You are on page 1of 2

NDB Project - Package IV Detailed Estimate for Pipe Culvert

Detailed Quantity Estimates For the Proposed Pipe Culverts -


3 Row 1000mm dia @ CH:21+255 (Reconstruction)
Bill No: 6.1
Ref. Dwg. No.:BC/ND/BD/2021/STR/PC (RC-3Rx1.0m) - 08
Length Breadth Units
Item Description Nos. Depth (m) Quantity
(m) (m)
6.1.1 Earthwork excavation in soils up to SDR by mechanical means for foundations of structures as per drawing and
technical specification including setting out, construction of shoring and bracing, removal of stumps and other deleterious
matter, dressing sides of bottom, back filling the excavation earth to the extent required etc., complete for finished item of
work as per MoRT&H (5th Revision) Specification Clause No. 304 and as directed by the Engineer-in-Charge .
For Face Wall 2 9.95 2.6 0.915 47.34
For Pipe Portion 1 10.766 5.09 0.535 29.32
Sub-Total 76.66
Add 0.34
Total 77 Cu.m.
6.1.2 Providing Vibrated Cement Concrete (1:3:6) mix using 40 mm size HBG crushed stone aggregate (Coarse aggregate
conforming to table 1000-1 and fine aggregate conforming to table 1000-2 of MoRT&H) including cost, conveyance of all
materials to site and labour charges, centering, machine mixing , laying, vibrating, curing etc., including all other
incidental and operational charges of all T&P etc., complete for finished item of work as per MoRT&H (5th Revision)
Specification Section Nos 1500, 1700 & 2100 and as directed by the Engineer-in-Charge for Levelling Course
Below Face Wall 2 9.95 2.60 0.15 7.76
Sub-Total 7.76
Add 0.24
Total 8 Cu.m.
6.1.3 Vibrated cement concrete M-15 Grade using 40 mm, 20 mm and 10 mm size HBG crushed stone aggregate (Coarse
aggregate conforming to table 1000-1 and fine aggregate conforming to table 1000-2 of MoRT&H) including cost and
conveyance of all materials to site and all labour charges, mixing using Concrete Batching Plant, laying in position,
compacting, Vibrating and curing including all other incidental and all other operational charges of T&P required etc.,
complete as per MoRT&H (5th Revision) Section Nos 1500, 1700, 2200 for Body Walls of HP Culverts

Face Wall straight portion 2 9.95 0.4 4.966 39.53


Tappering portion 2x1/2 9.95 2.000 4.966 98.81
Deduct for pipe portion 6X22/7x1/4 1.849 1.23 -13.18
Sub-Total 125.16
Add 0.84
Total 126 Cu.m.
6.1.4 Providing first class bedding with Granular material below the pipes of Hume pipe culverts suitably compacted /
rammed including cost and conveyance of materials to site etc., complete as per drawing and MoRT&H (5th Revision)
Specification Section No. 2900 and as directed by the Engineer-in-Charge .
Levelling coarse below pipe for bedding 1 10.766 5.09 0.535 29.32
Deduct for pipe portion 3 10.766 0.306 -9.88
Sub-Total 19.43
Add 0.57
Total 20 Cu.m.

Roads & Building Department,


Vax Consultants Pvt. Ltd. Government of Andhra Pradesh
NDB Project - Package IV Detailed Estimate for Pipe Culvert

Detailed Quantity Estimates For the Proposed Pipe Culverts -


3 Row 1000mm dia @ CH:21+255 (Reconstruction)
Bill No: 6.1
Ref. Dwg. No.:BC/ND/BD/2021/STR/PC (RC-3Rx1.0m) - 08
Length Breadth Units
Item Description Nos. Depth (m) Quantity
(m) (m)
6.1.5 Filling in between body walls with Gravel including cost, conveyance of all materials to site etc., complete as per
Clause 710.1.4 of IRC:78 and as per MoRT&H (5th Revision) Specification Section Nos. 2200 & 2907 and as per
Drawing and technical specifications for finished item of work .
Face Wall 2 9.95 4.966 (Avg) 98.81
Arround Pipe 1 10.766 5.090 4.2655 233.74
Deduct for pipe portion 3 10.766 1.188 -38.38
Sub-Total 294.18
Add 0.82
Total 295 Cu.m
6.1.6 Providing SS Revetment 300 mm thick including cost and conveyance of materials to site and including labour charges
for packing the stones for revetment etc., complete for finished item of work as per MoRT&H (5th Revision) Specification
Clause No. 2504 and as directed by the Engineer-in-Charge for Pitching of slopes
D/S side, Conical Portion 2 2.23 1.115 2.90
Cubical Portion 1 9.95 3 0.300 8.96
U/S side, Conical Portion 2 2.23 1.115 2.90
Cubical Portion 1 9.95 1.5 0.300 4.48
Sub-Total 19.24
Add 0.76
Total 20 Cu.m.
6.1.7 Providing and laying filter material with gravel underneath pitching in slopes including cost and conveyance of
materials to site including labour charges etc., complete for finished item of work as per MoRT&H (5th Revision)
Specification Clause No. 2504 and as directed by the Engineer-in-Charge
D/S side, Conical Portion 4 22/7*1/4* 0.15 (2.232+1.1152 4.96
2.23 )0.5
Sub-Total 4.96
Add 0.04
Total 5 Cu.m.
6.1.8 Providing, laying Reinforced cement concrete Hume 3 15 45 RM
pipes of 1000 mm diametre NP-4 class for pipe culverts
including cost and conveyance of Pipes etc., complete and
labour charges for laying, jointing of 1000 mm diametre
RCC hume pipes in position including lifting, aligning,
lowering and hoisting etc., as per drawing and as per
MoRT&H (5th Revision) Specification Section Nos 2900,
2905 & 2906 and IRC Special Publication No: 13 and as
directed by the Engineer-in-Charge for finished item of
work.

Roads & Building Department,


Vax Consultants Pvt. Ltd. Government of Andhra Pradesh

You might also like