Purpose Engineering Document Comment Discussion and Closed & Catch Up for design progress
Page 1 of 6
Agenda for Basic Design Review Meeting
CLIENT: PT. Pertamina Geothermal Energy
LUMUT BALAI 2 GEOTHERMAL FCRS & POWER PLANT PROJECT
DESIGN REVIEW SHEET PROJECT:
Contract Number: 459/PGE000/2022-S0
Page 2 of 6
Agenda for Basic Design Review Meeting
CLIENT: PT. Pertamina Geothermal Energy
LUMUT BALAI 2 GEOTHERMAL FCRS & POWER PLANT PROJECT
DESIGN REVIEW SHEET PROJECT:
Contract Number: 459/PGE000/2022-S0
17 LMB2-E-FC-PRO-AEF-MS0-0019 P&ID Of Emergency Diesel Generator System of FCRS July 31st-August 1st
18 LMB2-E-FC-PRO-OEL-MS0-0003 Process Calculation for Steam Separators of FCRS July 31st-August 1st Separated with
P&ID Discussion
Room
19 LMB2-E-FC-PRO-OEL-MS0-0004 Process Calculation for Silencer of FCRS July 31st-August 1st Separated with
P&ID Discussion
Room
20 LMB2-E-FC-PRO-OEL-MS0-0005 Process Calculation for Geothermal Pond of FCRS July 31st-August 1st Separated with
P&ID Discussion
Room
21 LMB2-E-FC-PRO-OEL-MS0-0007 Process Calculation for Steam Vessel of FCRS July 31st-August 1st Separated with
P&ID Discussion
Room
22 LMB2-E-FC-PRO-OEL-MS0-0008 Process Calculation for Rock Muffler of FCRS July 31st-August 1st Separated with
P&ID Discussion
Room
23 LMB2-E-FC-PRO-OEL-MS0-0009 Process Calculation for Scrubber of FCRS July 31st-August 1st Separated with
P&ID Discussion
Room
24 LMB2-E-FC-PRO-OEL-MS0-0010 Process Calculation for Compressed Air System of FCRS July 31st-August 1st Separated with
P&ID Discussion
Room
25 LMB2-E-FC-PRO-OEL-MS0-0012 Process Calculation for Steam Trap of FCRS July 31st-August 1st Separated with
P&ID Discussion
Page 3 of 6
Agenda for Basic Design Review Meeting
CLIENT: PT. Pertamina Geothermal Energy
LUMUT BALAI 2 GEOTHERMAL FCRS & POWER PLANT PROJECT
DESIGN REVIEW SHEET PROJECT:
Contract Number: 459/PGE000/2022-S0
Page 4 of 6
Agenda for Basic Design Review Meeting
CLIENT: PT. Pertamina Geothermal Energy
LUMUT BALAI 2 GEOTHERMAL FCRS & POWER PLANT PROJECT
DESIGN REVIEW SHEET PROJECT:
Contract Number: 459/PGE000/2022-S0
6 Calculation for Pipe Wall Thickness Brine Modification LMB-A and LMB-18 July 28th
Calculation for Thermal Insulation for Production Wells and LMB-19 July 28th
Page 5 of 6
Agenda for Basic Design Review Meeting
CLIENT: PT. Pertamina Geothermal Energy
LUMUT BALAI 2 GEOTHERMAL FCRS & POWER PLANT PROJECT
DESIGN REVIEW SHEET PROJECT:
Contract Number: 459/PGE000/2022-S0
Page 6 of 6