Professional Documents
Culture Documents
Chapter Three
Chapter Three
CHAPTER THREE
CLASSIFICATION AND TYPES OF HYDROPOWER DEVELOPMENT
Contents
The three basic elements are necessary in order to generate power from water:
Means of creating head, structure for water storage and/or diversion like a dam or a
barrage (weir).
A conduit to convey water, head race and tail race
A power station
1
Natnael Sitota Sinta
The diversion could be using a canal (Open flow diversion system) and a penstock.
The diversion tunnel and a penstock (Pressure Diversion System)
It consists of a long system of water conduits.
Classification and classification basis
Hydropower plants exhibits a great deal of variety and could be classified on the basis of:
2
Natnael Sitota Sinta
3
Natnael Sitota Sinta
4
Natnael Sitota Sinta
Water enters the power house through an intake structure incorporating some or all of the
following.
Entrance flume separated by piers and walls for each machine unit
The appurtenances of the entrance structure are the sill, fine rack or screen and
gate
Turbine chamber: scroll case with turbine
Concrete or steel draft tube
Power house building
5
Natnael Sitota Sinta
The dam with its appurtenance structures like spillway, energy dissipation
arrangements etc.
The intake with racks, stop logs, gates & ancillaries
The penstock conveying water to the turbine with inlet valve & anchorage
The main power house with its components
6
Natnael Sitota Sinta
7
Natnael Sitota Sinta
8
Natnael Sitota Sinta
9
Natnael Sitota Sinta
10
Natnael Sitota Sinta
Seasonal peaking
Short term peaking
This involves turbine operating for a few hours each day
To meet daily peaks
The recovery pumping during the early morning hours when energy loads
are lowest and cheap dump power is available
Weekly peaking
This requires operating turbines in generating mode to meet several peak
loads during the workweek.
Refilling the upper reservoir to a degree each day but gradually drawing down
the upper reservoir during the week.
Major recovery pumping during the weekend when loads are low
This requires relatively large reservoirs.
Seasonal peaking
Seasonal peaking would require very large upper reservoir storage
To provide longer generator operating during seasonal peaks
The recovery pumping would take large blocks of dump power
Site selection
11
Natnael Sitota Sinta
Storage of water: When the kinetic energy of water is low it is preferable to have the
reservoirs to collect the water for use of electricity production. The output of a
hydraulic plant will not be uniform if the available water is not uniform. The wide
variation of rainfall during the year makes it necessary to have the reservoirs. The
storage capacity of water is calculated by mass curve. The capacity of a plant is based
on the water energy available taking into account the losses due to evaporations and
percolation. Storage arrangements require topographical and geological investigations
so that natural foundations can be used to the best advantage. The storage reservoir
may be located near the power plant or some distance away from it.
Head of Water: The availability of head depends on the topography of the area. High
head means high potential energy. An increase in effective head reduces the quantity
of water to be stored and handled by penstock, screens and turbines and therefore the
capital cost of plant is reduced. The level of water in the reservoir for a proposed
plant should always be within limits throughout the year to maintain a constant head.
To get a most economical and effective head, it is necessary to consider all possible
factors which affect it and do a detail study.
Distance from power stations to the load centers: Most of the time the electric
power generated in hydroelectric power plant has to be used at some considerable
distance from the site of plant. The routes of transmission line and distance have to be
carefully considered to make the power generation economically viable. The cost of
erection of transmission line and its maintenance will depend on the route selected
and the length of the line.
Accessibility of site: Good access to the site is a desirable factor. This factor is very
important if the generated power is to be utilized at or near the plant site. The
transport facility must also be given due consideration. Construction of hydro power
project involves transport of huge amount of building materials, earth moving
equipment, electro mechanical equipment. The site should be such that it is possible
to construct new roads/railways lines if not already existing.
Geological investigation: Geological investigations are needed to see that the
foundation rock for the dam and other structures is firm, stable, impervious and
12
Natnael Sitota Sinta
strong enough to withstand water thrust and other stresses. The area should be free
from earthquake.
Sedimentation: The capacity of storage reservoir is reduced due to gradual
deposition of silt. Silt may also cause damage to the turbine blades. Silting from
forest cover areas is negligible. Regions subject to violent storms and not protected by
vegetation contribute lots of sill to the run off. Sometime this factor alone may render
an otherwise suitable site unsuitable.
Environmental Effects: Hydro projects submerge huge areas. This may involve
forest, fertile lands, and villages. The site selected should ensure safe and pleasing
surroundings, avoid health hazards and preserve important cultural and historic
aspects of the area.
Plant capacity: It is the capacity of the plant with respect to available, head, discharge,
and efficiency.
Installed capacity (Economical plant capacity): The plant capacity, which is
economically viable.
It is also defined as the maximum power, which can be developed by all generators of
the plant at the plant at the normal head and with full flow.
For selection of installed capacity, benefits from the project with different possible
installed capacitates are evaluated
Optimum installed capacity is selected after carrying out incremental analysis for the
most attractive alternative and also considering the system load factor (LF)
In addition, cost of generation from alternate sources such as wind energy, geothermal
turbines, and hydro are worked out.
The least cost of energy from among these options is adopted for evaluating the benefits
of the installation
Turbine selection and plant capacity determination require that rather detail information
has been determined on head and possible plant discharge. In theoretical sense, the
energy output, E, can be expressed mathematically as plant output or annual energy in a
functional relation as:
13
Natnael Sitota Sinta
The installed capacity is determined by equating the marginal cost and benefits for that
project, while determining the fixed cost of the project is assumed to be constant.
Let: Analyze marginal benefit and cost for 1Kw installation. Assuming Y% of the duration
corresponds to the best installed capacity for 1Kw power generation then
14
Natnael Sitota Sinta
[ ]
[ ]
Marginal benefit
[ ]
Marginal cost
[ ]
Now equating marginal cost and benefit, the value of “Y” can be obtained.
The power corresponding to Y% of tie in power duration curve is the best installed
capacity of the project.
15
Natnael Sitota Sinta
A step by-step process for this procedure is presented in a flow diagram of Figure below
4. Estimate head loss through hydro systems. This will formula is used
vary with penstock and draft tube
𝐻𝐼
𝑄𝑖 𝑄𝐶
5. Compute a net head for each of the flows 𝐻𝐶
characterized. Note: as river flows increase, tail water
rises and reduces net head
Where
6. Estimate plant efficiency. This can be made Qi = plant discharge at the percent exceedance
constant for pre-feasibility level design
QC = plant discharge at design full gate capacity
7. Choose a wheel or plant capacity flow. This full-gate Hi = net head at the percent exceedance being
flow will be limited by runner diameter and selected
penstock size studied
HC = net head at the percent exceedance at which
8. Compute plant discharge at all flow values for each
exceedence percentage. Note: at river flows greater flow in the river is at full design gate magnitude
than plant capacity the plant discharge may be less
than depending on the net head
16
Natnael Sitota Sinta
A river does not carry the same quantity of water through the year.
In general, we observe high flow in summer and low flow in winter and on the other hand,
the water demand is high in winter and low in summer.
A water supply, irrigation, or hydropower project drawing water directly from a river
may, therefore, be unable to satisfy the demands of it consumers during low flows.
Therefore, the regulation of the stream flow is required to meet the demands. This
regulation is possible by constructing reservoirs in the stream.
Reservoirs: are man-made structures that created to store water during times of excess
flow and supply if from storage when the demand exceeds the inflow.
When the total supply of water (ΣS) is sufficient to meet the total demand (ΣD) during a
specified period of time, the water storage is required when S<D
Characteristics of reservoir: Storage zones 1. Active storage.
2. Inactive storage.
3. Live storage.
4. Dead storage.
5. Flood storage.
6. Reservoir capacity: gross capacity of
reservoir.
7. Retention water level; top water level; normal
top water level; full supply level; normal
water level.
8. Flood surcharge; surcharge
9. Maximum water level; top of joint use (part
of reservoir capacity including both surcharge
and the empty part of active storage, assigned
to flood control or conservation depending on
the time of year.
10. Minim operation level; top of inactive storage
11. Freeboard
17
Natnael Sitota Sinta
The capacity of the reservoir is very important since the main function of the
reservoir is the storage of the water.
The desired yield, which is the amount of water delivered from a reservoir to meet
downstream requirements, must be available most of the time.
For an ideal reservoir site:
Suitable dam site
Adequate capacity with small submergence of land and other properties
Sufficient impervious and sound formation (bed and side) (reservoir basin should
be water tight)
Deep and narrow valley (less evaporation, low cost of expropriation)
The cost of real estate for the reservoir (Road and dwelling location) must be as
small as possible
Tributary areas which are unusually productive of sediment should be avoided is
possible
The quality of stored water must be satisfactory for its intended use
The reservoir banks and adjacent hill slope should be stable, unstable banks will
contribute large amount of soil material to the reservoir
After the determination of location of a reservoir, a special topographic map (1:5000
scaled) of the reservoir area is obtained with suitable contour intervals and
Elevation - Area Curve, and
Elevation – Storage Curve are obtained
18
Natnael Sitota Sinta
19
Natnael Sitota Sinta
Safe Yield (Firm Yield): The amount of water that is supplied for a critical period. It
is a guaranteed amount during this critical period.
Critical Period: The duration of lowest flow observed in the records of the stream.
Depending upon the length of the flow critical period may change so the safe
yield.
Yield is not calculated certainly. The probability must be used.
During the periods of high flow there will be extra available water, more than the safe
yield which is called secondary yield.
Average Yield: The arithmetic average of the safe and secondary yields over a long
period.
There is a risk involved for a reservoir.
The amount of risk depends on the purpose of the reservoir.
Target Yield: The yield determined based on the estimated demands for a reservoir.
For the determination of reservoir capacity, the critical period must be determined
first.
A long period of observed flow is required.
When short period of observed flows or no observations area available stochastic
methods are used to generate synthetic flows that has the same statistical properties
such as mean, variance, correlations etc.
The required capacity for a reservoir can be determined by the following methods:
Mass Curve Analysis (Ripple diagram method)
1. Determination of reservoir capacity for a known yield
2. Determination of yield from a known reservoir capacity
Sequent Peak Analysis
Operation Study
Other Approaches (Stochastic Methods and Optimization Analysis etc…)
1. Mass Curve Analysis (Ripple Diagram Method, 1883)
One of the most widely used methods. Used to determine active storage capacity.
Inflow hydrograph for stream at the dam site has been plotted.
If the flow is the daily or monthly discharge then the area under the curve up to a certain
time will be the volume of runoff for that period.
20
Natnael Sitota Sinta
Mass curve is continuously raising curve, as it is the plot of the accumulated inflow.
Period of no inflow would be represented by the horizontal lines on the mass inflow
curve. If there is high rate of flow the curve rise steeply. Thus relatively dry periods
are indicated as concave depressions on the mass curve.
The slope of the mass curve at any time is a measure of the inflow rate at that time (gives
the discharge at that time on the hydrograph)
Assumptions:
Demand is constant, constant rate of withdrawal, which the mass curve of demand
will be a straight line having a slope equal to the demand rate
The year repeats itself continuously
S p m
21
Natnael Sitota Sinta
22
Natnael Sitota Sinta
Note: It may also be noted that a demand line (the plotted tangents), when extended forward,
must intersects the mass curve. If it does not, the reservoirs will no refill
Note: When the demand curve is not a straight line, then the two mass curves are superimposed
over each other in such a way that their origin and axis coincide. The larger ordinate between the
two, gives the required storage capacity.
23
Natnael Sitota Sinta
The graphical approach is quite satisfactory if the reservoir releases are constant during
the period of analysis. Also, the demand rate is usually not a straight line, since the
demand (out flow) generally becomes non-uniform due to seasonal variations in the
demand.
When reservoir releases vary, the sequent-peak analysis is recommended.
2. Fixation of Reservoir Capacity Analytically using Sequent Peak Analysis
Sequent Peak Analysis is more suitable when the data of long observation periods or long
generated data are used, or when the demand is not constant
Find the maximum cumulative deficit over an adjacent sequence of deficit periods and
determine the maximum of these cumulative deficits.
Inflow sequence is assumed to repeat and the analysis is carried out over two cycles,
when necessary.
Two cycles are required in case the critical period lies toward the end of an inflow,
sequence.
How much minimum storage is required that corresponds to the maximum deficit that
occurs. Differences between inflows (S) and demands
(D) are calculated and their summations
obtained.
Σ(S-D) values are plotted against time as
shown in the figure.
On this plot the first peak value and next larger
peak (sequent peak) are determined.
The storage required between these two points
is the difference between the first peak and the
lowest point in this period.
This process is repeated for all the peaks in the
record period as shown in the figure also. The
maximum of the storage values is the required
capacity.
If the record period or generated data sequence is very long, the graphical solution may
be time consuming
In that case and analytical solution procedure may be applied for the analysis and it can
be solved easily using a computer
24
Natnael Sitota Sinta
In this way, the required storage Vt at the end of a period t can be expressed as:-
𝑲 𝑹𝒕 𝑸𝒕 𝒊𝒇 𝑷𝒐𝒔𝒆𝒕𝒊𝒗𝒆
𝑲𝒕 { 𝒕
𝟎 𝑶𝒕𝐡𝒆𝒓𝒘𝒊𝒔𝒆
At the beginning of the analysis, initially Kt-1 is set to zero and calculations continue to
find Kt values for up to twice the length of the record period.
The maximum of all the calculated values of Kt is the required storage capacity.
25
Natnael Sitota Sinta
Principal parameters necessary in making hydro- power studies are water discharge (Q) and
hydraulic head (H).
The measurement and analyses of these parameters are primarily hydrologic problems.
Thus determination of the potential head for a proposed hydropower plant is a surveying
problem that identifies elevations of water surfaces as they are expected to exist during
26
Natnael Sitota Sinta
operation of the hydro plant. Good contour maps may be sufficient to determine the value
for the hydraulic head.
27
Natnael Sitota Sinta
Neglect in any of these assessments leads to flaws in optimization and design, eventually
reflected in the project’s feasibility
Very critical information during project planning and optimization are the available flow
and head.
Very critical value, based on complex hydrological analysis Very critical value, but relatively easy to determine
easy to determine with topographic survey.
Too high Q : HPP oversized, expected annual
d
generation not achieved, revenue stream smaller Wrong Hn: leads to mismatch of turbine
(strong impact).
than required, financial viability critical.
Too low Qd: HPP dimensioned too small, more
attractive development solution possible.
Wrong Qd: not matching peak efficiency point of
installed turbine. development cycles:
Hydropower
Planning,
Implementation and
Operation and Maintenance
28
Natnael Sitota Sinta
29
Natnael Sitota Sinta
Site reconnaissance Pre-feasibility and feasibility Detailed design Only micro hydro
Altimeter Theodolite, total station
Additional topographic Clinometer/hypsometer
Hypsometer Stereoscopic aerials, and compass
survey of specific areas,
triangulation and control
if required
point survey
The studies to be carried out:
Resources studies:
Preparation/updating of resources inventories
Preparation/updating of resources rankings
Site specific studies:
1. Reconnaissance studies
2. Pre-feasibility studies
3. Feasibility studies
4. Definite plan or design studies
Resources studies:
30
Natnael Sitota Sinta
The identified project sites are ranked according to size, cost, electric demand, etc.
Preparation of resources inventories and their updating is a continuous process and
should not be stopped at any time.
Project investigation, planning and design are normally organized in several consecutive studies
which are listed here in increasing order of detail, importance and reliability
1. Reconnaissance studies
Are made to find potential energy sources and to estimate the energy available in
streams, and may not be too site specific
This study uses contour maps or digital elevation models to determine heads available
in streams and water flow can be estimated using parametric curves of the flow
duration in the streams
Some site specific resource studies may use mean annual runoff or a characteristics
such as the 95% of time flow available for energy development
The details and data requirements of these studies are regional in nature.
Accuracy of these data as a requirement is less.
Carried out for specific purpose such as: to establish the available potential in a
district.
They are concerned with project selection from inventories of resources.
The main objectives may be such as:
Find potential energy sources and Estimate energy available in a stream
Assessment of demand or define electric power need.
Selection of candidate projects from the resources inventories which will meet the
electric power demand.
Investigation of candidate projects & project alternatives to the best technical
level.
Technical ranking of candidate projects should be prepared and well recorded.
Estimation of preliminary cost and implementation schedule
Selection of a suitable project from the list of investigated candidate projects.
May not be site specific
31
Natnael Sitota Sinta
32
Natnael Sitota Sinta
33
Natnael Sitota Sinta
3. Feasibility study:
Are carried out to determine the technical, economical and environmental viability of
a project.
This phase of investigation consists of a detailed study which is directed towards the
ultimate permission, financing, final design and construction of the project under
investigation.
Made to formulate a specific project.
Assess the desirability of implementing hydropower development.
Presents the project layout as a result of the evaluation of design alternatives
Calculates the average annual electricity generation and the revenues
Gives information how the budgetary investment cost was determined
Evaluates the economic and financial profitability and its sensitivity against in the
assumptions
Assesses the environmental and social impacts
The main part of feasibility studies include
Data collection
Distribution Topography
Power market Geology
Tariffs, Socioeconomic data Seismic
Population Environment
Income Meteorology
Hydrology Infrastructure
Project feasibility estimation:
Power and energy estimation Seismic studies
Power system studies Construction materials
Water resources studies Existing infrastructure
Geology and foundation conditions
Layout optimization:
Project layout Auxiliary equipment
Sediment & control measures Transmission planning
Number and size of units
Environmental studies:
Assessment of environmental disturbance and their mitigation measures
34
Natnael Sitota Sinta
35
Natnael Sitota Sinta
Implementation phase:
Project implementation is a multidisciplinary job which include:
Approval and appropriation of funds
Pre-qualification and hiring of consultants
Detailed design
Preparation of tender/contract documents
Pre-qualification of contractors
Preparation of construction design and engineering design
Preparation of operation manual
Construction supervision
Construction of civil works
Supply and erection of equipment
Testing, commissioning and commercial operation
Preparation of completion report
36