CMA663 

TEST P6 JULY2023
AP246 6F

Q1) Develop a Work Program based on Planning Sheet Below (set calendar as 7 working days & 8 hours per day)
Q2) You are required to 
i) create a new project folder under your  CMA663 MAC 2023 EPS,Project ID RH_NAME (ie RH_AIMI) and 
     Project name is your GROUP_FULL NAME (ie 6H_AIMI ASHIKIN)
ii) a WBS, activity, duration
ii) assign resources by using any folder of resources (if any) under resources, or create new resources and 
iv) insert the cost in each activity 
v) create a suitable activity network diagram (relationship) based on date given

RUANG HALLSTAYTION
Activity Duration Start Date Finish Date Manpower Machine Cost
Preliminaries 
Site Clearance 3 04‐Jul‐22 06‐Jul‐22 1 General Worker 1 Backhoe, 3 Dumptruck, 1 Bulldozer RM6,500.00
Temporary Works 6 07‐Jul‐22 12‐Jul‐22 2 General Workers 1 Backhoe RM12,000.00

SubStructure
Piling Work 24 13‐Jul‐22 05‐Aug‐22 1 Piler 1 Piling Rig RM56,000.00
Pilecap 18 06‐Aug‐22 23‐Aug‐22 RM26,800.00
Ground Beam & Slab 21 18‐Aug‐22 07‐Sep‐22 6 Barbender, 6 Carpenter, 1 gang  2 Barbending Cutting Machine,  RM32,500.00
Concretor (4man), 3 BRC Layer 1 Cutting Table, 1 Mobile Crane

Superstructure
Column 15 24‐Aug‐22 07‐Sep‐22 RM12,000.00
Roof Beam & Slab 6 08‐Sep‐22 13‐Sep‐22 8 Barbender, 8 Carpenter, 1 gang  2 Barbending Cutting Machine,  RM17,000.00
Concretor (4man) 2 Cutting Table, 1 Mobile Crane

Roofing Work
Roof Structure 8 20‐Sep‐22 27‐Sep‐22 4 roofer 1 Mobile Crane RM45,000.00
Roof Cover 6 23‐Sep‐22 28‐Sep‐22 4 roofer 1 Mobile Crane RM33,000.00

Architectural Works
Brickwork 24 20‐Sep‐22 13‐Oct‐22 6 Bricklayer 1 Forklift, 1 Cement Mixer RM38,000.00
Door & Window Frame 8 06‐Oct‐22 13‐Oct‐22 2 Door & window Installer RM2,500.00
Plastering Work 14 02‐Oct‐22 15‐Oct‐22 6 Plasterer 1 Cement mixer RM46,000.00
Ceiling Finishes 18 16‐Oct‐22 02‐Nov‐22 3 Ceiling Installer RM27,000.00
Glazing Works 12 22‐Oct‐22 02‐Nov‐22 4 Architectural Workers RM35,000.00
Floor Finishes 12 03‐Nov‐22 14‐Nov‐22 4 Screeder RM18,000.00
Painting 10 15‐Nov‐22 24‐Nov‐22 4 Painter RM11,000.00
Door & Window 6 22‐Nov‐22 27‐Nov‐22 2 Door & window Installer RM8,500.00
Sanitary Fittings 3 25‐Nov‐22 27‐Nov‐22 1 Plumber RM6,200.00

Infrastructure
M&E External Works 16 03‐Nov‐22 18‐Nov‐22 3 M&E Workers 1 Excavator, 1 Backhoe, 1 Roller  RM17,000.00
Compactor
Roadwork 24 19‐Nov‐22 12‐Dec‐22 2 Skilled Worker, 1 Semi‐skilled 1 Backpusher, 1 Roller Compactor,  RM37,000.00
1 Paver Machine, 1 Vibro Roller 
Compactor, 1 Thermoplastic Machine
Landscape 12 01‐Dec‐22 12‐Dec‐22 2 Skilled Worker, 1 General Worker 1 Backhoe RM13,000.00

RM500,000.00