EPSB WEEKLY LIST OF ACTIVITY (20/05/2023-26/05/2023)

WORK PERMIT ISSUE DATE TASK DESCRIPTION LOCATION DURATION REMARKS


WP-23-0568 PREVENTIVE MAINTENANCE BAUS SB 1900hrs-0000hrs - No impact to operation.
WP-23-0568 PREVENTIVE MAINTENANCE SUJS SB 0700hrs-1300hrs - No impact to operation.
- Interruption possibility
EP-23-1758-1 CAPACITOR BANK CONTACTOR REPLACEMENT TTDS NB 0000Hrs-0400Hrs
20/05/2023 during replacement work.
EP-23-1678-1 EARTHING & LIGHTNING (VIADUCT) SRRS - BTHS 0000Hrs-0400Hrs - Require access to viaduct.
WP-23-0568 ONLINE PD MAPPING SRRS 0000Hrs-2359Hrs - No impact to operation.
WP-23-0568 PREVENTIVE MAINTENANCE TTDS NB 1900hrs-0000hrs - No impact to operation.
WP-23-0568 PREVENTIVE MAINTENANCE STKS NB 0700hrs-1300hrs - No impact to operation.
ON-LOAD TEST MOBILE GENSET FOR 1000KVA - Required to De-Energize
EP-23-1672-1 BTHS 0000Hrs-0400Hrs
21/05/2023 GENERATOR Both Bound
EP-23-1677-1 EARTHING & LIGHTNING (VIADUCT) BTHS - BSCS 0000Hrs-0400Hrs - Require access to viaduct.
WP-23-0568 ONLINE PD MAPPING BTHS 0000Hrs-2359Hrs - No impact to operation.
WP-23-0568 PREVENTIVE MAINTENANCE TTDS SB 1900hrs-0000hrs - No impact to operation.
WP-23-0568 PREVENTIVE MAINTENANCE STKS SB 0700hrs-1300hrs - No impact to operation.
22/05/2023
EP-23-1676-1 EARTHING & LIGHTNING (VIADUCT) MERS - BUBS 0000Hrs-0400Hrs - Require access to viaduct.
WP-23-0568 ONLINE PD MAPPING MERS 0000Hrs-2359Hrs - No impact to operation.
WP-23-0568 PREVENTIVE MAINTENANCE PHDS NB 1900hrs-0000hrs - No impact to operation.
WP-23-0568 PREVENTIVE MAINTENANCE KAJS NB 0700hrs-1300hrs - No impact to operation.
WP-23-0566 COMPETENT ENGINEER INSPECTION (INCLUDING
SUBS - SEMS 0700hrs-1900hrs - No impact to operation.
PYWP-23-1569 DEPOT)
WP-23-0568 ONLINE PD MAPPING PHDS 0700Hrs-0400Hrs - No impact to operation.
EP-23-1757-1
FIBRE CABLE REPLACEMENT KWDS & KWDF 0000Hrs-0400Hrs - No impact to operation.
PYWP-23-1803
- De-Energize MSB B for
replacement of UVR.
23/05/2023
- Normalize back MSB B after
complete.
EP-23-1759-1 UNDER VOLTAGE RELEASE (UVR) REPLACEMENT BAUS NB 0000Hrs-0400Hrs - ATS will change over to
another source during this
work.
- There will be a glitch during
ATS changeover.
EP-23-1675-1 EARTHING & LIGHTNING (VIADUCT) BSCS - BDUS 0000Hrs-0400Hrs - Require access to viaduct.

WP-23-0568 PREVENTIVE MAINTENANCE PHDS SB 1900hrs-0000hrs - No impact to operation.


WP-23-0568 PREVENTIVE MAINTENANCE KAJS SB 0700hrs-1300hrs - No impact to operation.
COMPETENT ENGINEER INSPECTION (INCLUDING
WP-23-0566 SEMP - KAJS 0700hrs-1900hrs - No impact to operation.
DEPOT)
WP-23-0568 ONLINE PD MAPPING BDUS 0700Hrs-0400Hrs - No impact to operation.
- No impact to operation.
- EPSB will standby manpower
PYWP-23-1803 24/05/2023 33kV & LV RELAY RECALIBRATION KWDF 0000Hrs-0400Hrs at in-between station and at
the relay recalibration work
station.
EP-23-1674-1 EARTHING & LIGHTNING (VIADUCT) BDUS - SUJS - KAJD 0000Hrs-0400Hrs - Require access to viaduct.

- Interruption possibility for all


EP-23-1671-1 PM BATTERY CHARGER SUBD INFRA & RSMO 0000Hrs-0400Hrs connected load to battery
charger.
WP-23-0568 PREVENTIVE MAINTENANCE PBDS NB 1900hrs-0000hrs - No impact to operation.
WP-23-0568 PREVENTIVE MAINTENANCE KAJD DCR 0700hrs-1300hrs - No impact to operation.
WP-23-0682 FIBRE CABLE REPLACEMENT BUBS SB 0000Hrs-0400Hrs - No impact to operation.
- De-Energize AT2 for
replacement of Temperature
Controller.
- Normalize back AT2 after
REPLACEMENT OF TEMPERATURE CONTROLLER AT complete.
EP-23-1756-1 25/05/2023 KAJD DCR 0000Hrs-0400Hrs
AT2 - ATS will change over to
another source during this
work.
- There will be a glitch during
ATS changeover.
EP-23-1673-1 EARTHING & LIGHTNING (VIADUCT) SUJS - STKS 0000Hrs-0400Hrs - Require access to viaduct.
WP-23-0568 ONLINE PD MAPPING SUJS & KAJD 0700Hrs-0400Hrs - No impact to operation.
WORK PERMIT ISSUE DATE TASK DESCRIPTION LOCATION DURATION REMARKS
WP-23-0568 PREVENTIVE MAINTENANCE PBDS SB 1900hrs-0000hrs - No impact to operation.
WP-23-0568 PREVENTIVE MAINTENANCE KAJD INFRA & RSMO 0700hrs-1300hrs - No impact to operation.
ONLINE PD MAPPING KWDS 0700Hrs-2359Hrs - No impact to operation.
- De-Energize RT2 for
replacement of Temperature
EP-23-1754-1 REPLACEMENT OF TEMPERATURE CONTROLLER AT RT2 KDAS NB 0000Hrs-0400Hrs Controller.
26/05/2023
- Normalize back RT2 after
complete.
- Change selector to out of
service before replacement
EP-23-1755-1 BBHI RELAY REPLCEMENT TMUS SB 0000Hrs-0400Hrs
work.
- No impact to operation.