Professional Documents
Culture Documents
1.0 Introduction
2.0 Definitions and Abbreviations
3.0 Responsibilities
4.0 Equipment & Tools
5.0 Specific Training
6.0 Material Handling
7.0 Permits
8.0 Methodology
9.0 Safety & Health
10.0 Backfilling and Clean-up
11.0 Demobilization
1.0 INTRODUCTION
Shell Nigeria Gas (SNG) is seeking to engage the services of a CONTRACTOR to construct a
Wall Retaining Fence at their Pressure Reduction and Metering Station(s) “PRMS”.
1.1 SCOPE
This method statement outlines the procedure and methodology for the Construction of Wall
Retaining Fence in PRMS. This procedure shall be read in conjunction with contract
specifications, Contract Approved Drawings and Project Approved Quality Plan.
Project Manager is responsible for overall project execution, quality and safety.
Adopt a leading role with respect to Contractor’s quality and safety procedures. The PM is
responsible for the overall implementation of this method statement. The Project Manager
shall ensure that the key personnel are well aware of the specifications and method
statement.
SE / Site Engineer shall arrange all materials, equipment, safety related items & manpower
& direct the Site Surveyors & Foremen to resort appropriate action for the smooth execution
of the works.
HSE Officer shall be responsible for safe working environment & conditions. Coordinate
with Site Engineer to identify potential hazards before works and advice methods of safe
working from new developments.
SS Site Surveyor shall be responsible for setting out for levels, layout, and lines & establish
top levels. Ensuring setting out books are properly maintained and filed when completed. To
also determining coordinates, levels, and limits where required by site engineer.
QA/QC Engineer shall be responsible for ensuring that execution of works are complying
with approved method statement and contract specifications/ drawings.
7.0 PERMITS
All necessary Permit to Work shall be obtained before commencement of work.
8.0 METHODOLOGY
The entire job site shall be cleared of bushes, debris and earthwork of the work area shall be carried out
manually with shovels so as to create enough space for all site activities.
The initial temporal erosion control materials (Sand Bag or Boulders) if there is any that has deteriorated
alongside debris within the erosion imparted area shall be removed and transfer to a temporary location
and /or dump site as approved by client site representative.
8.4 DEMOLITION
The affected and/or existing structure(s) shall be demolished and cart away of pieces of blocks as well as
any other associated materials while putting all the necessary hazards in consideration with safety
preventive measures.
Excavation shall be manually carried out as per approved drawing giving room for construction
allowance.
Sharp sand will be used to fill and level the base to the required level while plate compactor will be used
for compaction.
The Surveyor using a calibrated level instrument shall align and control the level.
Probing of the line with pipe detector will be done to determine if there is any underground facility on the
line. In case of obstruction the Client engineer will advise accordingly.
Filling in the trench with concrete or mortar for ground beam where the top surface is levelled to
form the underside of a floor slab shall be carried out.
Ground beam shall be laid to support the brick/block work where they form permanent
shuttering.
Bonding of solid brick blocks shall be done to obtain maximum strength whilst distributing the
loads to be carried throughout the wall, column or pier, ensure lateral stability and resistance to
side thrusts, as well as creating an acceptable appearance.
Mamtech’s personnel will comply with all safety rules as contained in the submitted HSE plan for the
project.
After loosing of the formwork, all side of the new Casting shall be backfilled as per contract instructions,
properly compacted.
11.0 DEMOBILIZATION
All equipment and tools shall be moved out of the site.