Professional Documents
Culture Documents
3 ٣ الحزمة رقم
Design and Construction of New Runway 15R/33L, إعادة إنشاء المدرج،15R/33L تصميم و إنشاء المدرج الجديد
Reconstruction of Runway 15L/33R, Associated البنى التحتية و الخدمات، ممرات الطائرات ذات الصلة،15L/33R
Taxiways, Infrastructure and Utilities
PART 1 - GENERAL
A. Drawings and general provisions of the Contract, including Conditions of Contract and
other Division 1 Specification Sections, apply to this Section.
1.2 SUMMARY
A. This Section includes requirements for temporary facilities and controls, including
temporary utilities, support facilities, and security and protection facilities.
B. Temporary utilities include, but are not limited to, the following:
C. Support facilities include, but are not limited to, the following:
D. Security and protection facilities include, but are not limited to, the following:
1. Environmental protection.
2. Stormwater control.
3. Tree and plant protection.
4. Site enclosure fence.
5. Security enclosure and lockup.
6. Barricades, warning signs, and lights.
7. Covered walkways.
8. Temporary enclosures.
9. Temporary partitions.
10. Fire protection.
1.3 DEFINITIONS
A. Sewer Service: Pay sewer service use charges for sewer usage, by all parties engaged in
construction, at Site.
B. Water Service: Pay water service use charges, whether metered or otherwise, for water used
by all entities engaged in construction activities at Site.
C. Electric Power Service: Pay electric power service use charges, whether metered or
otherwise, for electricity used in construction activities at Site.
D. Telephone Service: Pay telephone service use charges, for telephones installed at Site.
1.5 SUBMITTALS
A. Temporary Utility Reports: Submit reports of tests, inspections, meter readings, and similar
procedures performed on temporary utilities.
B. Temporary Utilities: Submit detailed proposals including drawings and product data as
requested; obtain the Engineer's approval prior to purchase, delivery, installation or
implementation, as applicable, of the following:
C. Support Facilities: Submit detailed proposals including drawings and product data as
requested; obtain the Engineer's approval prior to purchase, delivery, installation or
implementation, as applicable, of the following:
D. Security and Protection Facilities: Submit detailed proposals including drawings and
product data as requested; obtain the Engineer's approval prior to purchase, delivery,
installation or implementation, as applicable, of the following:
A. Regulations: Comply with industry standards and applicable laws and regulations of
authorities having jurisdiction including, but not limited to, the following:
B. Standards: Comply with ANSI A10.6, NECA's "Temporary Electrical Facilities," and
NFPA 241.
1. Electric Service: Comply with NECA, NEMA, and UL standards and regulations for
temporary electric service. Install service to comply with NFPA 70.
C. Tests and Inspections: Arrange for authorities having jurisdiction to test and inspect each
temporary utility before use. Obtain required certifications and permits.
1.7 CONDITIONS
A. Temporary Utilities: At earliest feasible time, when acceptable to the Engineer, change over
from use of temporary service to use of permanent service.
B. Temporary Use of Permanent Facilities: The Contractor shall assume responsibility for
operation, maintenance, and protection of each permanent service during its use as a
construction facility before Taking-Over, regardless of previously assigned responsibilities.
C. Conditions of Use: The following conditions apply to use of temporary services and
facilities by all parties engaged in the Works:
PART 2 - PRODUCTS
2.1 MATERIALS
A. General: Provide new materials suitable for use intended. Undamaged, previously used
materials in serviceable condition may be used for temporary facilities if approved by the
Engineer.
B. Construction Materials and Products: Comply with standards and applicable requirements
in appropriate Sections of the Specification.
2.2 EQUIPMENT
A. General: Provide new equipment suitable for use intended. Undamaged, previously used
equipment in serviceable condition may be used for temporary facilities if approved by the
Engineer. Refer to Appendices 1 and 2 herein for the requirements.
B. Temporary Site Offices: Prefabricated, mobile units or job-built construction, with lockable
entrances, operable windows, serviceable finishes and robust and secure fittings; insulated
sandwich panel, weathertight, heated and air-conditioned.
1. Incorporate sanitary facilities to the extent required for the number and gender of
personnel accommodated.
2. Support on foundations adequate for loading.
3. Provide and maintain all necessary and required services and utilities, including but
not necessarily limited to:
4. Engineer's Site Offices: Provide new fully functional offices suitable for use
intended, without furniture and equipment. The office requirements are as follows
for each room type as a minimum requirement, but shall not include the furniture,
equipment and supplies:
Employer's Site Offices: Provide new fully functional offices, with furniture and
equipment suitable for use intended and in compliance with the specifications of this
Section 01500. The office requirements are as follows for each room type as a
minimum requirement:
The above offices (for the Engineer and for the Employer) shall have telephone lines, fax
lines and internet.
The Employer may request, at his discretion, to split any of the above Employer's and
Engineer's offices to more than one location (maximum three), each fully in accordance
with the requirements and specifications of this section 01500.
Transportation: The Contractor shall provide five (5) fully automatic, air-conditioned, 4-
wheel drive SUVs, with strong axles and heavy duty tires, till the substantial completion of
the works, plus three months. Brochures of vehicles shall be submitted for the Engineer's
approval prior to placing the order.
C. Fire Extinguishers: Hand carried, portable, UL rated. Provide class and extinguishing agent
as indicated or a combination of extinguishers of NFPA-recommended classes for
exposures.
1. Comply with NFPA 10 and NFPA 241 for classification, extinguishing agent, and
size required by location and class of fire exposure.
1. Where power is accessible, provide electric water coolers to maintain dispensed water
temperature at 7.2 to 12.7 deg. C (45 to 55 deg. F).
F. Power Distribution System Circuits: Where permitted and overhead and exposed for
surveillance, wiring circuits, not exceeding 125-V ac, 20-A rating, and lighting circuits may
be nonmetallic sheathed cable.
G. NOT USED.
H. PERSONAL COMPUTERS FOR THE EMPLOYER: Install, connect and configure, for
the exclusive use of Employer’s staff, new computer equipment, peripheral hardware and
associated accessories, including all necessary cabling and computer workstation desking.
Computers provided for Employer’s staffs are the property of the Employer. Prior to the
expiration of the Contract, as and when directed, service, re-package and deliver to location
as directed by the Employer. Minimum Specifications are:
Notebooks and other equipment shall be subject to the approval of the Engineer
PART 3 - EXECUTION
A. Locate facilities where they will serve the Works adequately and result in minimum
interference with performance of the Works. Relocate and/or modify facilities as often as
required by progress of the Works.
B. Provide each facility ready for use when needed to avoid delay. Maintain and modify as
required. Do not remove facilities until permitted or directed to do so by the Engineer, or
until replaced, to the satisfaction of the Engineer, by authorized use of completed permanent
facilities.
A. General: Engage appropriate local utility company to install temporary service or connect
to existing service. Where utility company provides only part of the service, provide the
remainder with matching, compatible materials and equipment. Comply with utility
company requirements and recommendations.
1. Arrange with utility company, the Engineer, and existing users for time when service
can be interrupted, if necessary, to make connections for temporary services.
2. Provide for adequate capacity and peak-demand or special load requirements at each
stage of construction. Before temporary utility is available, provide trucked-in
services if necessary.
3. Obtain any necessary easements to bring temporary utilities to Site.
4. Charges and Costs; Pay for all connection, service and user charges and costs arising
in connection with the provision of temporary utilities.
B. Sewers and Drainage: If sewers are available, provide temporary connections to remove
effluent that can be discharged lawfully. If sewers are not available or cannot be used,
provide drainage ditches, dry wells, stabilization ponds, and similar facilities. If neither
sewers nor drainage facilities can be lawfully used for discharge of effluent, provide
containers to remove and dispose of effluent off-site in a lawful manner.
1. Filter out excessive soil, construction debris, chemicals, oils, and similar
contaminants that might clog sewers or pollute waterways before discharge.
2. Connect temporary sewers to municipal system as directed by sewer department
officials.
3. Maintain temporary sewers and drainage facilities in a clean, sanitary condition.
After heavy use, restore normal conditions promptly.
C. Water Service: Install water service and distribution piping in sizes and pressures adequate
for construction.
D. Water Service: If use of the Employer's existing or permanent water service facilities is
permitted, service, clean and maintain in a condition acceptable to the Engineer. At
Substantial Completion, restore these facilities to condition existing before initial use.
E. Sanitary Facilities: Provide temporary toilets, wash facilities, and drinking-water fixtures.
Comply with regulations, health codes and the Engineer's directions for type, number,
location, operation, and maintenance of facilities and fixtures. Provide separate toilet
facilities for male and female personnel.
1. Generally: Install where facilities will best serve needs of the Works, including
relocation whenever necessary.
a. Service and maintain, and keep clean, sanitary and orderly for use.
b. Provide toilet tissue, paper towels, paper cups, and similar disposable materials
for each facility. Maintain adequate supply. Provide covered waste containers
for disposal of used material.
2. Toilets: Install toilet facilities connected to local water and sewer lines. Provide
lavatories, mirrors, and water closets. Provide only potable-water connections.
Provide individual compartments for water closets. Provide suitable enclosure with
nonabsorbent sanitary finish materials and adequate ventilation and lighting.
3. Toilets: If use of the Employer's existing or permanent toilet facilities is permitted,
service, clean and maintain in a condition acceptable to the Engineer. At Substantial
Completion, restore these facilities to condition existing before initial use.
4. Temporary Site Toilets: Install self-contained toilet units. Shield toilets to ensure
privacy.
5. Wash Facilities: Install wash facilities supplied with potable water at convenient
locations for personnel who handle materials that require wash-up. Dispose of
drainage properly. Supply cleaning compounds appropriate for each type of material
handled.
6. Drinking-Water Facilities: Install containerized, tap-dispenser, bottled-drinking-
water units, including paper cup supply.
F. Cooling: Provide temporary cooling required by construction activities for curing or drying
of completed installations or for protecting installed construction from adverse effects of
high humidity. Select equipment from that specified that will not have a harmful effect on
completed installations or elements being installed.
H. Electric Power Service: Provide weatherproof, grounded electric power service and
distribution system of appropriate and sufficient size, capacity, and power characteristics
required for use during construction, including necessary start-up, testing and
commissioning of building operating systems and equipment. Include meters, transformers,
overload-protected disconnecting means, automatic ground-fault interrupters, and main
distribution switchgear.
1. Install electric power service underground, unless overhead service must be used.
2. Install power distribution wiring overhead and rise vertically where least exposed to
damage.
3. If at any time, temporary electric power service supply is interrupted or inadequate
for requirements, provide and operate back-up electric generators as necessary.
I. Electric Power Service: If use of the Employer's existing or permanent electric power
service is permitted, maintain equipment in a condition acceptable to the Engineer. At
Substantial Completion, restore equipment to condition existing before initial use.
J. Electric Distribution: Provide receptacle outlets adequate for connection of power tools and
equipment.
K. Lighting: Provide temporary lighting with appropriate control and local switching to
facilitate safe and proper execution of the Works. Provide adequate illumination to internal
areas during finishing operations and for inspections.
1. Install and operate temporary lighting that fulfills security and protection
requirements without operating entire system.
2. Install exterior site lighting that will provide adequate illumination for construction
operations, traffic conditions, and signage visibility when the Work is being
performed.
3. Install lighting for Works identification sign.
L. Telephone Service: Provide and maintain adequate temporary telephone facilities and
service for the duration of the Contract including Defects Liability Period, for all personnel
accommodated in temporary field offices.
M. Telephone Facilities for the Employer / Engineer: Provide and install a PABX in the
offices, with sufficient line connections and capacity to provide at least one extension in
every office or occupied space:
1. Provide the following telephone facilities, line connections and services for the
exclusive use of the Engineer and his staff:
2. Charges and Costs: Pay for all connection, service and user charges and costs arising
in connection with the provision of telephone facilities and services for the Employer
and the Engineer.
1. Locate field offices, site laboratory, storage and fabrication sheds, workshops,
sanitary facilities, and other temporary construction and support facilities for easy
access.
2. Maintain support facilities until near Substantial Completion. Unless otherwise
directed, remove before Substantial Completion, but retain adequate support facilities
up to 25% of the requirements to accommodate personnel remaining on Site after
issuance of Substantial Completion certificate for the whole of the works, including
relocating if necessary and under conditions acceptable to the Employer / Engineer.
B. Contractor's Site Offices: Provide and maintain temporary offices and facilities of sufficient
size, number and type to accommodate required office personnel, including sub-contractors,
at the Site. Furnish and equip as necessary. Keep clean and orderly for use.
D. Employer's and Engineer's Field Offices: maintain, clean (daily) and service all the
temporary offices and facilities for the exclusive use of the Engineer/Employer's
Representative, and their staff, sized, arranged, finished and equipped to the approval of the
Engineer:
3. Toilets;
a. Service and maintain, and clean toilets on a daily basis. Provide and
continuously stock with all associated consumable and supplies as and when
required or requested, including soaps, toilet paper and paper towels. The cost
of which are to be borne by the Contractor.
TEMPORARY FACILITIES AND CONTROLS 01500 - Page 14 of 20
K07098-3-SPC-PMC-01 REV 1.1
Package No. 3 ٣ اﻝﺤزﻤﺔ رﻗم
Design and Construction of New Runway 15R/33L, إﻋﺎدة إﻨﺸﺎء اﻝﻤدرج،15R/33L ﺘﺼﻤﻴم و إﻨﺸﺎء اﻝﻤدرج اﻝﺠدﻴد
Reconstruction of Runway 15L/33R, Associated اﻝﺒﻨﻰ اﻝﺘﺤﺘﻴﺔ و اﻝﺨدﻤﺎت، ﻤﻤرات اﻝطﺎﺌرات ذات اﻝﺼﻠﺔ،15L/33R
Taxiways, Infrastructure and Utilities
4. Kitchen; with:
a. Sets of crockery and cutlery sufficient for number of Engineer's staff and
visitors. Service and maintain, and clean kitchens on a daily basis. Provide and
continuously stock with all associated consumables and supplies as and when
requested or required, including drinking water, milk, sugar, tea and coffee
beverages. The cost of which are to be borne by the Contractor.
5. Storage Room.
6. Temporary car port shade structures adjacent to the Engineer's/Employer's site offices
including temporary paved vehicular access, car port hardstanding and walkways.
7. 7- The Contractor shall make arrangements for treatments against pets and insects.
8. 8- The Contractor shall make arrangements to maintain a suitable condition during
bad weather (Touz for example) by providing water tank systems and other control
units and measures.
E. Temporary Roads and Paved Areas: Construct and maintain temporary roads and paved
areas adequate to support loads and to withstand exposure to traffic during construction
period. Submit proposals and obtain prior approval to locate temporary roads and paved
areas coincidental with and in same location as permanent roads and paved areas. In such
cases review any proposed modifications to permanent paving with the Engineer, and:
1. Comply with applicable requirements in appropriate Sections of the Specification for
sub-grade, sub-base and base course construction of temporary paving.
2. Coordinate elevations and development of temporary roads and paved areas with
subgrade grading, compaction, installation and stabilization of subbase, and
installation of base and finish courses of permanent paving. Temporary roads should
be appropriately leveled and suitable for the passage of passenger cars more
specifically for the sections of the roads between the site access gate and the site
offices.
3. Install temporary roads and paved areas to minimize the need to rework the
installations and to result in permanent roads and paved areas without damage or
deterioration when occupied by the Employer.
4. Recondition and repair base after temporary use, including removing contaminated
material, regrading, proof-rolling, compacting and testing.
5. Delay installation of the final course of permanent pavement until immediately before
Substantial Completion. Coordinate with weather conditions to avoid unsatisfactory
results.
6. Extend temporary roads and paved areas, within construction limits indicated, as
necessary for construction operations, including delivery and storage of materials,
equipment usage, administration and supervision.
F. Traffic Controls: Provide temporary traffic controls at junction of temporary roads with
public roads. Include warning signs for public traffic and "STOP" signs for entrance onto
public roads. Comply with requirements of authorities having jurisdiction.
1. Dispose of rainwater in a manner that will not result in flooding of Site or adjoining
property nor endanger Permanent Works or temporary facilities.
2. Before connection and operation of permanent drainage piping system, provide
temporary drainage where roofing or similar waterproof deck construction is
completed.
H. Works Identification and Temporary Signs: Provide Works identification and other signs of
appropriate sizes and types. Install signs to inform public generally and persons seeking
entrance to Site. Do not permit installation of unauthorized signs.
1. Design, fabricate and erect two Works identification signs in approved locations.
Support on posts or framing of paint finished, preservative-treated wood or
galvanized steel.
a. Works name.
b. Employer's name, style and logo.
c. Engineer's name, style and logo
d. Contractor's name, style and logo.
e. Such other names, details and information as permitted and/or directed.
J. Janitorial Services: Provide janitorial cleaning services on a daily basis for all temporary
offices, toilets, wash facilities, and similar areas.
L. Storage and Fabrication Sheds: Provide sheds sized, furnished, and equipped to
accommodate materials and equipment involved, including temporary utility services.
Sheds may be open shelters or fully enclosed spaces within building or elsewhere on site.
M. Construction Aids and Miscellaneous Facilities: Provide all necessary aids and
miscellaneous facilities incidental and ancillary to the safe and efficient execution of
construction operations and the carrying-out of work in a proper workmanlike manner,
including but not necessarily limited to:
B. Stormwater Control: Provide earthen embankments and similar barriers in and around
excavations and subgrade construction, sufficient to prevent flooding by runoff of
stormwater from heavy rains.
C. Tree and Plant Protection: Unless otherwise indicated, install temporary fencing located
outside the drip line of trees to protect vegetation from construction damage. Protect tree
root systems from damage, flooding, and erosion.
D. Pest Control: Before deep foundation work has been completed, retain a local exterminator
or pest-control company to recommend practices to minimize attraction and harboring of
rodents, roaches, and other pests. Engage this pest-control service to perform extermination
and control procedures at regular intervals so that the Site will be free of pests and their
residues at Substantial Completion. Perform control operations lawfully, using
environmentally safe materials.
E. Site Enclosure Fence: Before construction operations begin install an enclosure fence with
lockable entrance gates. Locate where directed. Enclose entire Site or portion determined
sufficient to accommodate construction operations. Install in a manner that will prevent
people and animals from easily entering site except by entrance gates.
1. Provide approved open mesh or solid panel fencing with posts set in concrete bases.
2. Provide gates in sizes and at locations necessary to accommodate delivery vehicles
and other construction operations
3. Maintain security by limiting number of keys and restricting distribution to
authorized personnel.
F. Security Enclosure and Lockup: Install substantial temporary enclosure around partially
completed areas of construction. Provide lockable entrances to prevent unauthorized
entrance, vandalism, theft, and similar violations of security.
1. Secure Storage: Where materials and/or equipment are of high value or attractive for
theft, provide a secure lockup. Enforce discipline in connection with the installation
and release of such materials and/or equipment to minimize the opportunity for theft.
G. Barricades, Warning Signs, and Lights: Comply with standards, code requirements and
directions of the Engineer for erecting structurally adequate barricades. Paint with
appropriate colors, graphics, and warning signs to inform personnel and public of possible
hazard. Where appropriate and needed, provide lighting, including flashing red or amber
lights.
1. Where heating or cooling is needed and permanent enclosure is not complete, provide
insulated temporary enclosures. Coordinate enclosure with ventilating and material
drying or curing requirements to avoid dangerous conditions and effects.
2. Vertical Openings: Close openings of 2.5 m² or less with plywood or similar
materials.
3. Horizontal Openings: Close openings in floor or roof decks and horizontal surfaces
with load-bearing, wood-framed construction.
4. Install tarpaulins securely using fire-retardant-treated wood framing and other
materials.
J. Temporary Partitions: Where necessary, construct, erect and maintain dustproof partitions
and temporary enclosures to limit dust and dirt migration, and to separate areas from fumes
and noise.
K. Temporary Fire Protection: Until fire-protection needs are supplied by permanent facilities,
install and maintain temporary fire-protection facilities of types needed to protect against
reasonably predictable and controllable fire losses. Comply with NFPA 241. Strictly
observe all requirements and recommendations pertaining to fire safety on construction sites
as contained in the latest edition of the Fire Instruction Manual produced by the Fire Service
Department of the Department of Civil Aviation.
7. Provide hoses for fire protection of sufficient length to reach construction areas.
Hang hoses with a warning sign stating that hoses are for fire-protection purposes
only and are not to be removed. Match hose size with outlet size and equip with
suitable nozzles.
8. Provide temporary standpipes and hoses for fire protection. Hang hoses with a
warning sign stating that hoses are for fire-protection purposes only and are not to be
removed. Match hose size with outlet size and equip with suitable nozzles.
A. Supervision: Enforce strict discipline in use of temporary facilities. To minimize waste and
abuse, limit availability of temporary facilities to essential and intended uses.
B. Maintenance: Maintain facilities in good operating condition until removal. Protect from
damage caused by extreme temperatures and similar elements.
C. Temporary Facility Changeover: Except for using permanent fire protection as soon as
available, do not change over from using temporary security and protection facilities to
permanent facilities until Substantial Completion.
D. Termination and Removal: At the Engineer's sole discretion, remove each temporary
facility either when need for its service has ended, or when it has been replaced by
authorized use of a permanent facility, or at Substantial Completion. Complete, or if
necessary, restore permanent construction that may have been delayed because of
interference with a temporary facility. Repair damaged work, clean exposed surfaces, and
replace construction that cannot be satisfactorily repaired.
A. In addition to the requirements of the provisions of the General Conditions of Contract and
other Contract requirements, the Contractor shall submit for the Engineer's approval, within
15 days after the effective date of the notice to proceed for the Works, a proposed Safety
Program covering the following items:
a. The Health and Safety Plan shall contain but not be limited to the following:
b. The Contractor shall take into account that the works under this Contract may
be undertaken simultaneously with other Package Contracts. The Contractor is
to coordinate safety procedures with the Engineer and Safety Representatives
from other Package Contracts to implement and maintain a common safety
strategy.
c. Site Cleaning and Housekeeping: Each Package Contractor shall be
responsible for cleaning and housekeeping in their own work areas. The
provision of waste chutes, garbage skips and disposal shall be provided by each
package Contractor Package Contractor.
a. The Contractor shall include within the Health and Safety Plan the name of the
company’s qualified Safety Officer. He shall also submit the name and
qualification of a Health and Safety representative on site responsible for the
implementation of the Health and Safety Plan on site. The site safety
representative shall remain on site during operational working hours and shall
coordinate with the safety representatives of other package Contractors.
b. Appointment of the site Health and Safety representative will be subject to the
Engineer’s approval.
c. If in the opinion of the Engineer there is an infringement or breach in the
approved Health and Safety Plan, the Engineer reserves the right to instruct the
Contractor to undertake immediate corrective action without any liability for
any additional costs or time implication incurred by the Contractor in
undertaking the corrective action.
B. Upon the Engineer's approval of the Safety Program the Contractor shall, for the full term of
the Contract, operate the Safety Program, maintain accurate records of safety activities and
accident, and submit safety and accident reports to the Engineer on the approved forms.