 0.00% 100.00% 4,500.00 Installed but Ma'am Susan is asking for the approved RFA document due to
high cost & quality issue.
810,000.00 0.00% 100.00% 810,000.00 Installed but Ma'am Susan is asking for the approved RFA document due to
high cost & quality issue.
67,500.00 0.00% 100.00% 67,500.00 Installed but Ma'am Susan is asking for the approved RFA document due to
high cost & quality issue.
72,000.00 0.00% 100.00% 72,000.00 Installed but Ma'am Susan is asking for the approved RFA document due to
high cost & quality issue.
9,000.00 0.00% 100.00% 9,000.00 Installed but Ma'am Susan is asking for the approved RFA document due to
high cost & quality issue.
81,000.00 0.00% 100.00% 81,000.00 Installed but Ma'am Susan is asking for the approved RFA document due to
high cost & quality issue.
99,000.00 0.00% 100.00% 99,000.00 Installed but Ma'am Susan is asking for the approved RFA document due to
high cost & quality issue.
Installed but Ma'am Susan is asking for the approved RFA document due to
9,000.00 0.00% 100.00% 9,000.00 high cost & quality issue.
121,500.00 0.00% 100.00% 121,500.00 Installed but Ma'am Susan is asking for the approved RFA document due to
high cost & quality issue.
40,500.00 0.00% 100.00% 40,500.00 Installed but Ma'am Susan is asking for the approved RFA document due to
high cost & quality issue.
Installed but Ma'am Susan is asking for the approved RFA document due to
115,960.00 0.00% 100.00% 115,960.00 high cost & quality issue.
2,333,706.31
2nd Floor Inter-Connecting Ramp Safety Railings, iron steel epoxy-painted 37.75 Sq. M.
3rd Floor Inter-Connecting Ramp Safety Railings, iron steel epoxy-painted 37.75 Sq. M.
4th Floor Inter-Connecting Ramp Safety Railings, iron steel epoxy-painted 37.75 Sq. M.
151.00
100mm x 200mm Tubular Steel Railing Painted Finish 108.00 L.M. 4,100.00 Included 442,800.00
Ladder rung for Watertank 76.00 Sets 15,000.00 Included 1,140,000.00
Basement Domestic Water Tank Ladder rung 9.00 set
Basement Fire Water Tank Ladder rung 9.00 set
Basement Rain Water Tank Ladder rung 10.00 set
Not installed 48.00 set
76.00
Separator Beam 98.00 Sets 12,500.00 Included 1,225,000.00
Hoisting Beam 1.00 Sets 150,000.00 Included 150,000.00
Column Guard - Angle Bars 288.00 Sets 2,500.00 Included 720,000.00
Wheel Stop 67.00 Sets 4,250.00 Included 284,750.00
Ground Floor 7.00 set
Upper Ground Floor 15.00 set
2nd Floor 15.00 set
3rd Floor 15.00 set
4th Floor 15.00 set
67.00
21.0 PAINTING WORKS 31,000,000.00
COLOURTECH 1.00 Lot 31,000,000.00 31,000,000.00
INTERIOR WALL CONCERN
Basement
Common area walls unfinished painting. 678.93 Sq. M.
Fire exit #3 wall unfinished painting. 47.88 Sq. M.
Ground Floor
Lounge area 239.91 Sq. M.
Office 45.93 Sq. M.
Control room 43.56 Sq. M.
Security room 48.57 Sq. M.
Common toilet 10.98 Sq. M.
Parking area/Driveway 263.85 Sq. M.
STP 65.13 Sq. M.
Electrical room 26.13 Sq. M.
Fire exit #1 40.17 Sq. M.
Fire exit #3 wall unfinished painting, mid-landing wall rainwater seepage. 48.78 Sq. M.
Guard house 43.02 Sq. M.
Planter near main entrance 55.08 Sq. M.
Planter near ramp 21.85 Sq. M.
Material Recovery Facility/Waste Area unfinished painting. 191.46 Sq. M.
Upper Ground Floor
Parking area to include floor marking. 342.45 Sq. M.
Fire exit #1 39.30 Sq. M.
Fire exit #3 48.78 Sq. M.
Fire exit #1 exterior wall. 43.02 Sq. M.
Elevator core area 36.06 Sq. M.
Electrical room 33.00 Sq. M.
2nd Floor
Parking area to include floor marking. 342.45 Sq. M.
Fire exit #1 wall unfinished painting. 39.30 Sq. M.
Fire exit #3 final painting 48.78 Sq. M.
Fire exit #1 exterior wall. 43.02 Sq. M.
Elevator core area final painting. 36.06 Sq. M.
Electrical room unfinished painting. 26.43 Sq. M.
3rd Floor
Driveway/Parking paint floor marking. 342.45 Sq. M.
Fire exit #1 wall final painting. 39.30 Sq. M.
Fire exit #3 final painting. 48.78 Sq. M.
Fire exit #1 exterior wall. 43.02 Sq. M.
Elevator core area final painting. 36.06 Sq. M.
Electrical room unfinished painting. 26.43 Sq. M.
4th Floor
Driveway/Parking paint floor marking. 342.45 Sq. M.
Fire exit #1 wall final painting. 39.30 Sq. M.
Fire exit #3 final painting. 48.78 Sq. M.
Fire exit #1 wall final painting. 43.02 Sq. M.
Elevator lobby. 36.06 Sq. M.
Electrical Room unfinished painting. 26.43 Sq. M.
5th Floor
Multi-purpose area 66.93 Sq. M.
Genset room 115.11 Sq. M.
Electrical room 28.20 Sq. M.
Pump room 27.81 Sq. M.
Shower area 25.20 Sq. M.
Fire exit #1 wall final painting. 44.01 Sq. M.
Fire Exit 2 rainwater seepage thru wall. 49.23 Sq. M.
Transformer area 193.29 Sq. M.
Column Area 75.60 Sq. M.
Planter near Electrical room 29.23 Sq. M.
Planter near Pool deck 129.34 Sq. M.
6th Floor
Fire exit #1 wall final painting. 39.27 Sq. M.
Fire exit #2 rainwater seepage thru wall. 48.33 Sq. M.
6th Flr. hallway wall peeling paint between Rm.605 & Rm.606. 268.80 Sq. M.
Rm.601 wall rainwater seepage. 49.97 Sq. M.
Rm.602 wall rainwater seepage. 49.25 Sq. M.
Rm.603 wall rainwater seepage. 49.61 Sq. M.
Rm.603 dirt on the wall caused by hands in installing aircon enclosure.
Rm.605 dirt on the wall caused by hands in installing aircon enclosure. 48.14 Sq. M.
Rm.605 wall with crack.
Rm.606 wall with crack. 47.71 Sq. M.
Rm.606 wall rainwater seepage.
Rm.607 dirt on the wall caused by hands in installing aircon enclosure. 51.58 Sq. M.
Rm.607 wall peeling paint.
Rm.608 wall with crack. 47.74 Sq. M.
7th Floor
Fire exit #1 wall final painting. 39.27 Sq. M.
7th Flr. hallway wall peeling paint near Rm.705. 268.80 Sq. M.
Room 701 column rainwater seepage. 49.97 Sq. M.
Room 701 wall rainwater seepage.
Room 703 wall rainwater seepage. 49.61 Sq. M.
Room 704 wall rainwater seepage. 49.37 Sq. M.
Rm.704 sprinkler head with paint.
Room 705 wall rainwater seepage. 48.14 Sq. M.
Rm.706 wall peeling paint.
COMPUTATION FOR DEDUCTION
AMOUNT PROGRESS BALANCES / DEDUCTIVE NOTES / STATUS
ACCOMP. %
% AMOUNT
Wide spacing between posts & railings which is unsafe. As per Madam
Susan, this is to be done by Monocrete since the Owner was the one
337,749.25 30.00% 70.00% 236,424.48 working for the perimeter railings of the balconies and deck.
Wide spacing between posts & railings which is unsafe. As per Madam
Susan, this is to be done by Monocrete since the Owner was the one
337,749.25 60.00% 40.00% 135,099.70 working for the perimeter railings of the balconies and deck.
Wide spacing between posts & railings which is unsafe. As per Madam
Susan, this is to be done by Monocrete since the Owner was the one
337,749.25 60.00% 40.00% 135,099.70 working for the perimeter railings of the balconies and deck.
10,311,182.18
50,630.72 92.50% 7.50% 3,797.30 RETENTION WILL BE SUBJECTED TO THE COMPLETION OF PAINTING WORKS
ON THE PUNCH LIST & BALANCES OF WORK
164.76 Sq. M.
Room 2305 Lower Loft Living room wall rainwater seepage(1).
Room 2305 Lower Loft Living room wall rainwater seepage(2). 164.76 Sq. M.
Room 2305 Lower Loft Living room wall rainwater seepage(3).
Room 2305 Lower Loft Bedroom wall rainwater seepage.
Room 2305 Upper Loft Bedroom T&B wall rainwater seepage.
Room 2305 Upper Loft Bedroom wall rainwater seepage.
148.77 Sq. M.
Room 2305 Upper Loft mid-stair ceiling slab soffit rainwater seepage. Structural repair needed.
Viewing Deck Planter waterproofing adjacent to the Hallway needs to be rectified since electrical
bussduct is found below its floor level.
25th Floor
Fire exit #1 wall final painting. 43.11 Sq. M.
Fire Exit 2 wall unfinished painting. 46.53 Sq. M.
Stockroom final painting. 25.02 Sq. M.
Hallway wall and ceiling final paint. 106.74 Sq. M.
Room 2501 full primer paint. 139.32 Sq. M.
Room 2502 full primer paint.
Room 2502 Maid's room wall rainwater seepage.
Room 2502 Living room wall rainwater seepage(1).
227.58 Sq. M.
Room 2502 Living room wall rainwater seepage(2).
Room 2502 Bedroom wall rainwater seepage.
Room 2502 Balcony wall rainwater seepage.
Room 2503 full primer paint.
Room 2503 Living room near balcony wall rainwater seepage.
171.84 Sq. M.
Room 2503 Bedroom wall rainwater seepage.
Room 2503 Master bedroom wall rainwater seepage.
26th Floor
Stockroom wall rainwater seepage. 25.02 Sq. M.
Hallway wall and ceiling final paint. 106.74 Sq. M.
Room 2601 full primer paint.
Room 2601 Kitchen wall rainwater seepage.
Room 2601 Living room wall rainwater seepage(1).
139.32 Sq. M.
Room 2601 Living room wall rainwater seepage(2).
Room 2601 Bedroom wall rainwater seepage.
Room 2601 Balcony wall rainwater seepage.
Room 2602 full primer paint. 227.58 Sq. M.
Room 2603 full primer paint.
Room 2603 Balcony concrete floor with cracks which caused water seepage. Structural repair needed.
171.84 Sq. M.
Room 2603 Living room near balcony wall rainwater seepage.
Room 2603 Bedroom wall rainwater seepage.
Room 2603 Master bedroom wall rainwater seepage.
27th Floor
Fire Exit 1 unfinished painting. 43.11 Sq. M.
Fire Exit 2 precast wall joint painting. 46.53 Sq. M.
Electrical Room final painting. 19.68 Sq. M.
Stockroom wall rainwater seepage. 25.02 Sq. M.
Hallway wall and ceiling final paint. 106.74 Sq. M.
Room 2701 full primer paint.
Room 2701 Kitchen wall rainwater seepage.
Room 2701 Living room wall rainwater seepage.
139.32 Sq. M.
Room 2701 Bedroom wall rainwater seepage.
Room 2701 Balcony wall rainwater seepage.
Room 2701 Balcony wall rainwater seepage.
Room 2702 full primer paint.
Room 2702 Maid's room wall crack with rainwater seepage.
Room 2702 Living room wall rainwater seepage.
Room 2702 Living room wall crack with rainwater seepage(1).
Room 2702 Living room wall crack with rainwater seepage(2).
Room 2702 Bedroom wall rainwater seepage.
Room 2702 Master bedroom wall rainwater seepage. 227.58 Sq. M.
BASED ON THE CONTRACT BILL OF QUANTITIES
NO. WORK ITEM QTY UNIT UNIT COST TOTAL AMOUNT
MATERIAL LABOR
Room 2702 Balcony wall rainwater seepage.
Room 2703 full primer paint.
171.84 Sq. M.
Room 2703 Living room wall rainwater seepage.
Room 2703 Bedroom wall rainwater seepage. 171.84 Sq. M.
Room 2703 Master bedroom wall rainwater seepage.
Room 2703 Balcony wall rainwater seepage.
28th Floor
Fire Exit 1 unfinished painting. 43.11 Sq. M.
Stockroom final painting. 25.02 Sq. M.
Electrical Room final painting. 19.68 Sq. M.
Hallway wall and ceiling final paint. 106.74 Sq. M.
Room 2801 full primer paint.
Room 2801 Balcony concrete floor with cracks which caused water seepage. Structural repair needed.
139.32 Sq. M.
Room 2801 Living Room wall rainwater seepage.
Room 2801 Bedroom wall rainwater seepage.
Room 2801 Balcony concrete floor with cracks which caused rainwater seepage.
Room 2802 full primer paint.
Room 2802 Maid's Room wall rainwater seepage(1).
Room 2802 Maid's Room wall rainwater seepage(2). 227.58 Sq. M.
Room 2802 Living Room wall rainwater seepage.
Room 2802 Balcony floor rainwater seepage.
Room 2803 full primer paint. 171.84 Sq. M.
29th Floor
Fire exit #1 unfinished painting. 43.11 Sq. M.
Fire Exit 2 unfinished painting. 46.53 Sq. M.
Stockroom final painting. 25.02 Sq. M.
Hallway, final paint. 106.74 Sq. M.
Room 2901 full primer paint.
Room 2901 Living Room wall rainwater seepage.
139.32 Sq. M.
Room 2901 Bedroom wall rainwater seepage.
Room 2901 Master Bedroom wall rainwater seepage.
Room 2902 full primer paint.
Room 2902 Living Room concrete slab with cracks which caused water seepage. Structural repair
needed.
Room 3202 Master Bedroom concrete floor with cracks which caused water seepage. Structural repair 227.58 Sq. M.
needed.
Room 3203 Balcony concrete floor cracks which caused water seepage. Structural repair needed. 171.84 Sq. M.
Room 3203 Bedroom concrete floor with cracks which caused water seepage. Structural repair
needed.
Roof Deck
Walls final painting. 121.78 Sq.M.
Floor slab cracks which caused the rainwater to seep down the 32nd Floor Hallway ceiling slab soffit.
Patch-up of the gaps between wall and the helipad floor which cause the rainwater entry.
Plastering of unplastered CHB wall near Helipad stair which causes the rainwater seepage.
166,863.98 75.00% 25.00% 41,715.99 RETENTION WILL BE SUBJECTED TO THE COMPLETION OF PAINTING WORKS
ON THE PUNCH LIST & BALANCES OF WORK
142,186.48 50.00% 50.00% 71,093.24 RETENTION WILL BE SUBJECTED TO THE COMPLETION OF PAINTING WORKS
ON THE PUNCH LIST & BALANCES OF WORK
29,300.70 50.00% 50.00% 14,650.35 RETENTION WILL BE SUBJECTED TO THE COMPLETION OF PAINTING WORKS
ON THE PUNCH LIST & BALANCES OF WORK
VENTILATING FANS
JF - 1 (jet fan) 2.00 unit 105,644.82
MONOXIDE SENSOR
1)CARBON, HEAT SENSOR & CONTROL 1.00 unit 246,504.57
2)CONTROL PANEL 1.00 unit 64,004.51
4TH FLOOR
VENTILATING FANS
JF - 1 (jet fan) 2.00 unit 105,644.82
MONOXIDE SENSOR
1)CARBON, HEAT SENSOR & CONTROL 1.00 unit 246,504.57
2)CONTROL PANEL 1.00 unit 64,004.51
5 FLOOR
TH
VENTILATING FANS
TEF - 1 (Male/Female Common toilet exhaust fan) 2.00 unit 8,803.73
22ND FLOOR LOWER & UPPER LOFT
VENTILATING FANS
TEF - 1 (Room Unit toilet exhaust fan) 17.00 unit 8,803.73
23RD FLOOR LOWER & UPPER LOFT
VENTILATING FANS
TEF - 1 (Room Unit toilet exhaust fan) 17.00 unit 8,803.73
24TH-32ND FLOOR
VENTILATING FANS
TEF - 1 (Room Unit toilet exhaust fan) 45.00 unit 8,803.73
CONDENSATE DRAIN FOR FCU
24 - 32 FLOOR
TH ND
6,669,097.54
Fixture unit lost at the site. Completely delivered to the site from China (140
sets installed out of 161 sets delivered from China).
10,080.00 0.00% 100.00% 10,080.00
13,520.00 13,520.00 Charged to Gencon by Ma'am Susan due to site security negligence.
BASED ON THE CONTRACT BILL OF QUANTITIES
NO. WORK ITEM QTY UNIT UNIT COST TOTAL AMOUNT
MATERIAL LABOR
Water closet seat cover - Ground floor Common CR, 5th Male and Female CR, Room 1201, 1202, 1207,
1208, 1211, 1401, 1402, 1407, 1409, 1410, 1411, 1412, 1511, 1512,
1601, 1603, 1605, 1607, 1610, 1702, 1703, 1704, 1705, 1706, 1707, 1708, 1709, 1710,
1811, 1812, 1901, 1902, 1903, 1904, 1906, 1907, 1908, 1912, 2001, 2002, 2003, 2004,
2005, 2006, 2007, 2008, 2009, 2010, 2011, 2012, 2101, 2102, 2103, 2104, 2105, 2106,
2107, 2108, 2109, 2110, 2111, 2112 66.00 pcs. 169.00 50.70
Water closet flushing mechanism - Ground floor Common CR, 5th Male and Female CR, Room 703, 704,
705, 712, 1904, 1906, 1907, 1908
12.00 pcs. 455.00 136.50
Water closet flexible hose - Ground floor Common CR, 5th Male and Female CR, Room 1903, 1906, 1907,
1908, 2101, 2102, 2103, 2104, 2105, 2106, 2107, 2108, 2109,
2110, 2111, 2112 20.00 pcs. 154.00 46.20
Water closet angle valve - Ground floor Common CR, 5th Male and Female CR, Room 1701, 1702, 1703,
1704, 1705, 1706, 1707, 1708, 1709, 1710, 1802, 1803, 1805, 1806,
1807, 1810, 1811, 1812, 1901, 1902, 1903, 1904, 1906, 1910, 1911, 1912, 2001, 2002,
2003, 2004, 2005, 2006, 2007, 2008, 2009, 2010, 2011, 2012, 2101, 2102, 2103, 2104,
2105, 2106, 2107, 2108, 2109, 2110, 2111, 2112 54.00 pcs. 260.00 78.00
Shower head - 5th Floor Showe Area, Room 1902, 1903, 1904, 1906, 1907, 1908,
2107, 2108, 2109, 2110, 2111, 2112 15.00 pcs. 282.00 84.60
5th Floor Showe Area, Hand shower w/ shower hose 3.00 pcs. 479.00 143.70
5th Floor Showe Area, Room 1902, 1903, 1904, 1906, 1907, 1908, 2107, 2108, 2109, 15.00 pcs. 952.00 285.60
2110, 2111, 2112 Shower stand
Shower mixing valve - 5th Floor Showe Area, Room 1902, 1903, 1904, 1906, 1907,
2107, 2108, 2109, 2110, 2111, 2112 14.00 pcs. 1,591.86 477.56
Lavatory basin - Ground floor Common CR, 5th Male and Female CR, Room 1903, 1904, 1906, 2101, 2102,
2103, 2104, 2105, 2106, 2107, 2108, 2109, 2110, 2111, 2112
18.00 pcs. 1,190.00 357.00
Lavatory semi-pedestal - Ground floor Common CR, 5th Male and Female CR, Room 1903, 1904, 1906,
2002, 2101, 2102, 2103, 2104, 2105, 2106, 2107, 2108, 2109, 2110,
2111, 2112 19.00 pcs. 650.00 195.00
Lavatory mixing faucet - Ground floor Common CR, 5th Male and Female CR, Room 1101, 1102, 1104,
1105, 1106, 1107, 1207, 1212, 1408, 1409, 1410, 1411, 1412, 1501,
1502, 1506, 1512, 1601, 1603, 1604, 1605, 1606, 1607, 1609, 1610, 1611, 1612, 1701,
1703, 1704, 1705, 1706, 1802, 1803, 1804, 1805, 1806, 1807, 1810, 1811, 1812, 1901,
1902, 1903, 1904, 1906, 1907, 1908, 1910, 1911, 1912, 2001, 2002, 2003, 2004, 2005,
2006, 2007, 2008, 2009, 2010, 2011, 2012, 2101, 2102, 2103, 2104, 2105, 2106, 2107, 78.00 pcs. 836.00 250.80
2108, 2109, 2110, 2111, 2112
Lavatory flexible hose - Ground floor Common CR, 5th Male and Female CR, Room 1003, 1004, 1706, 1707,
1708, 1709, 1710, 1901, 1902, 1903, 1904, 1906, 1907, 1908,
1910, 1911, 1912, 2001, 2002, 2003, 2004, 2005, 2006, 2007, 2008, 2009, 2010, 2011,
2012, 2101, 2102, 2103, 2104, 2105, 2106, 2107, 2108, 2109, 2110, 2111, 2112 44.00 pcs. 159.00 47.70
Lavatory angle valve - Ground floor Common CR, 5th Male and Female CR, Room 1701, 1705, 1706, 1707,
1708, 1709, 1710, 1802, 1803, 1804, 1805, 1806, 1807, 1810,
1811, 1812, 1901, 1902, 1903, 1904, 1906, 1907, 1908, 1910, 1911, 1912, 2001, 2002,
2003, 2004, 2005, 2006, 2007, 2008, 2009, 2010, 2011, 2012, 2101, 2102, 2103, 2104,
2105, 2106, 2107, 2108, 2109, 2110, 2111, 2112 53.00 pcs. 165.00 49.50
Kitchen sink basin - Room 1903, 1906, 1907, 1908 4.00 pcs. 765.00 229.50
Kitchen sink faucet - Room 1902, 1904, 1906, 1907, 1908, 2001, 2002, 2003, 2004,
2005, 2006, 2007, 2008, 2009, 2010, 2011, 2012, 2101, 2102, 2103, 2104, 2105, 2106,
2107, 2108, 2109, 2110, 2111, 2112 29.00 pcs. 275.00 82.50
COMPUTATION FOR DEDUCTION
AMOUNT PROGRESS BALANCES / DEDUCTIVE NOTES / STATUS
ACCOMP. %
% AMOUNT
14,500.20 14,500.20
7,098.00 7,098.00
4,004.00 4,004.00 Charged to Gencon by Ma'am Susan due to site security negligence.
18,252.00 18,252.00 Charged to Gencon by Ma'am Susan due to site security negligence.
5,499.00 5,499.00 Charged to Gencon by Ma'am Susan due to site security negligence.
1,868.10 1,868.10 Charged to Gencon by Ma'am Susan due to site security negligence.
18,564.00 18,564.00
Charged to Gencon by Ma'am Susan due to site security negligence.
28,971.85 28,971.85 Charged to Gencon by Ma'am Susan due to site security negligence.
27,846.00 27,846.00 Charged to Gencon by Ma'am Susan due to site security negligence.
16,055.00 16,055.00 Charged to Gencon by Ma'am Susan due to site security negligence.
84,770.40 84,770.40 Charged to Gencon by Ma'am Susan due to site security negligence.
9,094.80 9,094.80 Charged to Gencon by Ma'am Susan due to site security negligence.
11,368.50 11,368.50 Charged to Gencon by Ma'am Susan due to site security negligence.
3,978.00 3,978.00 Charged to Gencon by Ma'am Susan due to site security negligence.
10,367.50 10,367.50 Charged to Gencon by Ma'am Susan due to site security negligence.
BASED ON THE CONTRACT BILL OF QUANTITIES
NO. WORK ITEM QTY UNIT UNIT COST TOTAL AMOUNT
MATERIAL LABOR
Kitchen sink flexible hose - Room 1901, 1902, 1903, 1904, 1906, 1907, 1908, 2001,
2002, 2003, 2004, 2005, 2006, 2007, 2008, 2009, 2010, 2011, 2012, 2101, 2102, 2103,
2104, 2105, 2106, 2107, 2108, 2109, 2110, 2111, 2112 31.00 pcs. 49.00 14.70
Kitchen sink angle valve - Room 1701, 1705, 1706, 1707, 1708, 1709, 1710, 1802,
1803, 1804, 1805, 1806, 1807, 1810, 1811, 1812, 1901, 1902, 1903, 1904, 1906, 1907,
1908, 1910, 1911, 1912, 2001, 2002, 2003, 2004, 2005, 2006, 2007, 2008, 2009, 2010,
2011, 2012, 2101, 2102, 2103, 2104, 2105, 2106, 2107, 2108, 2109, 2110, 2111, 2112 50.00 pcs. 109.00 32.70
1,974.70 1,974.70 Charged to Gencon by Ma'am Susan due to site security negligence.
7,085.00 7,085.00 Charged to Gencon by Ma'am Susan due to site security negligence.
157,850.00
73,907.92
66,907.92
7,000.00
GRAND TOTAL BASED ON THE WORK 53,818,184.82
BALANCES =