This document provides a detailed estimate for pipe culverts including quantities and costs of materials. It includes estimates for 7 items: 1) earthwork excavation, 2) leveling course concrete, 3) body wall concrete, 4) bedding material below pipes, 5) filling between walls with gravel, 6) stone revetment pitching of slopes, and 7) filter material underneath pitching. The total quantities estimated include 77 cubic meters of excavation, 8 cubic meters of leveling concrete, 126 cubic meters of body wall concrete, and other materials for constructing 3 rows of 1000mm diameter pipe culverts.
Original Description:
Original Title
6.1 - 2 - Estimates - Pipe 3 x 1.0 m Reconstruction 21+255
This document provides a detailed estimate for pipe culverts including quantities and costs of materials. It includes estimates for 7 items: 1) earthwork excavation, 2) leveling course concrete, 3) body wall concrete, 4) bedding material below pipes, 5) filling between walls with gravel, 6) stone revetment pitching of slopes, and 7) filter material underneath pitching. The total quantities estimated include 77 cubic meters of excavation, 8 cubic meters of leveling concrete, 126 cubic meters of body wall concrete, and other materials for constructing 3 rows of 1000mm diameter pipe culverts.
This document provides a detailed estimate for pipe culverts including quantities and costs of materials. It includes estimates for 7 items: 1) earthwork excavation, 2) leveling course concrete, 3) body wall concrete, 4) bedding material below pipes, 5) filling between walls with gravel, 6) stone revetment pitching of slopes, and 7) filter material underneath pitching. The total quantities estimated include 77 cubic meters of excavation, 8 cubic meters of leveling concrete, 126 cubic meters of body wall concrete, and other materials for constructing 3 rows of 1000mm diameter pipe culverts.
NDB Project - Package IV Detailed Estimate for Pipe Culvert
Detailed Quantity Estimates For the Proposed Pipe Culverts -
3 Row 1000mm dia @ CH:21+255 (Reconstruction) Bill No: 6.1 Ref. Dwg. No.:BC/ND/BD/2021/STR/PC (RC-3Rx1.0m) - 08 Length Breadth Units Item Description Nos. Depth (m) Quantity (m) (m) 6.1.1 Earthwork excavation in soils up to SDR by mechanical means for foundations of structures as per drawing and technical specification including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing sides of bottom, back filling the excavation earth to the extent required etc., complete for finished item of work as per MoRT&H (5th Revision) Specification Clause No. 304 and as directed by the Engineer-in-Charge . For Face Wall 2 9.95 2.6 0.915 47.34 For Pipe Portion 1 10.766 5.09 0.535 29.32 Sub-Total 76.66 Add 0.34 Total 77 Cu.m. 6.1.2 Providing Vibrated Cement Concrete (1:3:6) mix using 40 mm size HBG crushed stone aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate conforming to table 1000-2 of MoRT&H) including cost, conveyance of all materials to site and labour charges, centering, machine mixing , laying, vibrating, curing etc., including all other incidental and operational charges of all T&P etc., complete for finished item of work as per MoRT&H (5th Revision) Specification Section Nos 1500, 1700 & 2100 and as directed by the Engineer-in-Charge for Levelling Course Below Face Wall 2 9.95 2.60 0.15 7.76 Sub-Total 7.76 Add 0.24 Total 8 Cu.m. 6.1.3 Vibrated cement concrete M-15 Grade using 40 mm, 20 mm and 10 mm size HBG crushed stone aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate conforming to table 1000-2 of MoRT&H) including cost and conveyance of all materials to site and all labour charges, mixing using Concrete Batching Plant, laying in position, compacting, Vibrating and curing including all other incidental and all other operational charges of T&P required etc., complete as per MoRT&H (5th Revision) Section Nos 1500, 1700, 2200 for Body Walls of HP Culverts
Face Wall straight portion 2 9.95 0.4 4.966 39.53
Tappering portion 2x1/2 9.95 2.000 4.966 98.81 Deduct for pipe portion 6X22/7x1/4 1.849 1.23 -13.18 Sub-Total 125.16 Add 0.84 Total 126 Cu.m. 6.1.4 Providing first class bedding with Granular material below the pipes of Hume pipe culverts suitably compacted / rammed including cost and conveyance of materials to site etc., complete as per drawing and MoRT&H (5th Revision) Specification Section No. 2900 and as directed by the Engineer-in-Charge . Levelling coarse below pipe for bedding 1 10.766 5.09 0.535 29.32 Deduct for pipe portion 3 10.766 0.306 -9.88 Sub-Total 19.43 Add 0.57 Total 20 Cu.m.
Roads & Building Department,
Vax Consultants Pvt. Ltd. Government of Andhra Pradesh NDB Project - Package IV Detailed Estimate for Pipe Culvert
Detailed Quantity Estimates For the Proposed Pipe Culverts -
3 Row 1000mm dia @ CH:21+255 (Reconstruction) Bill No: 6.1 Ref. Dwg. No.:BC/ND/BD/2021/STR/PC (RC-3Rx1.0m) - 08 Length Breadth Units Item Description Nos. Depth (m) Quantity (m) (m) 6.1.5 Filling in between body walls with Gravel including cost, conveyance of all materials to site etc., complete as per Clause 710.1.4 of IRC:78 and as per MoRT&H (5th Revision) Specification Section Nos. 2200 & 2907 and as per Drawing and technical specifications for finished item of work . Face Wall 2 9.95 4.966 (Avg) 98.81 Arround Pipe 1 10.766 5.090 4.2655 233.74 Deduct for pipe portion 3 10.766 1.188 -38.38 Sub-Total 294.18 Add 0.82 Total 295 Cu.m 6.1.6 Providing SS Revetment 300 mm thick including cost and conveyance of materials to site and including labour charges for packing the stones for revetment etc., complete for finished item of work as per MoRT&H (5th Revision) Specification Clause No. 2504 and as directed by the Engineer-in-Charge for Pitching of slopes D/S side, Conical Portion 2 2.23 1.115 2.90 Cubical Portion 1 9.95 3 0.300 8.96 U/S side, Conical Portion 2 2.23 1.115 2.90 Cubical Portion 1 9.95 1.5 0.300 4.48 Sub-Total 19.24 Add 0.76 Total 20 Cu.m. 6.1.7 Providing and laying filter material with gravel underneath pitching in slopes including cost and conveyance of materials to site including labour charges etc., complete for finished item of work as per MoRT&H (5th Revision) Specification Clause No. 2504 and as directed by the Engineer-in-Charge D/S side, Conical Portion 4 22/7*1/4* 0.15 (2.232+1.1152 4.96 2.23 )0.5 Sub-Total 4.96 Add 0.04 Total 5 Cu.m. 6.1.8 Providing, laying Reinforced cement concrete Hume 3 15 45 RM pipes of 1000 mm diametre NP-4 class for pipe culverts including cost and conveyance of Pipes etc., complete and labour charges for laying, jointing of 1000 mm diametre RCC hume pipes in position including lifting, aligning, lowering and hoisting etc., as per drawing and as per MoRT&H (5th Revision) Specification Section Nos 2900, 2905 & 2906 and IRC Special Publication No: 13 and as directed by the Engineer-in-Charge for finished item of work.
Roads & Building Department,
Vax Consultants Pvt. Ltd. Government of Andhra Pradesh