You are on page 1of 3

Project : INFINITY SQUARE

Location : QUEZON BOULEVARD ST., QUIAPO, MANILA


Subject : Bid proposal for heritage bldg from second, third and fourth
Date : MAY 19, 2022
Item # Description of Works Quantity Units Labor Cost Total Amount
1.0 SECOND FLOOR
1.1 Roughing ins( including boxes)
Lighting outlet 512 Pcs 300.00 153,600.00
Siwitch outlet 48 Pcs 300.00 14,400.00
Convenience outlet 48 Pcs 360.00 17,280.00
Aircon outlet 9 Pcs 1,320.00 11,880.00
Water Heater Outlet 9 Pcs 1,320.00 11,880.00
Panel board( tap to pullbox only) 12 Pcs 2,700.00 32,400.00
1.2 Wiring System (including termination) -
Lighting oulet 512 Pcs 240.00 122,880.00
Switch outlet 48 Pcs 240.00 11,520.00
Convenience outlet 48 Pcs 150.00 7,200.00
Aircon outlet 9 Pcs 600.00 5,400.00
Water Heater Outlet 9 Pcs 600.00 5,400.00
Panelboard( tap to pullbox only) 12 Pcs 2,100.00 25,200.00
1.3 Installation of wiring devices and panelboard -
Lighting fixtures 512 Pcs 60.00 30,720.00
Siwich outlet 48 Pcs 162.00 7,776.00
Convenience outlet 48 Pcs 162.00 7,776.00
Acu outlet 9 Pcs 300.00 2,700.00
Water Heater Outlet 9 Pcs 300.00 2,700.00
Panelboards 12 Pcs 1,500.00 18,000.00
Sub-total 488,712.00
2.0 THIRD FLOOR
2.1 Roughing ins( including boxes)
Lighting outlet 478 Pcs 300.00 143,400.00
Siwitch outlet 48 Pcs 300.00 14,400.00
Convenience outlet 64 Pcs 360.00 23,040.00
Aircon outlet 12 Pcs 1,320.00 15,840.00
Water Heater Outlet 12 Pcs 1,320.00 15,840.00
Panel board( tap to pullbox only) 12 Pcs 2,700.00 32,400.00
2.2 Wiring System (including termination) -
Lighting outlet 478 Pcs 240.00 114,720.00
Switch outlet 48 Pcs 240.00 11,520.00
Convenience outlet 64 Pcs 150.00 9,600.00
Aircon outlet 12 Pcs 600.00 7,200.00
Water Heater Outlet 12 Pcs 600.00 7,200.00
Panelboards( tap to pullbox only) 12 Pcs 2,100.00 25,200.00
2.3 Installation of wiring devices and panelboard -
Lighting fixtures 478 Pcs 60.00 28,680.00
Switch oulet 48 Pcs 162.00 7,776.00
Convenience outlet 64 Pcs 162.00 10,368.00
Acu outlet 12 Pcs 300.00 3,600.00
Water Heater Outlet 12 Pcs 300.00 3,600.00
Panelbords 12 Pcs 1,500.00 18,000.00
Sub-total 492,384.00
3.0 FOURTH FLOOR
3.1 Roughing ins( including boxes)
Lighting outlet 513 Pcs 300.00 153,900.00
Siwitch outlet 46 Pcs 300.00 13,800.00
Convenience outlet 61 Pcs 360.00 21,960.00
Aircon outlet 12 Pcs 1,320.00 15,840.00
Water Heater Outlet 12 Pcs 1,320.00 15,840.00
Panel board( tap to pullbox only) 12 Pcs 2,700.00 32,400.00
3.2 Wiring System (including termination) -
Lighting outlet 513 Pcs 240.00 123,120.00
Switch outlet 46 Pcs 240.00 11,040.00
Convenience outlet 61 Pcs 150.00 9,150.00
Aircon outlet 12 Pcs 600.00 7,200.00
Water Heater Outlet 12 Pcs 600.00 7,200.00
Panelboards( tap to pullbox only) 12 Pcs 2,100.00 25,200.00
3.3 Installation of wiring devices and panelboard -
Lighting fixtures 513 Pcs 60.00 30,780.00
Switch outlet 46 Pcs 162.00 7,452.00
Convenience oulet 61 Pcs 162.00 9,882.00
Acu outlet 12 Pcs 300.00 3,600.00
Water Heater Outlet 12 Pcs 300.00 3,600.00
Panelboards 12 Pcs 1,500.00 18,000.00
Sub-total 509,964.00
4.0 FIFTH FLOOR
4.1 Roughing ins( including boxes)
Lighting outlet 513 Pcs 300.00 153,900.00
Siwitch outlet 46 Pcs 300.00 13,800.00
Convenience outlet 61 Pcs 360.00 21,960.00
Aircon outlet 12 Pcs 1,320.00 15,840.00
Water Heater Outlet 12 Pcs 1,320.00 15,840.00
Panel board( tap to pullbox only) 12 Pcs 2,700.00 32,400.00
4.2 Wiring System (including termination) -
Lighting outlet 513 Pcs 240.00 123,120.00
Switch outlet 46 Pcs 240.00 11,040.00
Convenience outlet 61 Pcs 150.00 9,150.00
Aircon outlet 12 Pcs 600.00 7,200.00
Water Heater Outlet 12 Pcs 600.00 7,200.00
Panelboards( tap to pullbox only) 12 Pcs 2,100.00 25,200.00
4.3 Installation of wiring devices and panelboard -
Lighting fixtures 513 Pcs 60.00 30,780.00
Switch outlet 46 Pcs 162.00 7,452.00
Convenience oulet 61 Pcs 162.00 9,882.00
Acu oulet 12 Pcs 300.00 3,600.00
Water Heater Outlet 12 Pcs 300.00 3,600.00
Panelboards 12 Pcs 1,500.00 18,000.00
Sub-total 509,964.00
5.0 TESTING AND COMMISSIONING
Testing and Commissioning 1 Lot 75,000.00 75,000.00
Sub-total 75,000.00
GRAND TOTAL: 2,076,024.00

TERMS AND CONDITIONS:


1. Fifty percent (50%) down payment. Fifty percent (50%) upon job completion.
2. Completion of job shall be ninety (90) calendar days upon receipt of your purchase order and down payment.
3. Additional works other than the above subject shall be affected only upon your written authority and any
4. This proposal is valid within two (2) weeks only and is subject to change thereafter.

In the event that this proposal is agreeable to you, please indicate your conformity hereto by signing the space

SUBMITTED BY: ENGR. MIGUEL A. DELEON / ENGR. ROMY MARTINEZ CONFORME: