Overland flow time (tov), by Kebry Method: K 1.44 L (overland-flow length, in m) 1025 N 0.05 S (Terrain Slope) 0.59% tov (in min) 30.30
Channel flow time (tch), by Kirby Method:
K 0.0195 L (channel flow length, in m) 540 S (Channel slope) 0.0056 tch (in min) 18.29
Watershed area (in sq miles) 0.6 155.40 Ha
Gross total time of concentration (in min) 46.48
Duration (in min) 48.59
Return period (in yr) 2 Intensity (in mm/hr) 44.01 Return period (in yr) 5 Intensity (in mm/hr) 55.01 Return period (in yr) 25 Intensity (in mm/hr) 81.28 C 0.70 Q=CIA (in m3/s) 13.30 (for 2 yr RP) Q=CIA (in m3/s) 16.62 (for 5 yr RP) Q=CIA (in m3/s) 24.56 (for 25 yr RP) Stream Geometric Design [Sample] Discharge, Q2 (m3/sec) 13.30 Assumed Velocity, V (m/s) 1.1 Area Required, Ar (m2) 12.09
Cross Sectional Parameter, corresponding to 2 year return
period Discharge: Bottom Width, b (m) 7 Side Slope (Zl H: 1 V), zl 1.8 Side Slope (Zr H: 1 V), zr 1.8 Channel Depth, y (m) 1.4 Top Width, T (m) 12.04 Area of Channel 13.33 Wetted Perimeter, P (m) 12.77 Hydraulic mean radius, R 1.04
Existing Channel Slope, S (m/m) 0.006
Required Slope 0.0010
Manning's roughness, n 0.030
Manning's Velocity, Vm (m/s) 1.10
Froude Number F 0.33
Discharge, Q25(m3/sec) 24.56
Enter Assumed Velocity, V (m/s) 1.12 Area Required, Ar (m2) 21.93
Cross Sectional Parameter, corresponding to 25 year return
period Discharge: Extra width, wl 3 Extra width, wr 3 Total width 18.04 Enter Side Slope (Zl H: 1 V), zl 1 Enter Side Slope (Zr H: 1 V), zr 1 Depth Ye 0.47 Top width 18.98 Area Extra 8.6997 Total Area 22.03 Total Wetted Perimeter 20.61 Hydraulic mean radius, R 1.07