Kindly refer table below for EPSB List of Activity (09/07/2022 – 22/07/2022) for your record and perusal.

WORK PERMIT
DATE TASK DESCRIPTION LOCATION DURATION REMARKS
NO.
 Normalisation of HA2, HB3, R1 & R2 Incomer.
 Power will be interrupted at Entire Ring 4 for
Normalisation of SSU Semantan
EP-22-2202-1 09/07/2022 SEMP-BUBS 0000Hrs-0400Hrs temporary during switching activities.
Portal
 Affected Station (SEMP, MUNS, PASS, MERS,
BUBS, IVS1, IVS2).

WP-22-0872 09/07/2022 DB & SSB Relay Recalibration SUJS-KAJD 0700Hrs-1900Hrs  No Impact to Operation.

WP-22-0872 10/07/2022 DB & SSB Relay Recalibration STKS-KAJS 0700Hrs-1900Hrs  No Impact to Operation.

EP-22-2200-1 11/07/2022 Earthing Viaduct Inspection SUJS-STKS 0000Hrs-0400Hrs  Required to De-energize DC traction supply.

STKS-KAJS
EP-22-2199-1 12/07/2022 Earthing Viaduct Inspection 0000Hrs-0400Hrs  Required to De-energize DC traction supply.
Line End

EP-22-2198-1 13/07/2022 Earthing Viaduct Inspection BDUS-SUJS 0000Hrs-0400Hrs  Required to De-energize DC traction supply.
WP-22-0872 14/07/2022 DB & SSB Relay Recalibration SUBD 1900Hrs-0700Hrs  No Impact to Operation.

WP-22-0872 15/07/2022 DB & SSB Relay Recalibration KWSS 1900Hrs-0700Hrs  No Impact to Operation.

WP-22-0872 16/07/2022 DB & SSB Relay Recalibration KDAS 1900Hrs-0700Hrs  No Impact to Operation.

 Normalisation of LM2 STKS - LM1 KAJE (SB).


 Power will be interrupted at BSCS, BDUS,
Normalisation of LM2 STKS - SUJS, STKS SB & KAJD (A) for temporary
EP-22-2201-1 16/07/2022 BSCS-STKS 0000Hrs-0400Hrs
LM1 KAJE (SB) during switching activities.
 Affected Station (BSCS, BDUS, SUJS, STKS SB
& KAJD (A))
 Require to open AT2 at DCR B.
 Genset will run automatically to supply
On-Load Test Fixed Genset for essential load.
EP-22-2201-1 16/07/2022 SUBD 0000Hrs-0400Hrs
1250KVA Generator  Required FMAD to on pump sprinkle, pump
hose reel and pump hydrant to prevent
genset run without load.

WP-22-0872 20/07/2022 DB & SSB Relay Recalibration BSCS-BDUS 0700Hrs-1900Hrs  No Impact to Operation.
WP-22-0872 21/07/2022 DB & SSB Relay Recalibration BTHS-SRRS 0700Hrs-1900Hrs  No Impact to Operation.

WP-22-0872 22/07/2022 DB & SSB Relay Recalibration TCOS-TASS 0700Hrs-1900Hrs  No Impact to Operation.