Professional Documents
Culture Documents
Revised Contract time:- 3 Year and 7 months Total Amount W/VAT 1,722,099,316.81
PREVIOUS PAYMENT CHECK (C) To date Work Executed after IPC#24 in Birr (A-B) 140,804,198.89
No. Date Net Payment VAT (D) Price Adjustment In Birr -
Advance 449,243,300.04 67,386,495.01 (E)Work Executed Including Price Adjustment in Birr 1,036,314,848.20
IPC No.1 up to IPC
1_21 572,933,088.32 92,078,532.05 1,036,314,848.20
No.21 (F)Work Executed Including Variation order & Price Adju
22 IPC No.22 21,014,028.71 3,377,254.61 DEDUCTIONS ADDITIONS
23 IPC No.23 18,170,354.94 2,920,235.62 Description Amount Amount
24 IPC No.24 14,739,982.54 2,368,925.76 1. Total Previous Payment 655,710,965.14
25 IPC No.25 6,822,870.75 1,273,146.03 2. Rebate -
26 IPC No.26 10,411,043.24 1,942,698.14 3. Retention 5% 51,815,742.41
27 IPC No.27 7,198,038.26 1,343,152.19 4. Advance Repayment up to IPC#24 223,877,662.34
28 IPC No.28 4,421,558.38 825,061.72 5. Advance Repayment after IPC#24 104,910,478.31
29 Total Deduction 1,036,314,848.20 1,036,314,848.201
30 Net Payment Due to the Contractor W/O/VAT -
31
32
33
34
35
36
37 VAT PAYMENT CHECK
Total Previous Payment 655,710,965.14 106,129,006.13 Total Executed Amount 1,036,314,848.20
Amount of Advance Taken Birr W/O/VAT 449,243,300.04 Previous Paid VAT 106,129,006.13
Amount of Advance Repaid Birr W/O/VAT 328,788,140.65 Net VAT Payable on This Certificate -
Outstanding Advance Payment 120,455,159.39 Total Payment to the Contractor with 15% VAT -
We Certify that the Contractor is now Entitled to the Sum of Birr Five Million Two Hundred Forty Six Thousand Six Hundred Twenty & 11/100 only Including
15% VAT.
Executed Amount(Birr)
Ammendement
Item No. Work Description Contract No. 2 Amount
(Birr)
Current Previous Total To Date
Title:
Issue No: A1
Interim Payment Measurement No.29 (IPC No. 19 after Ammendement Contrat No.2) Page No:AKOF/CE/046
1 of 19
Issue Date: Feb
01,2021
Project: Lot-I: Welmel Weir and Feeder Canal Structures Construction Work Consultant: ECWDSC-WEDSWS
Location: Oromia Region, East Bale Zone, Angetu Woreda Contract Amount: ETB 1,497,477,666.79
1.7 Running cost for water and power supply Wk 143 10,000.00 1,430,000.00 158.00 158.00 - 1,580,000.00 1,580,000.00
1.9 Temporary access and haul roads Km 30 120,000.00 3,600,000.00 20.74 20.74 - 2,488,320.00 2,488,320.00
Maintenance of access and haul roads constructed by
1.10
the Contractor under item 1.9 Sum 1 5,823,360.00 5,823,360.00 85% 85% - 4,949,856.00 4,949,856.00
1.11 Provide Engineer's office net floor area of 80 m2 sum 1 10,000,000.00 10,000,000.00 100% 100% - 10,000,000.00 10,000,000.00
1.12 Allow measures against nuisance from dust etc. Wk 1 5,000.00 5,000.00 - - - - -
Provision and maintenance of construction posts for
1.13
project identification sum 1 5,000.00 5,000.00 0% - - - -
1.15 Provide furniture for the Engineer's office sum 1 5,000,000.00 5,000,000.00 95% 95% - 4,750,000.00 4,750,000.00
1.16 Maintenance of office for the Engineers staff sum 1 2,000,000.00 2,000,000.00 60% 60% - 1,200,000.00 1,200,000.00
Allow For Supplementary Electricity and Water
1.17
Supply for the Engineer Staff PS 0.25 5,000,000.00 1,250,000.00 - - - - -
1.24 Allow for security service sum 1 28,800.00 28,800.00 80% 80% - 23,040.00 23,040.00
Preparation and submission of Contractor's working
1.25
drawings sum 1 2,208,000.00 2,208,000.00 90% 90% - 1,987,200.00 1,987,200.00
Title:
Issue No: A1
Interim Payment Measurement No.29 (IPC No. 19 after Ammendement Contrat No.2) Page No: 2 of 19
AKOF/CE/046
Issue Date: Feb 01,2021
Project: Lot-I: Welmel Weir and Feeder Canal Structures Construction Work Consultant: ECWDSC-WEDSWS
Location: Oromia Region, East Bale Zone, Angetu Woreda Contract Amount: ETB 1,497,477,666.79
Title:
Issue No: A1
Interim Payment Measurement No.29 (IPC No. 19 after Ammendement Contrat No.2) Page No: 3 of 19
AKOF/CE/046
Issue Date: Feb 01,2021
Project: Lot-I: Welmel Weir and Feeder Canal Structures Construction Work Consultant: ECWDSC-WEDSWS
Location: Oromia Region, East Bale Zone, Angetu Woreda Contract Amount: ETB 1,497,477,666.79
Title:
Issue No: A1
Interim Payment Measurement No.29 (IPC No. 19 after Ammendement Contrat No.2) Page No: 4 of 19
AKOF/CE/046
Issue Date: Feb 01,2021
Project: Lot-I: Welmel Weir and Feeder Canal Structures Construction Work Consultant: ECWDSC-WEDSWS
Location: Oromia Region, East Bale Zone, Angetu Woreda Contract Amount: ETB 1,497,477,666.79
Title:
Issue No: A1
Interim Payment Measurement No.29 (IPC No. 19 after Ammendement Contrat No.2) Page No: 5 of 19
AKOF/CE/046
Issue Date: Feb 01,2021
Project: Lot-I: Welmel Weir and Feeder Canal Structures Construction Work Consultant: ECWDSC-WEDSWS
Location: Oromia Region, East Bale Zone, Angetu Woreda Contract Amount: ETB 1,497,477,666.79
Title:
Issue No: A1
Interim Payment Measurement No.29 (IPC No. 19 after Ammendement Contrat No.2) Page No: 6 of 19
AKOF/CE/046
Issue Date: Feb 01,2021
Project: Lot-I: Welmel Weir and Feeder Canal Structures Construction Work Consultant: ECWDSC-WEDSWS
Location: Oromia Region, East Bale Zone, Angetu Woreda Contract Amount: ETB 1,497,477,666.79
Title:
Issue No: A1
Interim Payment Measurement No.29 (IPC No. 19 after Ammendement Contrat No.2) Page No: 7 of 19
AKOF/CE/046
Issue Date: Feb 01,2021
Project: Lot-I: Welmel Weir and Feeder Canal Structures Construction Work Consultant: ECWDSC-WEDSWS
Location: Oromia Region, East Bale Zone, Angetu Woreda Contract Amount: ETB 1,497,477,666.79
Title:
Issue No: A1
Interim Payment Measurement No.29 (IPC No. 19 after Ammendement Contrat No.2) Page No: 8 of 19
AKOF/CE/046
Issue Date: Feb 01,2021
Project: Lot-I: Welmel Weir and Feeder Canal Structures Construction Work Consultant: ECWDSC-WEDSWS
Location: Oromia Region, East Bale Zone, Angetu Woreda Contract Amount: ETB 1,497,477,666.79
Title:
Issue No: A1
Interim Payment Measurement No.29 (IPC No. 19 after Ammendement Contrat No.2) Page No: 9 of 19
AKOF/CE/046
Issue Date: Feb 01,2021
Project: Lot-I: Welmel Weir and Feeder Canal Structures Construction Work Consultant: ECWDSC-WEDSWS
Location: Oromia Region, East Bale Zone, Angetu Woreda Contract Amount: ETB 1,497,477,666.79
Title:
Issue No: A1
Interim Payment Measurement No.29 (IPC No. 19 after Ammendement Contrat No.2) Page No: 10 of 19
AKOF/CE/046
Issue Date: Feb 01,2021
Project: Lot-I: Welmel Weir and Feeder Canal Structures Construction Work Consultant: ECWDSC-WEDSWS
Location: Oromia Region, East Bale Zone, Angetu Woreda Contract Amount: ETB 1,497,477,666.79
6.1 Sluices gate 5m*2.2, 1 service gate,I emergency gate t 11.00 85,000.00 935,000.00 - - - - -
6.2 Embedded parts including stem etc for the above t 11.00 85,000.00 935,000.00 10.38 10.38 - 882,130.00 882,130.00
Head Regulator Gate 2.4m*1.8m emergency gate and
6.3
service gate
t 3.00 85,000.00 255,000.00 - - - - -
6.4 Embedded parts includingswt of stem etc t 3.00 85,000.00 255,000.00 3.00 3.00 - 255,000.00 255,000.00
6.5 Gate size 3.1*1.15m two locations on canals t 3.20 85,000.00 272,000.00 - - - - -
Title:
Issue No: A1
Interim Payment Measurement No.29 (IPC No. 19 after Ammendement Contrat No.2) Page No: 11 of 19
AKOF/CE/046
Issue Date: Feb 01,2021
Project: Lot-I: Welmel Weir and Feeder Canal Structures Construction Work Consultant: ECWDSC-WEDSWS
Location: Oromia Region, East Bale Zone, Angetu Woreda Contract Amount: ETB 1,497,477,666.79
Title:
Issue No: A1
Interim Payment Measurement No.29 (IPC No. 19 after Ammendement Contrat No.2) Page No: 12 of 19
AKOF/CE/046
Issue Date: Feb 01,2021
Project: Lot-I: Welmel Weir and Feeder Canal Structures Construction Work Consultant: ECWDSC-WEDSWS
Location: Oromia Region, East Bale Zone, Angetu Woreda Contract Amount: ETB 1,497,477,666.79
Title:
Issue No: A1
Interim Payment Measurement No.29 (IPC No. 19 after Ammendement Contrat No.2) Page No: 13 of 19
AKOF/CE/046
Issue Date: Feb 01,2021
Project: Lot-I: Welmel Weir and Feeder Canal Structures Construction Work Consultant: ECWDSC-WEDSWS
Location: Oromia Region, East Bale Zone, Angetu Woreda Contract Amount: ETB 1,497,477,666.79
Title:
Issue No: A1
Interim Payment Measurement No.29 (IPC No. 19 after Ammendement Contrat No.2) Page No: 14 of 19
AKOF/CE/046
Issue Date: Feb 01,2021
Project: Lot-I: Welmel Weir and Feeder Canal Structures Construction Work Consultant: ECWDSC-WEDSWS
Location: Oromia Region, East Bale Zone, Angetu Woreda Contract Amount: ETB 1,497,477,666.79
118 PVC dustbin for storing density sand 100 1 capacity - 1,000.00 - - - - -
Sand pouring cylinder 200 mm dia complete with
119 metal trays 500 mm x 500 mm x 500 mm deep with - 1,000.00 - - - - -
200 mm dia hole in centre
120 Calibrating containers 200 mm dia. - 1,000.00 - - - - -
AGGREGATE TESTING APPARATUS - - - - -
1 Bulk density measure 1.4 dm³ 1 1,500.00 1,500.00 1.00 1.00 - 1,500.00 1,500.00
2 Bulk density measure 2.8 dm³ 1 1,800.00 1,800.00 1.00 1.00 - 1,800.00 1,800.00
Aggregate crushing value apparatus complete
3
including metal measure
1 2,500.00 2,500.00 1.00 1.00 - 2,500.00 2,500.00
Title:
Issue No: A1
Interim Payment Measurement No.29 (IPC No. 19 after Ammendement Contrat No.2) Page No: 15 of 19
AKOF/CE/046
Issue Date: Feb 01,2021
Project: Lot-I: Welmel Weir and Feeder Canal Structures Construction Work Consultant: ECWDSC-WEDSWS
Location: Oromia Region, East Bale Zone, Angetu Woreda Contract Amount: ETB 1,497,477,666.79
Title:
Issue No: A1
Interim Payment Measurement No.29 (IPC No. 19 after Ammendement Contrat No.2) Page No: 16 of 19
AKOF/CE/046
Issue Date: Feb 01,2021
Project: Lot-I: Welmel Weir and Feeder Canal Structures Construction Work Consultant: ECWDSC-WEDSWS
Location: Oromia Region, East Bale Zone, Angetu Woreda Contract Amount: ETB 1,497,477,666.79
Title:
Issue No: A1
Interim Payment Measurement No.29 (IPC No. 19 after Ammendement Contrat No.2) Page No: 17 of 19
AKOF/CE/046
Issue Date: Feb 01,2021
Project: Lot-I: Welmel Weir and Feeder Canal Structures Construction Work Consultant: ECWDSC-WEDSWS
Location: Oromia Region, East Bale Zone, Angetu Woreda Contract Amount: ETB 1,497,477,666.79
Title:
Issue No: A1
Interim Payment Measurement No.29 (IPC No. 19 after Ammendement Contrat No.2) Page No: 18 of 19
AKOF/CE/046
Issue Date: Feb 01,2021
Project: Lot-I: Welmel Weir and Feeder Canal Structures Construction Work Consultant: ECWDSC-WEDSWS
Location: Oromia Region, East Bale Zone, Angetu Woreda Contract Amount: ETB 1,497,477,666.79
Bill No. 11: Shewe Bridge and RCSlab community Bridge crossing - - - - -
A Shewe Bridge - - - - -
1* Foundation for Structures - - - - -
Excavation for Structures irrespective of depth ranges
1.1* - - - - -
and classes of excavation
1.1.1* Common Excavation m3 425.11 156.47 66,516.93 - - - -
1.2* Backfilling to excavation utilization - - - - -
1.2.1 Imported material m3 181.97 155.00 28,205.35 - - - -
1.3 Foundation fill - - - - -
1.3.1 Rock fill m3 50.26 303.67 15,261.21 - - - -
1.3.2 Compacted granular fill m3 119.52 896.00 107,085.53 - - - -
Mass Concrete (c-15 ) with plums of stone
1.3.3
(Cyclopean concrete)
m3 69.52 3,765.06 261,728.15 - - - -
1.4 Formwork for Concrete - - - - -
1.4.1 Formwork m2 53.15 311.31 16,547.07 - - - -
1.5 Steel Reinforcement for structures - - - - -
Reinforcement for Bridges,mild steel bar, deformed
1.5.1
grade 40
ton 0.45 65,000.00 29,250.00 - - - -
Reinforcement for Bridges,High yield stress steel
1.5.2
bar, deformed grade 40
ton 1.59 65,000.00 103,155.00 - - - -
1.6 Concrete for structures - - - - -
1.6.1 Cast-in -situ concrete for bridge, Grade 25/20 m3 27.17 4,145.00 112,619.24 - - - -
1.6.2 Cast-in -situ concrete for bridge, Grade 20/20 m3 50.09 4,490.82 224,952.36 - - - -
1.6.3 Cast-in -situ concrete for bridge, Grade 15/20 m3 62.50 3,765.06 235,316.25 - - - -
1.7 Bridge Railing ,Drainage for structures - - - - -
1.7.1 Reinforced Concrete railing m 10.00 970.02 9,700.20 - - - -
1.8 Expansion Joints - - - - -
Expansion Joints including 20mm compressible joint
1.8.1
filler board
m 68.50 1,250.00 85,625.00 - - - -
1.8.2 Filled Joints - - - - -
Filled Joints-Preformed expansion joint filler(20mm
1.8.3
thick)
m 54.00 1,250.00 67,500.00 - - - -
1.9 Sealing Joints - - - - -
Joint Sealant, 20mm deep grouted polysulphide
1.9.1
sealant
m 99.00 1,250.00 123,750.00 - - - -
1.1 Drainage pipes and weep holes - - - - -
1.10.1 Drainage pipes,10cm internal diameter PVc Nr 4.00 1,005.25 4,021.00 - - - -
1.11 Stone Masonry Structures - - - - -
1.11.1 Stone Masonry Wall - - - - -
1.11.1.1 Cement-mortared Stone masonry Wall(Class B) m3 231.89 1,900.00 440,599.55 - - - -
Sub-total A 1,931,832.84 - - -
Contractor's Representative Consultant's Representative Clients' Representative
Name:_________________________ Name:_________________________ Name:_________________________
Sign.__________________________ Sign.__________________________ Sign.__________________________
Date:__________________________ Date:__________________________ Date:__________________________
›KT¾G< Ÿ}T ÖpLL Y^ }s^ß Alemayehu Ketema General Contractor Document No:
Title:
Issue No: A1
Interim Payment Measurement No.29 (IPC No. 19 after Ammendement Contrat No.2) Page No: 19 of 19
AKOF/CE/046
Issue Date: Feb 01,2021
Project: Lot-I: Welmel Weir and Feeder Canal Structures Construction Work Consultant: ECWDSC-WEDSWS
Location: Oromia Region, East Bale Zone, Angetu Woreda Contract Amount: ETB 1,497,477,666.79
Sub-total B 3,473,462.96 - - -
Total of Bill Nr. 11 Carried to Summary 5,405,295.80 - - -
Total of all Bills carried to Summary 1,497,477,666.67 - 1,036,314,848.20 1,036,314,848.20
Issue Date:
Project: Lot-I: Welmel Weir and Feeder Canal Structures Construction Work Consultant:ECWDSC-WEDSWS
Feb 01,2021
Location: Oromia Region, East Bale Zone, Angetu Woreda Contract Amount: ETB 1,497,477,66.79
Location: Oromia Region, East Bale Zone, Angetu Woreda Contract Amount: ETB 1,497,477,66.79
Location: Oromia Region, East Bale Zone, Angetu Woreda Contract Amount: ETB 1,497,477,66.79
Client: FDRE, Ministry of Irrigation and Lowland Payment No: 27
Contractor: Alemayehu Ketema General Contractor Date:- October,2022
Location: Oromia Region, East Bale Zone, Angetu Woreda Contract Amount: ETB 1,497,477,66.79
Client: FDRE, Ministry of Irrigation and Lowland Payment No: 27
Contractor: Alemayehu Ketema General Contractor Date:- October,2022