NEOM RC Building EPC SOW

Contractor : Nesma United Industries Co. Ltd. Project Code: PM210011


Document No. : PM210011-NUI900-ZI3-00004 Rev. 00 Date Submitted: 21-June-23

NEOM GHE
NESMA Inspection and Test Plan
NESMA-ITP-ELE-002-Conduits ,Fittings and
Accessories

REVISION HISTORY

Rev Pages Date Description

Issued by Checked By Approved


June. Issued For Air Products
00 21, Review and Al Hambra Daie Bency Mohan Representative
2023 Approval
PROJECT CONTRACT NO: PM210011 INSPECTION AND TEST PLAN DOC. No.: NESMA-ITP-ELE-E-002
DESCRIPTION: Conduit System REV.: 00 DATE:
Procedure, Checklist / QVDs, ITRs Scope of
Comments
Specification Survey Reports Responsibilities
Activity
Inspection / Test Points IFC drawing, Calibration Certificates
No.
Manufacturer's recommendation Lab Test Reports NESMA AP NGHC
International Codes & Standards Approved Material Submittals
1.0 GENERAL / DOCUMENT REVIEW
Verify and ensure latest revision of IFC AP Approval of IFC drawings Tools & Equipment
1.1 drawings, Specifications, approved Material and Spec for Elec Install. 4EEL- Calibration Certificates, R R R
Submittals etc. are being utilized P27, Rev. 1, Sec.15 Checklist & Mat’l Submittal
Conduct a pre-construction Quality Control PM210011-000-WP4-00001
1.2 Minutes of meeting H W W
meeting Clause 6.9
PM210011-000-WP4-00001 AP Personnel approval
1.3 Personnel Qualification R R R
Clause section 9 confirmation.
Verify testing equipment, operating manuals, AP Approved tools &
PM210011-000-WP4-00001
1.4 and calibration certifications are available and Equipment Calibration H R R
Clause 5.1.8
current. Certificates
2.0 MATERIAL RECEIVING INSPECTION
Spec for Elec Install. 4EEL-P27,
AP Approved Material Submittal
EMT, HDG-RGS, LFMC, FMC Conduit, Fittings Rev. 1, Sec.15.1-8 & PM210011-
and Accessories NUI900-EM4-00004 rev.01,
document & NIC-ELE-MAT-002- H W W
Rev.00
Sec.11
Spec for Elec Install. 4EEL-P27,
PVC, uPVC, PVC Coated and Plastic Flexible Rev. 1, Sec.15.1-8 & PM210011- AP Approved Material Submittal
H W W
Conduit , Fittings and Accessories NUI900-EM4-00004 rev.01, document & NIC-ELE-MAT-002-
2.1 Sec.11 Rev.00
Supports: C-Channel, Boxes, Enclosure,
Threaded Rod, Bushing, Gland, hanger, Clip, Spec for Elec Install. 4EEL-P27, AP Approved Material Submittal
Clamp, Strut, Bolts & Nut, Spring Nut, Lock nut, Rev. 1, Sec.15.1-8 & PM210011- document & NIC-ELE-MAT-002-
NUI900-EM4-00004 rev.01, Rev.00 H W W
Screws, Anchor / Stud bolts, Fishers, Cable Tie,
Sec.11
Solvent, Lubricant, other similar in nature and
Accessories
3.0 INSTALLATION
Spec for Elec Install. 4EEL-P27,
EMT, HDG-RGS, LFMC, FMC Conduit, Rev. 1, Sec.15.1-8 & PM210011- NIC-ELE-INST-002-Rev.00
NUI900-EM4-00004 rev.01,
H W W
Boxes, Enclosure, Fittings and Accessories Checklist
Sec.12
3.1 Spec for Elec Install. 4EEL-P27,
PVC, uPVC, PVC Coated, Plastic Flexible Rev. 1, Sec.15, Spec. 4EL64201A NIC-ELE-INST-002-Rev.00
Conduit, Boxes, Enclosure, Fittings and MS-PM210011-NUI900-EM4- Checklist H W W
Accessories 00004 rev.01 Sec.12 and IFC
drawing

NESMA-ITP-ELE-02-Conduit System. Revision no. 00


PROJECT CONTRACT NO: PM210011 INSPECTION AND TEST PLAN DOC. No.: NESMA-ITP-ELE-E-002
DESCRIPTION: Conduit System REV.: 00 DATE:
Procedure, Checklist / QVDs, ITRs Scope of
Activity Comments
Inspection / Test Points Specification Survey Reports Responsibilities
No. IFC drawing, Calibration Certificates NESMA AP NGHC
Manufacturer's recommendation Lab Test Reports
Spec for Elec Install. 4EEL-P27,
Supports, Hanger, C-Channel, Unistrut, Clamp,
Rev. 1, Sec.15, Spec. 4EL64201A NIC-ELE-INST-002-Rev.00
Clip, Threaded Rod, Anchor Bolts, Bolt & Nut, MS-PM210011-NUI900-EM4- Checklist H W W
Spring Nut, Gland, Bushing, Fishers and other 00004 rev.01 Sec.12 and IFC
Fittings accessories drawing
3.2
Spec for Elec Install. 4EEL-P27,
Rev. 1, Sec.15, Spec. 4EL64201A NIC-ELE-INST-002-Rev.00
Boxes & Wiring Devices Installation MS-PM210011-NUI900-EM4- Checklist H W W
00004 rev.01 Sec.12 and IFC
drawing
Spec for Elec Install. 4EEL-P27,
Rev. 1, Sec.15, Spec. 4EL64201A NIC-ELE-INST-002-Rev.00
3.3 Building Wires and Cables Pulling into Conduit MS-PM210011-NUI900-EM4- Checklist H W W
00004 rev.01 Sec.12 and IFC
drawing
5.0 FINAL DOCUMENTATION
TE-PRJEX-60008 Rev.02 PQP
Non-Conformance closed out
Ensure that Non-Conformance, Rejections 1.2 and Spec for Elec Install.
5.1 reports and work inspection R R R
and Corrective Action have been closed out 4EEL-P27, Rev. 1, chapter request acceptance
Sec.15
Verify completeness of all duly signed QC TE-PRJEX-60008 Rev.02 PQP
AP Approved tools &
Inspection Records inclusive of related reports 1.2 and Spec for Elec Install.
5.2 Equipment Calibration R R R
i.e. Field Testing Report and Test Equipment 4EEL-P27, Rev. 1, chapter Certificates
Calibration Certificates. Sec.15
Ensure that all Quality Records generated TE-PRJEX-60008 Rev.02 PQP
during the construction stage shall be firmly 1.2 and Spec for Elec Install.
5.3 Quality log records and files R R R
maintained and organized (hard copies as 4EEL-P27, Rev. 1, chapter
well as electronic (soft) copies) Sec.15

Legend:

NESMA-ITP-ELE-02-Conduit System. Revision no. 00


1 Surveillance: Client Inspector representative to monitor work in progress without notice from Construction Organization

Witness: Client Inspector representative shall be notified of the timing of Inspection or test in advance. However, the inspection or test shall be performed as scheduled if the
2
QA/QC organization representative is not present.

Hold: Client Inspector representative shall be notified of the timing of inspection or test in advance. Inspection or test shall not be carried out without the Client Inspector
3
representative in attendance.

LEGEND

H Hold Point for QC Inspection/ Test R Review

W Witness Inspection/Test I 100% Contractor Inspection/Test

S Surveillance