Professional Documents
Culture Documents
stoppage in the construction process, missing repairs after the completion of the project, defect
remediation of acceptance and handover"
• Publisher: Zhan's Subscribe to Publisher's New Book Alert New Feature Introduction
brief introduction
The ability to "never repeat the same mistakes" is as important as the correct construction!
Related parties: construction site director, site engineer, quality control and security personnel
●Design aspect ▎Not fully evaluating the construction conditions/not fully evaluating the
current situation of the base/unapproved construction drawings/unexamined construction
plans/changing the design for customer needs/imperfect structural design
●Material surface ▎Material quality defects/improper storage or deployment after entering the
site/wrong application method
☆ First-hand on-site experience, strive to be detailed with illustrations and real photos
Table of contents
Column Master the missing state and the key points of repair
Basic engineering
3. Damage, displacement or loss of the covering plate of the opening of the guide ditch
4. After the spoil pit is dug, the water accumulates or the wall collapses
14. Grout leakage at the end plate when the parent unit is pouring concrete
The key points of the construction of the hypothetical project of the diaphragm wall
25. The phenomenon of honeycomb and exposed steel bars in the pile body
27. The position of the pile core is not on the original measured pile core connection line
31. Improper erection of the support system causes deformation of the retaining wall
32. Collapse of safety support
34. Cracks appear in the welds of the middle column or gantry column
37. The phenomenon of loosening and displacement of the cladding sheet of the construction
platform
50. A large amount of water accumulated on the excavation surface of the earthwork
5. Reinforcement works
54. Floating rust, dirt or concrete residue on the surface of the steel bar
58. Openings, corners, and reinforcing steel bars passing through beams are wrong
60. The steel bar at the discontinuous end of the beam and column is not anchored with hooks
61. Wrong binding of steel bar anchor hooks at discontinuous ends of beams
64. Wrong binding of steel bars at the junction of large and small beams
65. Erroneous installation of the main reinforcement bar connector of the column
66. After setting out the structure, it is found that the position of the wall column reinforcement
is offset
69. The pipeline is arranged on the outside of the wall column reinforcement
70. Cut off column hoops and tie bars to install pipelines
78. The finish surface of the clear water formwork is not good
81. After the formwork is removed, the formwork is not sorted and reused
82. The wall column formwork does not leave a clean opening
7. Concrete engineering
90. Honeycombs appear on the structural surface after the concrete formwork is removed
91. Honeycombs appear at the bottom of the wall and column after the concrete formwork is
removed
94. There are cracks or cracks in the cured concrete after pouring
95. The finished surface of concrete pouring is not smooth
97. The edges and corners of beams, columns and walls are damaged and fall off
101. The concrete finish surface of the inclined floor slab is poor
103. The strength of the concrete compressive test is not up to the standard
8. Scaffolding project
109. The scaffolding is unstable or collapsed during the operation of the external wall
111. The looseness or deformation of the triangular bracket affects the stability of the scaffold
112. Cross tie rods and lower rails are loose or improperly removed
Renovation
9. Cement painting project
115. White bloom phenomenon appears on the smooth surface of cement powder
120. There are traces of trowel on the smooth surface of cement powder
122. Waves or small hard particles appear on the smooth surface of cement powder
133. The external wall tiles are damaged or wrongly laid at the corners of the bricks
136. The appearance of the water and electricity pipes passing through the wall bricks is messy
139. Poor construction of the waterway plugging outside the door and window frame
142. Water leakage from the bottom of the wall or threshold of the light compartment
143. The wall surface of the light compartment is uneven due to construction
147. Items hanging on the wall of the light compartment are loose
148. The sealing plate of the light compartment does not reach the top
153. Striped brush marks, orange peel or unevenness appear on the painted surface
161. After painting, the paint surface is not easy to dry or sticks back
163. Dark spots or dark spots appear on the woodwork paint surface
174. Cracks occur on the edge of the plate ceiling flat top
178. Rust marks appear on the flat top of the metal ceiling
186. Baihua Seeps from the Bottom of the Wall and Pillar
207. Rainwater infiltrates from the corners of door and window frames or cracks in walls
208. Rain water infiltrates from the edges of doors and windows
215. Water leaks from the vent pipe passing through the roof
220. The sound insulation effect of glass doors and windows is not good
221. Rainwater infiltrated into the room from the door and window frames
223. Distortion and deformation of metal door and window frame materials
224. Pollution and scratches on the surface of metal door and window frames
227. The automatic opening and closing of the fire door is not smooth
228. Deformation or sagging of fire door leaves
232. The sound is too loud when the metal rolling door is rolled
233. The surface of the metal rolling door is peeled off, corroded or deformed
235. The lifting and lowering of the metal rolling door is abnormal
243. The surface paint of the wooden door is wrinkled or peeled off
244. The key cannot be pulled out after being inserted into the door lock
245. The key is inserted into the door lock and the rotation is not smooth
247. Cracks between the door frame and the wall surface
251. Water leakage from the edges of glass and door and window frames
252. Bad gaskets are used in the glass groove to damage the glass
254. The sound insulation effect of glass doors and windows is not good
take back
sequence
Author's Preface
Planning to release six books in the series "CSI Seeing Construction Sites", the third volume
"Construction Contingency Repairs" is published this time. The content mainly introduces the
causes of defects, repair methods and preventive measures during or after construction.
When the building enters the after-sales service and warranty stage after completion, the
construction unit is often exhausted due to the defects of the building. During the review with
the customer service department, it was found that most of the defects were caused by
inattention or negligence during construction. If the supervisors can pay more attention during
the construction stage, the problems can be reduced, and the manpower and cost of
maintenance after the event can also be reduced. However, The on-site supervisors are busy
with work every day, and it is inevitable that they are sometimes negligent. There is no need to
blame them, just care and encourage them.
This book lists a total of 259 deficiencies, each of which points out the four directions of the
cause, inspection method, repair method, and preventive work. Check all the reasons suggested
in the book once to find out the real reason.
1. Chapters 1 to 4 belong to basic engineering. Problems in this part usually occur in the
construction stage, and the follow-up impact is huge, so special precautions should be taken.
The header part is separated by blue.
3. Chapters 9 to 15 belong to interior and exterior decoration projects. Most of the problems
gradually appeared after the completion of the project. Careful construction is the key to
prevent defects. The header part is separated by green.
4. Chapters 16 to 18 belong to the door and window project. Most of the problems occurred
after the completion of the project, so protective measures are indispensable. The book headers
are separated by purple.
There must be many missing problems during and after the construction of the building. This
book tries to collect and analyze personal experience, company information, third-party
suppliers and other channels. It is still impossible to include all the problems that occur, but the
concept of prevention is more important than cure It is very important. I hope that construction
workers can make full use of various control tables and checklists (to be listed in Volume 4)
when performing supervision tasks on site, and try their best to prevent problems from
occurring.