Note - Procurement (including subcontracted activities) - Man-hours for each item to be procured or relevant value (in cost) of the material.
Note - Each deliverable shall be weighted in accordance with the value assigned to it within the programme. For those tagged items and equipment packages do not have
Site Acceptance Test, Site Material Receipt Inspection Record (MRIR) will be accepted to claim the progress rate
Receipt of all
Construction / Commissioning
Submission of
Dispatch documentation and Spare Parts as applicable.
Sl No. Nature of Items vendor drawings/ Site Delivery
Ex-Works
documentation
(for off the shelf items 100%
upon receipt of MRIR)
1 Bulk Materials 10% 75% 95% 100%
Note - Each deliverable shall be weighted in accord with the value assigned to it within the programme