Professional Documents
Culture Documents
Adfi-Eme-Gfts Ces-Mos-05 - R00 - Slab Construction For Existing Trench
Adfi-Eme-Gfts Ces-Mos-05 - R00 - Slab Construction For Existing Trench
Rev. 00
W
METHOD STATEMENT SUBMITTAL FOR SLAB CONSTRUCTION FOR EXISTING TRENCH
Document Number Revision Date
ADFI-EME-GFTS/CES-MOS-05_R00 R00 11-11-2023
Project: EPC for 1.2MWp Capacity Roof Top PV Plant for AL DAHRA FOOD Project
INDUSTRIES – Kizad City (Abu Dhabi) Code:
Ref. No. ADFI-EME-GFTS/CES-MOS-05_R00
METHOD STATEMENT
Date: 11/11/2023
Required By:
Description of Submittal:
Method Statement Submittal – Slab
Construction For Existing Trench Division:
Calculations O & M Manual (Prel.) Test Reports Others (Specify) Issued For:
REVIEW STATUS
A. Approved B. Approved As Noted C. Revise and Resubmit D. Not Approved
Client Comments:
Received by Client
2|Page
METHOD STATEMENT SUBMITTAL FOR SLAB CONSTRUCTION FOR EXISTING TRENCH
Document Number Revision Date
ADFI-EME-GFTS/CES-MOS-05_R00 R00 11-11-2023
Contents
1. SLAB CONSTRUCTION FOR EXISTING TRENCH ........................................................................................................ 5
1.1 Introduction: - ................................................................................................................................................. 5
2. DEFINITION & ABBREVATION.................................................................................................................................. 5
3. LEGAL REQUIREMENTS & REFERENCE DOCUMENTS .............................................................................................. 6
4. DUTIES & RESPONSIBILITIES.................................................................................................................................... 6
4.1 Project/Construction Manager ....................................................................................................................... 6
4.2 Project/Site Engineer ...................................................................................................................................... 6
4.3 QA/QC Engineer/Inspector ............................................................................................................................. 6
4.4 HSE Representative ......................................................................................................................................... 7
4.5 Supervisor/Foreman ....................................................................................................................................... 7
4.6 Subcontractor ................................................................................................................................................. 7
4.7 Management Representative/Logistic Manager/Logistic Superintendent .................................................... 7
4.8 GFTS/CES Workforce ....................................................................................................................................... 8
5. RESOURCES ............................................................................................................................................................. 9
5.1 Manpower Requirement................................................................................................................................. 9
5.2 Resources ........................................................................................................................................................ 9
5.3 Material ........................................................................................................................................................... 9
6. SCOPE OF WORK ..................................................................................................................................................... 9
6.1 General Description: - ..................................................................................................................................... 9
6.2 NOCs and Permit Requirements: - ................................................................................................................ 10
6.3 Safety Precaution & Site Preparation: - ........................................................................................................ 10
6.4 Trench Preparation: - .................................................................................................................................... 10
6.5 Provision Of Site Security, Fencing, Barriers & Signage: - ............................................................................. 10
6.6 Concrete Grade Selection: - .......................................................................................................................... 11
6.7 Iron Rebar: - .................................................................................................................................................. 12
6.8 Reinforcement Installation: - ........................................................................................................................ 12
6.9 Concrete Mixing & Pouring: - ........................................................................................................................ 12
6.10 Removal Of Shuttering: - ............................................................................................................................... 13
6.11 Curing Procedures: -...................................................................................................................................... 13
6.12 Crane Operation: - ........................................................................................................................................ 13
6.13 Final Inspection & Quality Control: - ............................................................................................................. 14
3|Page
METHOD STATEMENT SUBMITTAL FOR SLAB CONSTRUCTION FOR EXISTING TRENCH
Document Number Revision Date
ADFI-EME-GFTS/CES-MOS-05_R00 R00 11-11-2023
4|Page
METHOD STATEMENT SUBMITTAL FOR SLAB CONSTRUCTION FOR EXISTING TRENCH
Document Number Revision Date
ADFI-EME-GFTS/CES-MOS-05_R00 R00 11-11-2023
1.1 Introduction: -
This guide explains how we are going to make a strong foundation a solid slab, for the trench that's already there.
The goal is to ensure the trench stays strong and doesn't have any issues. By following the right steps and using
good construction methods, we want to make sure the slab we build is strong and lasts a long time. This way, we
make sure the trench works well and stays in good shape. This slab is to cover the existing trench at 3 points and
slab dimensions will be based on existing slab dimensions.
5|Page
METHOD STATEMENT SUBMITTAL FOR SLAB CONSTRUCTION FOR EXISTING TRENCH
Document Number Revision Date
ADFI-EME-GFTS/CES-MOS-05_R00 R00 11-11-2023
6|Page
METHOD STATEMENT SUBMITTAL FOR SLAB CONSTRUCTION FOR EXISTING TRENCH
Document Number Revision Date
ADFI-EME-GFTS/CES-MOS-05_R00 R00 11-11-2023
4.5 Supervisor/Foreman
Their responsibilities include but are not limited to:
Responsible to carry out the work in safe manner and to supervise the work force together with the proper
execution and monitoring of works, and all appropriate checks will be carried out during each stage of the
works.
Regular brief workforce in ensuring work activities shall be carries out in safe manner.
He will be responsible for distribution of all approved shop drawings and method statements to tradesmen.
He should check and ensure that the tools and equipment follow applicable requirements.
He also should ensure that material used is approved and not damaged during installation, being aware that
damaged materials will be rejected.
He shall ensure that all works follow standards and shop drawings.
4.6 Subcontractor
Conduct regular safety meetings and toolbox talks to discuss potential hazards and safety protocols.
Identify, report, and mitigate potential safety hazards on the installation site in discussion with site engineer.
Use appropriate personal protective equipment (PPE) such as helmets, gloves, safety glasses as required as
per approved and check by site HSE/safety supervisor/officer.
Securely store and manage tools and equipment to prevent accidents or tripping hazards.
Maintain and inspect safety equipment, including fire extinguishers and first-aid kits.
Follow lockout/tagout procedures when working with electrical components to prevent electrical accidents.
Communicate and coordinate with other team members to ensure a safe working environment.
Conduct emergency drills and ensure all team members are familiar with evacuation procedures.
Participate in HSE training programs to stay updated on best practices and regulations.
Promote a culture of safety and responsibility among team members and subcontractors.
Maintain a clean and organized work area to reduce the risk of accidents and injuries.
7|Page
METHOD STATEMENT SUBMITTAL FOR SLAB CONSTRUCTION FOR EXISTING TRENCH
Document Number Revision Date
ADFI-EME-GFTS/CES-MOS-05_R00 R00 11-11-2023
Regularly reviewing the policy and effectiveness of the housekeeping programs and ensuring that necessary
changes are made and communicated to all concerned individuals.
Ensure periodic environmental related Trainings/toolbox particularly on waste management to enhance
awareness and reinforce the skills of all workforce including subcontractors.
Ensure subcontractors, service providers and other related personnel in the business operations comply with
the waste management plan.
Report daily any environmental noncompliance and addressed to the concerned department
managers/supervisor.
Carry out regular environmental awareness sessions and assist personnel in applying environmental
standards on site.
Conduct regular audits/inspections to check that committed impact mitigation measures are being
implemented.
Liaise between management and other interested parties.
Taking all reasonable measures to ensure that the requirements of EAD –Environmental Agency Abu Dhabi,
Abu Dhabi CoP 54.0 – Waste Management and Abu Dhabi Law No. 21 and all other regulatory and statutory
are enforced.
Participate in walking around with all interested parties containing a description of on-going activities,
control, and monitoring programs.
8|Page
METHOD STATEMENT SUBMITTAL FOR SLAB CONSTRUCTION FOR EXISTING TRENCH
Document Number Revision Date
ADFI-EME-GFTS/CES-MOS-05_R00 R00 11-11-2023
5. RESOURCES
5.2 Resources
Barricades, Safety Signs, PPE kits (task specific) & Safety Cones
Hand tools, grinder/cutting tools.
Electrical Toolbox
Crane
5.3 Material
Cement
Granules & dust
Shovel
Ferma or frame (To cast slab)
Rebar (to strengthen slab)
Water
6. SCOPE OF WORK
These cover slabs will be designed and constructed as per existing slab specifications except size of the iron rebar.
Our plan is to consider T12@160 size rebar.
9|Page
METHOD STATEMENT SUBMITTAL FOR SLAB CONSTRUCTION FOR EXISTING TRENCH
Document Number Revision Date
ADFI-EME-GFTS/CES-MOS-05_R00 R00 11-11-2023
10 | P a g e
METHOD STATEMENT SUBMITTAL FOR SLAB CONSTRUCTION FOR EXISTING TRENCH
Document Number Revision Date
ADFI-EME-GFTS/CES-MOS-05_R00 R00 11-11-2023
Ensure all selected security measures comply with legal and regulatory requirements, obtaining necessary
permits or approvals.
Source high-quality materials and engage reputable contractors or skilled personnel for proper
installation of fencing, barriers, and signage.
Establish a secure perimeter around the site using fencing and barriers, implementing access control
measures like gates and entry points. This will be done under AL DAHRA facility management team.
Install clear and informative signage throughout the site to guide personnel, visitors, and emergency
responders.
Schedule routine inspections and maintenance to identify damages, weaknesses, or signs of wear.
Provide training to personnel on access control, and emergency procedures to foster a culture of safety
awareness.
M25 grade concrete is also used as an RCC, the Reinforced cement concrete.
M25 is used majorly during the construction of slabs, columns, footing, or beams.
M25 application is also suitable for use in any exposed work, where one doesn't need to cover the
concrete mixture for later finishing.
11 | P a g e
METHOD STATEMENT SUBMITTAL FOR SLAB CONSTRUCTION FOR EXISTING TRENCH
Document Number Revision Date
ADFI-EME-GFTS/CES-MOS-05_R00 R00 11-11-2023
For Al DAHRA, we will use M25 grade concrete so that slab will be long lasting without any cracks and
honeycomb.
6.7 Iron Rebar: -
T12@160 rebar will be used to cast slab for the trench. This rebar will tightly hold the cement, aggregate
and sand. Mesh type structure will be made using rebar for the slab.
The distance between adjacent slider rebar will be 16mm.
12 | P a g e
METHOD STATEMENT SUBMITTAL FOR SLAB CONSTRUCTION FOR EXISTING TRENCH
Document Number Revision Date
ADFI-EME-GFTS/CES-MOS-05_R00 R00 11-11-2023
Special care should be taken when vibrating corners and around reinforcement.
After casting completion, ensure an adequate number of workers are available for finishing, cleaning, and
protection.
Maintain a field record of concrete activities.
Maintain the curing conditions for a minimum of 3/4 days to ensure the development of the required
strength and durability.
Conduct a final walkthrough and inspection to ensure that all construction activities have been completed
to the satisfaction of the project requirements.
Formally hand over the construction site to the relevant authorities or project stakeholders, marking the
conclusion of the project.
This extended method statement provides a comprehensive guide for the construction of slabs in an
existing trench, emphasizing safety, quality control, and adherence to project specifications.
Always consult with relevant professionals and authorities before undertaking construction activities and
adapt the method statement based on the specific requirements of your project and any applicable local
regulations.
The commitment to safety, attention to quality, and adherence to project specifications outlined in this
method statement aim to ensure a successful and compliant construction process.
14 | P a g e
METHOD STATEMENT SUBMITTAL FOR SLAB CONSTRUCTION FOR EXISTING TRENCH
Document Number Revision Date
ADFI-EME-GFTS/CES-MOS-05_R00 R00 11-11-2023
7. QUALITY CONTROL
• All the activities will be done according to approved ITP, and we will issue RFI for the activities that require
Witness and Hold points once finish the cable laying in a section. The concealed cable laying construction
should be inspected timely after completed according to approved ITP & Checklist Quality Dept. shall be
involved to prepare the acceptance record and inspection before backfilling. Correction shall be made in
time as soon as the disqualification is found during construction. After finishing repairing the new report
shall be submitted in time to the Quality Dept. for acceptance. After acceptance of cable laying, we will fill in
the checklist and submit it to Quality Dept. for approval.
4 Bedding inspection √ √
5 Backfilling inspection √ √
6 Inspection of Cable fixed √ √
Inspection of Cable Termination (for LV,
7 √ √
earthing cables)
Inspection of cable route marker
8 √ √
installation.
Inspection of Cable Termination (for
9 √ √
control cables)
10 Manufacturing of vertical grounding pole
11 Overlap length of grounding electrode √ √
12 Embedment depth of grounding electrode √ √
Concealment work acceptance before
13 √ √
backfilling
14 Backfilling √ √
Table 2: Control Point Setting in The Process of Operations
• Before a confined space work activity, a PTW for the confined space operation should be handled; the
confined space operator should undergo special training in the safety training of the confine space
operation, and then earned the confined space work permit.
• At the confined space work areas, mechanical ventilation and appropriate lighting equipment must be
provided.
• Appropriate personal protective equipment (PPE) provided and used standby man continuously present
during confined space entry.
16 | P a g e
METHOD STATEMENT SUBMITTAL FOR SLAB CONSTRUCTION FOR EXISTING TRENCH
Document Number Revision Date
ADFI-EME-GFTS/CES-MOS-05_R00 R00 11-11-2023
• Access and Egress - Safe access/egress shall always be provided for materials and operations. Where
emergency routes are required, these shall be determined, arranged, and instructions given prior to
commencement of the work.
• GFTS/CES shall ensure that all first aid facilities are appropriately identified and marked with the recognized
first aid sign, as per OSHAD-SF – CoP 17.0 – Safety Signage and Signals, and that the environment where first
aid treatment may take place is, as far as reasonably practicable, free from hazards.
• Smoking will be strictly prohibited anywhere in the construction area and site offices. Smoking only in
designated areas.
17 | P a g e
METHOD STATEMENT SUBMITTAL FOR SLAB CONSTRUCTION FOR EXISTING TRENCH
Document Number Revision Date
ADFI-EME-GFTS/CES-MOS-05_R00 R00 11-11-2023
• Material shall not be placed/allocated in a way that interrupts and affects the set Site Emergency Evacuation
and Traffic Management Plans.
• Liaison with project team as per project requirements and ensured all the logistic protocols are in place.
• Ensuring social distance in offices/sites and in buses during traveling as per local rules and regulations.
• All vehicles including contractor and visitor vehicles shall be subject to the site rules for vehicles.
• Arrangements shall be made by the Employer to brief contractors and visitors’ drivers and operators on the
safety requirements of the site traffic routes.
• M/s GFTS/CES Site Engineer / Site Supervisors shall check and ensure all safety precautions are taken prior
to commencement of work. Also, they shall ensure method statement and risk assessment has been
communicated and a pre-task safety briefing is conducted to personnel involved in the task daily.
• Prior to commencing work on the roof (in the designated work area), it is imperative to set up safety cones
and cautionary tape to demarcate the work zone.
• Plant Equipment - All plant equipment associated with this activity shall be inspected prior to the works
commencing and at regular periods during the works to ensure that all required certification is current and
that the plant equipment is maintained in a safe and suitably working manner.
• All lifting activities using lifting equipment and accessories must only be carried out by third party trained
personnel, such as crane operator and rigger (slinger/signaler).
• Any injury / illness sustained whilst at work must be reported immediately and treated by a trained first
aider, HSE Officer and / or site nurse. Incident escalation reporting procedure shall always be followed.
18 | P a g e
METHOD STATEMENT SUBMITTAL FOR SLAB CONSTRUCTION FOR EXISTING TRENCH
Document Number Revision Date
ADFI-EME-GFTS/CES-MOS-05_R00 R00 11-11-2023
9. ENVIRONMENTAL ISSUES
• Housekeeping - always, M/s GFTS/CES supervision shall monitor the work area, to reduce, as far as
reasonably practical the storage of rubbish, waste materials and debris in the workplace. All waste materials
generated during the curse of the shift / day shall be removed from the workplace to a suitable waste
segregation area.
• Applicable provisions of legal requirements shall be observed in relation to the control of any substances
hazardous to health. Site legal register shall be communicated to relevant person onsite to ensure the
effectiveness of every activity.
19 | P a g e
METHOD STATEMENT SUBMITTAL FOR SLAB CONSTRUCTION FOR EXISTING TRENCH
Document Number Revision Date
ADFI-EME-GFTS/CES-MOS-05_R00 R00 11-11-2023
• Materials and Waste Management - Material safety data sheet must be made available if any substances are
used for works to be carried out. Any waste materials, containers, etc. disposed of properly in the
designated skips / waste points.
• Contractors and subcontractors will ensure effective dust and emission control measures in place for every
dust generating activity carried out on site, not only to protect the health and safety of the no-site
workforce, but also members of the public in the locality.
• GFTS/CES will ensure all necessary precautions to control noise and in case of high noise exceeding
permissible exposure limit, precautionary measures will be in place like Earmuffs and Ear Plugs will be
provided to employees working near to the area.
• Sufficient ventilation will be provided as needed to maintain welding fumes and smoke below permissible
exposure limits. Where sufficient ventilation cannot be achieved, alternative methods will be developed.
20 | P a g e
METHOD STATEMENT SUBMITTAL FOR SLAB CONSTRUCTION FOR EXISTING TRENCH
Document Number Revision Date
ADFI-EME-GFTS/CES-MOS-05_R00 R00 11-11-2023
• Position cutting equipment and materials to allow safe movement and avoid overloading the work platform.
• Ensure secure and safe electrical connections, protecting against electrical hazards.
• Maintain clear communication between team members using hand signals or radios, with an established
emergency communication system.
• procedure reviews.
• Develop a comprehensive safety plan, including emergency procedures, and obtain any necessary permits.
• Regularly inspect cutting equipment to identify and address issues.
• Establish a rescue plan to safely retrieve workers in emergencies or in the event of a accident.
• Cutting procedures, we will comply once we start the activity.
• PTW systems shall be considered whenever it is intended to carry out work which may adversely affect the
safety of personnel, plant, or the environment.
• Operations must have vehicle headlights illuminated between sunset and sunrise or in conditions where
visibility is impaired due to adverse conditions, e.g., Fog, rain, or dust.
• Lighting - always, appropriate, and suitable lighting shall be provided to ensure the works can be undertaken
in a safe and competent manner.
• Health surveillance will be undertaken to workers upon the exposure of specified substances or hazardous
process including exposure to extremely hot working environment and a possible exposure to a possible
disease or adverse health effect.
• Work is to be planned so that an appropriate number of employees are acclimatized and prepared to work
in a high temperature environment, not work alone in heat stress areas, in accordance with OSHAD-SF – CoP
21 | P a g e
METHOD STATEMENT SUBMITTAL FOR SLAB CONSTRUCTION FOR EXISTING TRENCH
Document Number Revision Date
ADFI-EME-GFTS/CES-MOS-05_R00 R00 11-11-2023
30.0 - Lone Work and/or in Remote Locations. It must be ensured that no lone work will be initiated without
proper supervision.
• GFTS/CES shall provide adequate resources, as appropriate to ensure safe execution of work scope. Be
aware of the dangers of heat fatigue and dehydration.
• No worker should work on site outside of normal working hours unless a permit is obtained from the
contractor.
• The Emergency Response Coordinator assists the emergency team coordinator/ leader carry out his duties.
• In the event of the Incident controller not been present on site the emergency response coordinator will
assume the role of the incident controller.
• Fire Fighting and first aid training will be completed for emergency response team members.
• Safety helmet
• Safety footwear
• High visibility clothing
22 | P a g e
METHOD STATEMENT SUBMITTAL FOR SLAB CONSTRUCTION FOR EXISTING TRENCH
Document Number Revision Date
ADFI-EME-GFTS/CES-MOS-05_R00 R00 11-11-2023
Additional/alternative PPE will be worn for specific tasks. This PPE may include, but not limited to:
• Eye Protection appropriate to the task, Face shield, glasses, gloves
• Other gloves appropriate to the task
• Ear plugs/ear defenders as appropriate
11. APPENDIX
• Risk Assessment ADFI-EME-GFTS/CES-RA-05_R00
• Supporting documents of Crane Operator and appointed person – to be shared at the time of work.
23 | P a g e