Professional Documents
Culture Documents
EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.
LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.
SCHEDULED INSPECTION DATE & TIME ACTUAL INSPECTION DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIME
SAUDI ARAMCO USE ONLY
SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER WORK PERMIT REQUIRED?
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
A General Requirements:
The following Checklists have been completed:
A) SAIC-L-2090 was completed & Procedure has been accepted for Sch. Q, Att VI
this Special Process Control Procedure. Tables &
A1
B) SAIC-L-2091 is to be completed (UT) & calcs are acceptable. SAEP-311
C) SAIC-L-2092 & SAIC-L-2093 are (Procedure)
acceptable for Materials.
Design package for each hot tap includes fully dimensioned dwgs, a SAEP-311,
A2
materials list, Direct Charge Requisitions and welding procedures. Para. 5.2.2
Form 7627-ENG, "Hot Tap / Stopple & Reinforcement Calc Request" has SAEP-311,
B1
been initiated by the Responsible Engineer Para. 5.2.3.2
Form 7627-ENG, "Hot Tap / Stopple & Reinforcement Calc Request" &
SAEP-311,
B2 complete form 7235-ENG, "Hot Tap Data & Checklist" per App A.2 and
Para. 5.2.3.2
A.3 in Attachment 1. Verify Completion of these sections.
Mark the exact hot tap location & number (obtained from Form SA SAEP-311,
B5
7627-ENG) alongside each hot tap location. Field Walkdown! Para. 5.2.3.4
Review & concur with design package prior to the start of the SAEP-311,
C1
installation. Para. 5.4.1
Ensure that the connection is installed in accordance with the design SAEP-311,
C2
package Para. 5.4.2
Inspect and determine the minimum pipe wall thickness at the tie-in
weld areas by a continuous UT scan along the lines to be welded & SAEP-311,
C3
record this on the applicable form in Appendix A.1 of SAEP-311. Para. 5.4.3
Use SATR-NDT-2007 (See Attachment 1)
Page 1 of 18
Inspect the branch connection/split tee, before and during the
SAEP-311,
C6 installation, for compliance with the approved drawings and welding
Para. 5.4.6
procedures.
Page 2 of 18
SAUDI ARAMCO ID/PID - REV 0- 18-May-05 (Standards Cutoff - March 2013) Rev 7 31-Mar-13
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
Confirm that the hydrostatic test pressure for branch connection is SAEP-311,
C7
correct at the time of test, as prescribed in Sect 4 -Form SA 7627-ENG Para. 5.4.7
Verify that calibrated pressure gauges and relief valve are properly SAEP-311,
C8
installed for hydrotesting. Para. 5.4.8
If the hot tap is required for a stopple operation, the pipe roundness and
alignment of the stopple fitting must be checked and approved by the Hot
SAEP-311,
Tap & Stopple Unit. For stopple installation, make sure that the Hot Tap Unit
C11 Para. 5.2.3.5
conducts pipe roundness check to ensure that it meets the requirements
stipulated in Table-1 of section 9.7 and mark the exact location of the
stopple.
D Additional Pre-Welding Requirements … Agreed Upon Hold Points shall not be Bypassed
All work shall be in strict compliance with GI-0002.100, Work Permit System.
Note: Hot Work SAEP-311,
D1
Permit (Form SA 924-2) has been obtained and available on site, prior to Para. 7.1
starting work.
The proper safety and fire protection equipment is at site and in workable
SAEP-311,
D2 condition prior to the start of the job and that all relevant
Para. 7.2
personnel are notified of the scheduled hot work.
Page 3 of 18
SAUDI ARAMCO ID/PID - REV 0- 18-May-05 (Standards Cutoff - March 2013) Rev 7 31-Mar-13
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
If a potential exists for a Hydrogen Sulfide release (or other toxic gas)
at a work site, all personnel involved shall be provided with an SAEP-311,
D3
appropriate breathing apparatus. (GI-1780.001, "Atmosphere- Para. 7.3.1
Supplying Respirators").
SAEP-311,
E1
Para. 13.4.1
In cases where a pipeline has been cut or ingress of air has otherwise been
allowed, the air must be removed from the pipeline before welding can be
SAEP-311,
performed. One method of removing the air is by putting the line in service
E2
with an adequate flow rate to ensure that the air is displaced from the
Para. 13.4.2
pipeline. Once this has been achieved,
welding can proceed with or without flow.
Page 4 of 18
SAUDI ARAMCO ID/PID - REV 0- 18-May-05 (Standards Cutoff - March 2013) Rev 7 31-Mar-13
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
Inspect the branch connection/split tee, before and during installation, for
SAEP-311,
G1 compliance with the approved drawings and welding procedures.
Para. 5.4.6
Hold Point for Inspection to witness welding (approved WPS)
Power wire brush the area for attachment welds to remove all
traces of paint, rust and scale. (Excess UT couplant must be dry) Sch. Q, Att VI
The fit-up of the connection to the header shall provide for a Tables &
G2 standard pipe bevel and 1/16 inch minimum root gap. Install the nozzle or SAEP-311
boss connection using full penetration welds in the exact location shown on (Approved
the approved drawing, using a qualified welder and a CSD approved welding procedure)
procedure. Inspection Unit will verify proper weld joint fit-up.
Sch. Q, Att VI
Ensure that the nozzle connections are not welded on the inside unless the Tables &
G3 hot tap cutter is at least one pipe size smaller than the nozzle. The cutters SAEP-311
sometimes break if cut is made through a weld. (Approved
procedure)
Sch. Q, Att VI
Visually examination shall be completed from the root side to ensure proper Tables &
G4 penetration & fusion have been achieved. Use proper tools such as mini- SAEP-311
light & small mirrors. (Approved
procedure)
REMARKS:
NOTES:
1. Utilize attachments 1 & 2 for information specific to Pre-welding checkpoints. Inspector required reading for Safety includes SAEP-311.
2. SAES-L-052 is no longer utilized for Hot Taps. SAEP-311 is MANDATORY. SAEP-310 requirements may also be mandatory in the event
that damage assessment & Pressure Piping Considerations come into the picture due to Inspection Findings (HIC Damage, etc).
3. Utilize SATR-NDE-2007 for HOT TAP UT REPORT (Also in Attachment 1).
REFERENCE DOCUMENTS:
1- SAEP-311 -- Installation of Hot Tapped Connections, (17 March 2013)
2- SAES-W-011 -- Welding Requirements for On-Plot Piping, (4 October 2009)
3.-Schedule -"Q"- Attachment-IV (Table- Approved special procedure)
Page 5 of 18
MBER
ACTOR
RE-INSP DATE
Page 6 of 18
MBER
ACTOR
RE-INSP DATE
Page 7 of 18
MBER
ACTOR
RE-INSP DATE
P-311.
he event
Work Verified
Work Verified
Work Verified
ES N = NO F = FAILED
Page 8 of 18
SAUDI ARAMCO ID/PID - REV 0- 18-May-05 (Standards Cutoff - March 2013) Rev 7 31-Mar-13
SAEP-311 Appendix A - APPLICABLE FORMS for HOT TAP & STOPPLE INSTALLATION
SAUDI ARAMCO ID/PID - REV 0- 18-May-05 (Standards Cutoff -Mar 2013) Rev 7 31-Mar-13