: GAC-12-VX-RMH-LAH-006
Attachment - 1
Pre-Commissioning Checks: Generator Step Up Transformer (GSUT)
Transformer/Item No.
System / Equipment
CHECKED
REMARKS
ACTIVITIES OK
Calik / LII
Attachment - 2
Pre Commissioning Test: Insulation Resistance (IR) Test
Doc. No. : GAC-12-VX-RMH-LAH-006
Transformer/Item No.
System / Equipment
Before measuring the insulation resistance, it should be made sure that the bushings are cleaned thoroughly
with clean cotton cloth and HV neutral is disconnected from Earth.
After successful completion of IR test the earth connection to HV neutral to be restored. The insulation
resistance as per following table should be measured with 5 kV Insulation Tester.
It is preferable to have a motor operated “Insulation Tester” and the readings taken after one minute (60
Seconds) from starting shall be recorded as IR value.
When IR test is completed for any winding, discharge the static charge by static discharge stick or by IR tester
with automatic discharging capabilities.
Test Results
Ambient temperature__________
Calik / LII
Attachment - 3
Pre Commissioning Test: Voltage ratio test on each tap
Doc. No. : GAC-12-VX-RMH-LAH-006
Transformer/Item No.
System / Equipment
The ratio shall be checked on all taps and between all the windings and the results should roughly tally with
factory test reports as well as the rating and diagram plate details. Ratio shall be checked by applying a three
phase 380V supply on the high voltage side and measuring the voltage on the low voltage side at all tap
positions.
Test Results
Calik / LII
Attachment - 4
Pre Commissioning Test: Resistance Measurement of Windings
Doc. No. : GAC-12-VX-RMH-LAH-006
Transformer/Item No.
System / Equipment
Kelvin Bridge meter or low resistance tester shall be used for the measurement of resistance at all windings. Tapped
winding resistance shall be measured at all tap positions. Absolute steady reading should be obtained for minimum 1
minute. The tap winding resistance trend shall be gradually decreasing with increase in tap position.
A. Resistance of HV Winding
Ambient temperature__________
B. Resistance of LV Winding
Doc. No. : GAC-12-VX-RMH-LAH-006
Ambient temperature__________
NOTE:
i. Formula for calculating the resistance at 75°C: R 75 = RT (235+75)/ (235+T), where RT = Resistance
Measured At Winding Temperature T.
Calik / LII
Attachment - 5
Pre Commissioning Test: Gas Operated Relays (Buchholz Relay) of Transformer
Doc. No. : GAC-12-VX-RMH-LAH-006
Transformer/Item No.
System / Equipment
Check whether the gas operated relay is mounted as per drawing. Check the operation of the alarm and trip
contacts to the relay independently by draining oil through drain valve. During this test, isolating valves at both
the ends of the Buchholz Relay shall be closed. Open the vent valve and then open the drain valve to drain the
oil from Buchholz Relay slowly. Air will enter in to the relay slowly and alarm & trip contacts will be closed one
after another. The air from the Buchholz relay shall be released after the test.
Test Results
Calik / LII
Attachment - 6
Pre Commissioning Test: Auxiliary Equipments
Doc. No. : GAC-12-VX-RMH-LAH-006
Transformer/Item No.
System / Equipment
The setting and correct working of the alarm & trip contacts of winding temperature indicator (WTI) and oil
temperature indicator (OTI) shall be verified by conducting the following steps –
Test Results
Temperature Measured
Reading of OTI (C) Reading of WTI (C) Remarks
By Thermometer (C)
30
40
50
60
70
80
90
100
The setting and correct working of the contacts for operation of the cooling fans shall be verified by conducting
the following steps –
Test Results
Calik / LII
Attachment - 7
Pre Commissioning Test: Oil Test
Doc. No. : GAC-12-VX-RMH-LAH-006
Transformer/Item No.
System / Equipment
Test Results
Calik / LII
Attachment - 8
Commissioning Checks: GSUT for GTG
Doc. No. : GAC-12-VX-RMH-LAH-006
Transformer/Item No.
System / Equipment
CHECKED
ACTIVITIES OK REMARKS
Test Results
Date Time 220kV Bus Voltage (kV) LV side Voltage (kV) Ambient Winding Oil Remarks
Doc. No. : GAC-12-VX-RMH-LAH-006
Notes :
a) Voltage at 6.3kV incomer panel shall be recorded as per commissioning procedure of UAT & IPBD.
b) After 6 hours of no load operation transformer can be loaded.
Calik / LII
Attachment – 9
Commissioning Checks: GSUT for STG
Doc. No. : GAC-12-VX-RMH-LAH-006
Transformer/Item No.
System / Equipment
ACTIVITIES CHECKED
REMARKS
OK
1. Before energizing the transformer check the
following:
a. Check the surrounding of the transformer is
clean and freely accessible.
b. Check & ensure that Neutral of the transformer
is properly connected to earth.
c. Check & ensure that transformer tap is at
normal tap position.
d. Ensure all pre-commissioning checks and tests
of transformer have been successfully
completed (Refer attachments -1 to 10) and test
results are satisfactory.
2. Check and ensure that all pre-commissioning checks
and tests of generator have been successfully
completed and are ready for energization
3. Check and ensure that pre-commissioning checks
and tests of 220kV bay have been successfully
completed.
4. Check and ensure that all pre-commissioning checks
and tests of IPBD has been successfully completed.
5. Check and ensure that IPBD is properly connected
with GSUT and Generator.
6. Check and ensure that earth switches of 220kV
isolators and isolators are open. Also ensure that
220kV CB is open.
7. Check and ensure that all relays for Generator
protections have been successfully tested and set at
recommended settings.
8. STG will be started and commissioned as per
commissioning sequence of STG.
9. The transformer will be energized with increase of
voltage at generator terminal.
10. After reaching the rated voltage at generator
terminal check that no abnormality (voice/vibration)
are observed in the IPBD and GSUT.
11. Check voltage and phase sequence at the secondary
side of 220kV VT. Phase sequence of 220kV VT and
VT at generator terminal shall be same as phase
sequence of 220kV bus VT.
12. Check and ensure that when the synchroscope of
generator synchronizing circuit is at 12 o’clock
position voltage difference between same phase
voltage of generator terminal VT and 220kV VT is
Doc. No. : GAC-12-VX-RMH-LAH-006
Test Results
220kV Bus Voltage (kV) LV side Voltage (kV) Ambient Winding Oil
Date Time L1-L2 L2-L3 L3-L1 L1-L2 L2-L3 L3-L1 Temp 0C Temp 0C Temp 0C Remarks
220kV Bus Voltage (kV) 220kV Side Current (A) Ambient Winding Oil
Date Time L1-L2 L2-L3 L3-L1 L1 L2 L3 Temp 0C Temp 0C Temp 0C Remarks
Doc. No. : GAC-12-VX-RMH-LAH-006
Calik / LII