Request for Inspection/Test

(RFI)
Project NORTH FIELD EXPANSION EPC-2 RFI No. NFXP2-DAP-ST-RFI-03305

Subcontractor DAI DUNG Request Date 19/May/2023

Discipline STEEL STRUCTURE Inspection Date 20/May/2023 Time 14:00

Location LONG AN FACTORY System

ITP No. NFXP2-DAP-ST-ITP-00001 Rev. 0 ITP Step No. 6.1

Inspection Point Sub-con. H Contractor W COMPANY S 3rd Party -

No. Inspection Items Quantity Remarks

Check the surface preparation for item:[LOT N3] TBOG COMPRESSOR SHELTER ;
1 [JBOG] PIPERACK - STEEL STRUCTURE ;[LOT N & N3] PIPEWAY (INCL. DO 501, pcs
502);HP CORRIDOR PIPE BRIDGE 1

No. Attachments Rev. Remarks

1 Member list -

2 Approved Drawing -

Reason for RFI Rejection / Cancellation


1. Poor Workmanship 2. Use of Non-approved Material 3. Use of Wrong material
4. Deviation from DWG/SPC./MS 5. Deviation from ITP 6. Unacceptable Test Procedure
7. Incomplete Work 8. Safety Issues 9. Test Equipment Unavailability
10. Weather Conditions 11. Test Crew Not-Available 12. Pre-Activity Comment Not-Cleared
13. Documentation Unavailability 14. Material Not-Available 15. Other
Comments

Accepted □ Accepted with comments □ Rejected □ Cancelled □

Subcontractor Construction QA/QC COMPANY

Designation QC Inspector

Name

Date

Signature
Request for Inspection/Test
(RFI)
Project North Field Expansion EPC-2 RFI No. NFXP2-DAP-ST-RFI-03305

Subcontractor Dai Dung Corp. Request Date 19/May/2023

Discipline Steel Structure Inspection Date 20/May/2023 Time 14:00

Member list-LA4

No. Item no. Drawing No. Rev Q.ty Unit Inspection Result Remarks

1 LN3-TCS-BE049-8/11 NFXP2-DAP-ST-LN3-TCS-AS-BE049 0 1 PC £ Accepted £ Rejected


2 LN3-TCS-BE067-1/3 NFXP2-DAP-ST-LN3-TCS-AS-BE067 0 1 PC £ Accepted £ Rejected
3 LN3-TCS-BE085-7/14 NFXP2-DAP-ST-LN3-TCS-AS-BE085 0 1 PC £ Accepted £ Rejected
4 LN3-TCS-BE085-13/14 NFXP2-DAP-ST-LN3-TCS-AS-BE085 0 1 PC £ Accepted £ Rejected
5 LN3-TCS-BE111-6/8 NFXP2-DAP-ST-LN3-TCS-AS-BE111 0 1 PC £ Accepted £ Rejected
6 LN3-TCS-BE153-1/2 NFXP2-DAP-ST-LN3-TCS-AS-BE153 1 1 PC £ Accepted £ Rejected
7 LN3-TCS-BE205-1/4 NFXP2-DAP-ST-LN3-TCS-AS-BE205 0 1 PC £ Accepted £ Rejected
8 LN3-TCS-BE205-2/4 NFXP2-DAP-ST-LN3-TCS-AS-BE205 0 1 PC £ Accepted £ Rejected
9 LN3-TCS-CB003-1/8 NFXP2-DAP-ST-LN3-TCS-AS-CB003 1 1 PC £ Accepted £ Rejected
10 LN3-TCS-CB003-3/8 NFXP2-DAP-ST-LN3-TCS-AS-CB003 1 1 PC £ Accepted £ Rejected
11 LN3-TCS-CB003-4/8 NFXP2-DAP-ST-LN3-TCS-AS-CB003 1 1 PC £ Accepted £ Rejected
12 LN3-TCS-CB003-6/8 NFXP2-DAP-ST-LN3-TCS-AS-CB003 1 1 PC £ Accepted £ Rejected
13 LN3-TCS-CB004-3/4 NFXP2-DAP-ST-LN3-TCS-AS-CB004 1 1 PC £ Accepted £ Rejected
14 LN3-TCS-CB005-1/1 NFXP2-DAP-ST-LN3-TCS-AS-CB005 1 1 PC £ Accepted £ Rejected
15 LN3-TCS-CB006-1/1 NFXP2-DAP-ST-LN3-TCS-AS-CB006 1 1 PC £ Accepted £ Rejected
16 LN3-TCS-CB009-1/2 NFXP2-DAP-ST-LN3-TCS-AS-CB009 1 1 PC £ Accepted £ Rejected
17 LN3-TCS-CO018-1/1 NFXP2-DAP-ST-LN3-TCS-AS-CO018 1 1 PC £ Accepted £ Rejected
18 LN3-TCS-CO020-1/1 NFXP2-DAP-ST-LN3-TCS-AS-CO020 1 1 PC £ Accepted £ Rejected
19 LN3-TCS-CO022-1/1 NFXP2-DAP-ST-LN3-TCS-AS-CO022 0 1 PC £ Accepted £ Rejected
20 LN3-TCS-CO023-1/1 NFXP2-DAP-ST-LN3-TCS-AS-CO023 1 1 PC £ Accepted £ Rejected
21 LN3-TCS-CO044-1/1 NFXP2-DAP-ST-LN3-TCS-AS-CO044 1 1 PC £ Accepted £ Rejected
22 LN3-TCS-RF002-2/3 NFXP2-DAP-ST-LN3-TCS-AS-RF002 1 1 PC £ Accepted £ Rejected
23 LN3-TCS-RF013-2/2 NFXP2-DAP-ST-LN3-TCS-AS-RF013 1 1 PC £ Accepted £ Rejected
24 LN3-TCS-RF014-2/2 NFXP2-DAP-ST-LN3-TCS-AS-RF014 1 1 PC £ Accepted £ Rejected

Subcontractor Construction QA/QC COMPANY

Designation QC Inspector

Name

Date

Signature
Request for Inspection/Test
(RFI)
Project North Field Expansion EPC-2 RFI No. NFXP2-DAP-ST-RFI-03305

Subcontractor Dai Dung Corp. Request Date 19/May/2023

Discipline Steel Structure Inspection Date 20/May/2023 Time 14:00

Member list-LA4

No. Item no. Drawing No. Rev Q.ty Unit Inspection Result Remarks

1 RD-HP-CPB1-BE1014-1/1 NFXP2-DAP-ST-RD-HP-CPB1-AS-BE1014 0 1 PC £ Accepted £ Rejected


2 RD-HP-CPB1-BR1002-1/1 NFXP2-DAP-ST-RD-HP-CPB1-AS-BR1002 0 1 PC £ Accepted £ Rejected
3 RD-HP-CPB1-CO1002-1/1 NFXP2-DAP-ST-RD-HP-CPB1-AS-CO1002 0 1 PC £ Accepted £ Rejected
4 RD-HP-CPB1-CO1008-2/2 NFXP2-DAP-ST-RD-HP-CPB1-AS-CO1008 0 1 PC £ Accepted £ Rejected

Subcontractor Construction QA/QC COMPANY

Designation QC Inspector

Name

Date

Signature
Request for Inspection/Test
(RFI)
Project North Field Expansion EPC-2 RFI No. NFXP2-DAP-ST-RFI-03305

Subcontractor Dai Dung Corp. Request Date 19/May/2023

Discipline Steel Structure Inspection Date 20/May/2023 Time 14:00

Member list-LA4

No. Item no. Drawing No. Rev Q.ty Unit Inspection Result Remarks

1 LN3-PW-BE097-1/1 NFXP2-DAP-ST-LN3-PW-BE097 0 1 PC £ Accepted £ Rejected


2 LN3-PW-HB033-1/3 NFXP2-DAP-ST-LN3-PW-HB033 0 1 PC £ Accepted £ Rejected
3 LN3-PW-HB033-2/3 NFXP2-DAP-ST-LN3-PW-HB033 0 1 PC £ Accepted £ Rejected
4 LN3-PW-HB039-2/2 NFXP2-DAP-ST-LN3-PW-HB039 0 1 PC £ Accepted £ Rejected

Subcontractor Construction QA/QC COMPANY

Designation QC Inspector

Name

Date

Signature
Request for Inspection/Test
(RFI)
Project North Field Expansion EPC-2 RFI No. NFXP2-DAP-ST-RFI-03305

Subcontractor Dai Dung Corp. Request Date 19/May/2023

Discipline Steel Structure Inspection Date 20/May/2023 Time 14:00

Member list-LA4

No. Item no. Drawing No. Rev Q.ty Unit Inspection Result Remarks

1 JB-PR-BE902-1/2 NFXP2-DAP-ST-JB-PR-AS-BE902 0 1 PC £ Accepted £ Rejected


2 JB-PR-BE902-2/2 NFXP2-DAP-ST-JB-PR-AS-BE902 0 1 PC £ Accepted £ Rejected
3 JB-PR-BE939-1/6 NFXP2-DAP-ST-JB-PR-AS-BE939 0 1 PC £ Accepted £ Rejected
4 JB-PR-BE939-4/6 NFXP2-DAP-ST-JB-PR-AS-BE939 0 1 PC £ Accepted £ Rejected
5 JB-PR-BE939-5/6 NFXP2-DAP-ST-JB-PR-AS-BE939 0 1 PC £ Accepted £ Rejected
6 JB-PR-BE939-6/6 NFXP2-DAP-ST-JB-PR-AS-BE939 0 1 PC £ Accepted £ Rejected
7 JB-PR-LD001-1/1 NFXP2-DAP-ST-JB-PR-AS-LD001 0 1 PC £ Accepted £ Rejected
8 JB-PR-LD002-1/1 NFXP2-DAP-ST-JB-PR-AS-LD002 0 1 PC £ Accepted £ Rejected
9 JB-PR-LD007-1/1 NFXP2-DAP-ST-JB-PR-AS-LD007 0 1 PC £ Accepted £ Rejected
10 JB-PR-LD009-1/1 NFXP2-DAP-ST-JB-PR-AS-LD009 0 1 PC £ Accepted £ Rejected
11 JB-PR-LD013-1/1 NFXP2-DAP-ST-JB-PR-AS-LD013 0 1 PC £ Accepted £ Rejected
12 JB-PR-LD015-1/1 NFXP2-DAP-ST-JB-PR-AS-LD015 0 1 PC £ Accepted £ Rejected
13 JB-PR-LD018-1/1 NFXP2-DAP-ST-JB-PR-AS-LD018 0 1 PC £ Accepted £ Rejected

Subcontractor Construction QA/QC COMPANY

Designation QC Inspector

Name

Date

Signature