INSPECTION DATE

20-Jul-23

PERMANENT WORK

LOCATION OF CSTS QC COMPANY INSPECTION INSPECTION


NO RFI NO QC INSPECTOR NAME ITEM / WORK TO BE INSPECTED TAG NO REASON
INSPECTION INVOLVEMENT INVOLVEMENT STATUS RESULT
Finishing inspection: Check completeness of structural concrete works
12 RFI-CIV020307M-LC01670 AR 9 HOLD POINT WITNESS Fahrul H. Baadila prior to proceed with backfilling activities for all item’s foundation : LIGHTING POLE ADD ACC
• Lighting Pole at AR 9
Physical verification of prefabricated precast :
13 RFI-CIV021401M-LC00459 AR 9 WITNESS SURVEILLANCE Fahrul H. Baadila X00-AR9-BOX-CUL-STA130 ADD ACC
• Box Culvert at AR9
Inspection on Precast Installation
• Check Position of Precast: Horizontal, vertical and Elevation
14 RFI-CIV021402M-LC00719 AR 9 WITNESS SURVEILLANCE Fahrul H. Baadila • Check the connection to main structure X00-AR9-BOX-CUL-STA130 ADD ACC
• Grout Placement Inspection for: :
• Box Culvert at AR9
Inspection during delivering fresh structural concrete :
15 RFI-CIV020305M-LC07346 AR 9 HOLD POINT WITNESS Fahrul H. Baadila X00-AR9-BOX-CUL-STA130 ADD ON GOING NOT READY
• Box Culvert at AR9
Inspection of subgrade and grade layer before laying fill material. :
16 RFI-CIV020101M-LC06132 AR 9 WITNESS WITNESS Fahrul H. Baadila X00-AR9-VDIT ADD ACC
• V-Ditch at AR-9
Check and verify cutting and bending of reinforce
rebar including,
X00-AR9-BOX-CUL-STA120-JB
17 RFI-CIV021202M-LC04369 AR 9 WITNESS SURVEILLANCE Fahrul H. Baadila - bending shape ADD ON GOING
X00-AR9-BOX-CUL-STA140-JB
- Size/length for :
• Box Culvert at AR9 NOT READY
Field inspection: check before concrete delivery/placement : X00-AR9-BOX-CUL-STA120-JB
18 RFI-CIV020304M-LC06012 AR 9 WITNESS WITNESS Fahrul H. Baadila ADD ON GOING
• Box Culvert at AR9 X00-AR9-BOX-CUL-STA140-JB
Inspection during delivering fresh structural concrete : X00-AR9-BOX-CUL-STA120-JB
19 RFI-CIV020305M-LC07347 AR 9 HOLD POINT WITNESS Fahrul H. Baadila ADD ON GOING
• Box Culvert at AR9 X00-AR9-BOX-CUL-STA140-JB
Field inspection: check before concrete delivery/placement :
X00-AR9-VDIT
20 RFI-CIV020304M-LC06013 AR 9 WITNESS WITNESS Fahrul H. Baadila • V-Ditch at AR-9 ADD ACC
X00-AR9-UDIT
• U-Ditch Type 1 at AR-9
Inspection during delivering fresh structural concrete :
X00-AR9-VDIT
21 RFI-CIV020305M-LC07348 AR 9 HOLD POINT WITNESS Fahrul H. Baadila • V-Ditch at AR-9 ADD ACC
X00-AR9-UDIT
• U-Ditch Type 1 at AR-9