CHECK LIST FOR EQUIPMENT AND VESSELS ABOUT ISOLATION

Equipment or vessel isolation,engg,Cleaning and Re commisioning - Schedule Jobs


Date :- 16-05-2023
AREA - Crystallizer floor Zeolite Plant
EQUIPMENT - ZV07

Sl
No ACTIVITY NOS. SIZE DEPT. Status Remarks
.
PROCESS ACTIVITY
1 Close the dischrge valve ZR-XV-01D of ZR01. 1 80 NB Process
2 Close discharge valve ZV-XV-07B of ZV07. 1 80 NB Process
3 Close steam valve ZV-XV-07A of ZV07. 1 80 NB Process
4 Isolate the Loadcell ZR-WIA-07A. 1 Process
5 Isolate the Agitator AV07. 1 Process
ISSUE OF WORK PERMIT FOR FOLLOWING JOBS
6 ZV07 Inlet and Outlet valve to be isolated. Instrument
7 Agitator AV07 to be isolated. Electrical
8 Crystallizer Loadcell ZR-WIA-07A to be isolated. Instrument
PROCESS ACTIVITY
9 Check the ventilation Process
10 Check the oxygen level inside ZV07. Process
11 Check the isolation of above mentioned lines Process
12 Check the temperatures inside ZV07. Process
13 Issue the confined space work permit Process
CLEANING OF VESSEL/TAPPING/PIPELINES
14 Inside Vessel cleaning including wall Process
ENGINEERING REMOVAL,SERVICING OR REPLACEMENT
15 ZV-TI-07A and ZV-TI-07B need to be clean. Instrument
RE COMMISIONING JOBS
16 Refixing all the above mentioned pipe lines Mechanical
17 Refixing all the above mentioned valves Mechanical
18 Refixing the manhole. Mechanical
PRE COMMISIONING JOBS
19 Check the status of all work permit clearance Process
20 Check for all blinds are removed which was put during vessel isolation Process

SIGNATURE , DATE & TIME

Process Engineer

Mechanical in Charge

Mechanical Section In Charge

Electrical Section In Charge

Instrument Section In Charge


Process Area In Charge
CHECK LIST FOR EQUIPMENT AND VESSELS ABOUT ISOLATION

Equipment or vessel isolation,engg,Cleaning and Re commisioning - Schedule Jobs


Date :- 16-05-2023
AREA - Crystallizer floor Zeolite Plant
EQUIPMENT - ZV06

Sl
No ACTIVITY NOS. SIZE DEPT. Status Remarks
.
PROCESS ACTIVITY
1 Close the dischrge valve ZR-XV-01C of ZR01. 1 80 NB Process
2 Close discharge valve ZV-XV-06B of ZV06. 1 80 NB Process
3 Close steam valve ZV-XV-06A of ZV06. 1 80 NB Process
4 Isolate the Loadcell ZR-WIA-06A. 1 Process
5 Isolate the Agitator AV06. 1 Process
ISSUE OF WORK PERMIT FOR FOLLOWING JOBS
6 ZV06 Inlet and Outlet valve to be isolated. Instrument
7 Agitator AV06 to be isolated. Electrical
8 Crystallizer Loadcell ZR-WIA-06A to be isolated. Instrument
PROCESS ACTIVITY
9 Check the ventilation Process
10 Check the oxygen level inside ZV06. Process
11 Check the isolation of above mentioned lines Process
12 Check the temperatures inside ZV06. Process
13 Issue the confined space work permit Process
CLEANING OF VESSEL/TAPPING/PIPELINES
14 Inside Vessel cleaning including wall Process
ENGINEERING REMOVAL,SERVICING OR REPLACEMENT
15 ZV-TI-06A and ZV-TI-06B need to be clean. Instrument
RE COMMISIONING JOBS
16 Refixing all the above mentioned pipe lines Mechanical
17 Refixing all the above mentioned valves Mechanical
18 Refixing the manhole. Mechanical
PRE COMMISIONING JOBS
19 Check the status of all work permit clearance Process
20 Check for all blinds are removed which was put during vessel isolation Process

SIGNATURE , DATE & TIME

Process Engineer

Mechanical in Charge

Mechanical Section In Charge

Electrical Section In Charge

Instrument Section In Charge


Process Area In Charge
CHECK LIST FOR EQUIPMENT AND VESSELS ABOUT ISOLATION

Equipment or vessel isolation,engg,Cleaning and Re commisioning - Schedule Jobs


Date :- 16-05-2023
AREA - Crystallizer floor Zeolite Plant
EQUIPMENT - ZV05

Sl
No ACTIVITY NOS. SIZE DEPT. Status Remarks
.
PROCESS ACTIVITY
1 Close the dischrge valve ZR-XV-01B of ZR01. 1 80 NB Process
2 Close discharge valve ZV-XV-05B of ZV05. 1 80 NB Process
3 Close steam valve ZV-XV-05A of ZV05. 1 80 NB Process
4 Isolate the Loadcell ZR-WIA-05A. 1 Process
5 Isolate the Agitator AV05. 1 Process
ISSUE OF WORK PERMIT FOR FOLLOWING JOBS
6 ZV05 Inlet and Outlet valve to be isolated. Instrument
7 Agitator AV05 to be isolated. Electrical
8 Crystallizer Loadcell ZR-WIA-05A to be isolated. Instrument
PROCESS ACTIVITY
9 Check the ventilation Process
10 Check the oxygen level inside ZV05. Process
11 Check the isolation of above mentioned lines Process
12 Check the temperatures inside ZV05. Process
13 Issue the confined space work permit Process
CLEANING OF VESSEL/TAPPING/PIPELINES
14 Inside Vessel cleaning including wall Process
ENGINEERING REMOVAL,SERVICING OR REPLACEMENT
15 ZV-TI-05A and ZV-TI-05B need to be clean. Instrument
RE COMMISIONING JOBS
16 Refixing all the above mentioned pipe lines Mechanical
17 Refixing all the above mentioned valves Mechanical
18 Refixing the manhole. Mechanical
PRE COMMISIONING JOBS
19 Check the status of all work permit clearance Process
20 Check for all blinds are removed which was put during vessel isolation Process

SIGNATURE , DATE & TIME

Process Engineer

Mechanical in Charge

Mechanical Section In Charge

Electrical Section In Charge

Instrument Section In Charge


Process Area In Charge
CHECK LIST FOR EQUIPMENT AND VESSELS ABOUT ISOLATION

Equipment or vessel isolation,engg,Cleaning and Re commisioning - Schedule Jobs


Date :- 16-05-2023
AREA - Crystallizer floor Zeolite Plant
EQUIPMENT - ZV04

Sl
No ACTIVITY NOS. SIZE DEPT. Status Remarks
.
PROCESS ACTIVITY
1 Close the dischrge valve ZR-XV-01A of ZR01. 1 80 NB Process
2 Close discharge valve ZV-XV-04B of ZV04. 1 80 NB Process
3 Close steam valve ZV-XV-04A of ZV04. 1 80 NB Process
4 Isolate the Loadcell ZR-WIA-04A. 1 Process
5 Isolate the Agitator AV04. 1 Process
ISSUE OF WORK PERMIT FOR FOLLOWING JOBS
6 ZV04 Inlet and Outlet valve to be isolated. Instrument
7 Agitator AV04 to be isolated. Electrical
8 Crystallizer Loadcell ZR-WIA-04A to be isolated. Instrument
PROCESS ACTIVITY
9 Check the ventilation Process
10 Check the oxygen level inside ZV04. Process
11 Check the isolation of above mentioned lines Process
12 Check the temperatures inside ZV04. Process
13 Issue the confined space work permit Process
CLEANING OF VESSEL/TAPPING/PIPELINES
14 Inside Vessel cleaning including wall Process
ENGINEERING REMOVAL,SERVICING OR REPLACEMENT
15 ZV-TI-04A and ZV-TI-04B need to be clean. Instrument
RE COMMISIONING JOBS
16 Refixing all the above mentioned pipe lines Mechanical
17 Refixing all the above mentioned valves Mechanical
18 Refixing the manhole. Mechanical
PRE COMMISIONING JOBS
19 Check the status of all work permit clearance Process
20 Check for all blinds are removed which was put during vessel isolation Process

SIGNATURE , DATE & TIME

Process Engineer

Mechanical in Charge

Mechanical Section In Charge

Electrical Section In Charge

Instrument Section In Charge


Process Area In Charge
CHECK LIST FOR EQUIPMENT AND VESSELS ABOUT ISOLATION

Equipment or vessel isolation,engg,Cleaning and Re commisioning - Schedule Jobs


Date :- 16-05-2023
AREA - Reactor floor Zeolite Plant
EQUIPMENT - ZR01

Sl
No ACTIVITY NOS. SIZE DEPT. Status Remarks
.
PROCESS ACTIVITY
1 Close the dischrge valve ZV-XV-01B of ZV01. 1 80 NB Process
2 Close the dischrge valve ZV-XV-02B and manual globe valve of ZV02. 1 80 NB Process
3 Close the dischrge valve ZV-XV-03B of ZV03. 1 80 NB Process
4 Close discharge valve ZV-XV-01A of ZR01. 1 80 NB Process
5 Close discharge valve ZV-XV-01B of ZR01. 1 80 NB Process
6 Close discharge valve ZV-XV-01C of ZR01. 1 80 NB Process
7 Close discharge valve ZV-XV-01D of ZR01. 1 80 NB Process
8 Isolate the Loadcell ZR-WIC-01. 1 Process
9 Isolate the Agitator AR01. 1 Process
ISSUE OF WORK PERMIT FOR FOLLOWING JOBS
10 ZR01 Inlet and Outlet valve to be isolated. Instrument
11 Reactor Agitator AR01 to be isolated. Electrical
12 Reactor Loadcell ZR-WIC-01 to be isolated. Instrument

PROCESS ACTIVITY
13 Check the ventilation Process
14 Check the oxygen level inside ZR01. Process
15 Check the isolation of above mentioned lines Process
16 Check the temperatures inside ZR01. Process
17 Issue the confined space work permit Process
CLEANING OF VESSEL/TAPPING/PIPELINES
18 Inside Vessel cleaning including wall Process
ENGINEERING REMOVAL,SERVICING OR REPLACEMENT
19 ZR-TI-01 need to be clean. Instrument
RE COMMISIONING JOBS
20 Refixing all the above mentioned pipe lines Mechanical
21 Refixing all the above mentioned valves Mechanical
22 Refixing the manhole. Mechanical
PRE COMMISIONING JOBS
23 Check the status of all work permit clearance Process
24 Check for all blinds are removed which was put during vessel isolation Process

SIGNATURE , DATE & TIME

Process Engineer

Mechanical in Charge

Mechanical Section In Charge

Electrical Section In Charge

Instrument Section In Charge


Process Area In Charge