You are on page 1of 1

Subject: Labor Cost for VALENCIA BRANCH

Owner: DAVAO ROS-VER / NEW PAG-ASA PAWNSHOP


Location: Valencia, Bukidnon
Contractor:Romeo Rato

Vault Room 10.433 sq.m


Showcase area 17.395 sq.m
Office Area 13.914 sq.m
Bodega 14.958 sq.m
Total Floor Area 56.7 sq.m

Labor Cost Breakdown


DESCRIPTION AMOUNT
Masonry Works ₱ 180,300.00
Carpentry Works ₱ 164,000.00
Welding Works ₱ 25,500.00
Painting Works ₱ 160,250.00
Mobilization/Demobilization ₱ 30,000.00
Total Labor Cost ₱ 560,050.00

Cost per sq.m ₱ 9,877.43