Professional Documents
Culture Documents
+ - 2deviation Variance s2
Deviation s
pk Ay- # deviation Ay+ # deviation
68% Investment= Ay+-1 deviation 19,337 26,063 PV of project cf has 68% pro
95% Ay+- 2deviation 15,974 29,426 PV of project cf has 95% pro
Ex. 2 With the PV of above cf and the investment stated below, find average, deviation and 68-&95% -probability-range f
Invest= $20,000 Note. Use the same 3 scenarios and probabilities (40% for normal, 45% for expansion, and 15% recess
Scenario (k) Net Present Values Probability (pk) NPV*pk Deviation (Ak-Ay)
Expansion 6,000 40% 2400 3,300
Normal 2,000 45% 900 -700
Recession -4,000 15% -600 -6,700
Expected Net PV= 2,700
Ex-3 What is the probability that the NPV obtained in Ex2 is greater than zero.
=P(NPV)>0 ?
NPV= -663 0 2700
22,700
11,310,000
3,363 11310000
6,063
9,426
PV)>0 ?
27.30%
(80% of 34%)
27.3% + 50%= 77.3% probability that NPV greater than zero
SENSITIVITY ANALYSIS AND PROJECT SELECTION
Projects (NPV)= Xk
Scenario (k) Probability (k) 1 2 3 4
Recessive 5% -10,000 0 -15,000 -3,000
Pessimistic 15% -4,000 6,000 -8,000 5,000
Normal 40% 0 7,000 1,000 11,000
Optimistic 25% 6,000 9,000 9,000 14,000
Expansive 15% 9,000 10,000 18,000 17,000
(Source: Example 9.3 Sapag, pp.282)
1- Dominance of one project over another project When expected results of Alternative X is better than
Say let's work with projects 1 and 2 another alternative Y in all scenarios
This criterion can be used to eliminate one of these alternati
Projects (NPV) Xk
Scenario (k) Probability (k) 1 2 3 4
Recessive 5% -10,000 0 -15,000 -3,000
Pessimistic 15% -4,000 6,000 -8,000 5,000
Normal 40% 0 7,000 1,000 11,000
Optimistic 25% 6,000 9,000 9,000 14,000
Expansive 15% 9,000 10,000 18,000 17,000
Since project 2 dominates projects 1 in NPV in all scenarios, project 1 is eliminated, thus simplying decision making.
2. Aspiration level: Can be project with the highest probability of sucess, given an aspiration level previously defined.
Of all of these projects, under very conservative scenarios (recessive, pessimistic and normal) project 2 has the highest N
3. Expected Value E[ (X)] Find the highest Expected Value(NPV) E(X)= p1*X1+p2*X2+….+pn*Xn
Project E[ NPV x]
2 (0*.05)+(6000*.15)+(7000*.4)+(9000*.25)+(10000*.15)= 7450
3 (-15000*.05)+(-8000*.15)+(1000*.4)+(9000*.25)+(18000*.15)= 3400
4 (-3000*.05)+(5000*.15)+(11000*.4)+(14000*.25)+(17000*.15)= 11050
((0-7450)^2)*.05+
4-Variance of projects: RISK CRITERION
SAPAG book
Check on your notes or books from your previous Financial Management courses you have taken: CAPM
e X is better than
g decision making.
previously defined.
rank
2
lowest profit Choose project 4 3
(Highest profit) 1
^2)*.05+
+((10000-7450)^2)*.15= 4,747,500
2)*.25+((18000-3400)^2)*.15= 78,540,000
050)^2)*.25+((17000-11050)^2)*.15= 22,847,500