GENERAL INFORMATION
Project: Client:
Consultant: Contractor: Al Eslah General Contracting Est.
Conducted By: Date:
Poor: Absence of major control measures (High risk), works to be stopped and risk assessment to be reviewed immediately.
Fair: Some minor controls are missing (medium risk), Additional control measures to be implemented
Good: All control measures are in place (low risk), only monitoring is required

DESCRIPTION

Evaluation Remarks
(Inside your observation,
Items
Good Fair Poor N/A and proposed corrective
action plan.)
Vehicles & mobile equipment are licensed by
£ £ £ £
concerned authority.
Vehicle & mobile equipment 3rd Party certified £ £ £ £
Driver/operator is licensed and competent. £ £ £ £
Operator 3rd party certified
Engine in good operational condition. £ £ £ £
No visible leaks £ £ £ £
Maintenance done by competent personnel
Windows & mirrors are clean & obstruction
£ £ £ £
free.
Seat is in good condition and seat belt
£ £ £ £
functioning properly.
Lights / indicators / wipers / horns properly
£ £ £ £
operational
Tyres are free of damage and fully inflated £ £ £ £
Reversing alarm & beacons working properly £ £ £ £
Periodical inspection & maintenance & record
£ £ £ £
kept
Provided with fire extinguisher and first aid
£ £ £ £
box, and in good condition
Provided with the noise silencer/enclosure £ £ £ £
Banks man available with all the equipment

Approved By:
Position Name Date Signature
HSE Officer
Project Engineer Ahmad Zeshan
Project Manager Amin Mohammad

Doc Ref: AE/AD/PSAF/EHS/VME-/F-18 Rev: 01 Date: 20.08.2016 Page: 1 of 1