Daily Monitoring Report Theodore Data Center
Daily Monitoring Report Theodore Data Center
Equipment Name ▲
Running Status.
Chilled Water Pump 1 Standby
Chilled Water Pump 2 Normal
Condenser Pump 1 Normal
Condenser Pump 2 Standby
Cooling Tower 1 Standby
Cooling Tower 2 Normal
Number
▲
General Power Equipment Status Running Status..
1 MVSG A Normal
2 MVSG B Normal
3 LVSG A Normal
4 ATS-LVSG A Normal
5 LVSG B Normal
6 ATS-LVSG B Normal
7 LVSG C1 Normal
8 ATS-LVSG C1 Normal
9 LVSG C2 N/A
10 ATS-LVSG C2 N/A
11 LVSG D1 Normal
12 ATS-LVSG D1 Normal
13 LVSG D2 N/A
14 ATS-LVSG D2 N/A
15 FSS A (Novec) Data Hall 1&2 Normal
16 FSS B(Novec) Data Hall 1&2 Normal
17 Transformer C Normal
18 Transformer D Normal
19 FSS A (Novec) Data Center 1 Normal
20 FSS B (Novec) Data Center 3 Normal
21 Transformer A Normal
22 Transformer B Normal
Number
▲
Room Name Running Status...
Number
▲
Emergency Backup Power Status..
1 Genset 1 Standby
2 Genset 2 Standby
3 Fuel Pump 1 Auto
4 Fuel Pump 2 Standby
5 Synchro 1 Panel Standby
6 Synchro 2 Panel Online
7 Daytank 1&2 (Liters) 6176.25
8 Daytank 3 (Liters) 7362.9
9 Total Diesel Fuel Reserve (Liters) 13539.15
Number ▲
2F Parameter Reading LVSG A DP Rectifier A LVSG B DP Rectifier B UPS 1 UPS 2
1 Voltage (LL) Line 1 398 399 404 405 397 402
2 Voltage (LL) Line 2 406 406 408 408 404 406
3 Voltage (LL) Line 3 408 408 398 398 406 397
4 Current (LL) Line 1 486 196 567 197 162 123
5 Current (LL) Line 2 448 199 579 197 135 120
6 Current (LL) Line 3 490 197 567 195 140 118
7 Power KW (Ave) 320.29 136.35 391.57 135.48 90.95 72.08
Number
▲
2F Parameter Reading. CPS1 (Rectifier Rm2) CPS2 (Rectifier Rm1) CPS3 (Rectifier Rm2) CPS4 (Rectifier Rm1)
2F DC1 (DC-DC
Converters) ▼
1-1 1-2 1-3 1-4 1-5 1-6 2-1 2-2 2-3 2-4 2-5 2-6 3-1 3-2 4-1 4-2
Current (Amps) 546 391 343 334 299 356 611 308 414 313 266 343 604 300 595 295
% Utilization 36 25 22 22 20 23 40 20 27 20 17 22 39 19 39 19
2F DC2 (DC-DC
Converters) ▼
3-3 3-4 4-3 4-4
Current (Amps) 39 2 38 2
% Utilization 2 0 2 0
Third Floor Electrical Rooms
Number
▲
Rooms Name... Running Status.....
Number ▲
3F Parameter Reading LVSG C LVSG D UPS 1. UPS 2.
1 Voltage (LL) Line 1 403 403 398 399
2 Voltage (LL) Line 2 406 407 398 399
3 Voltage (LL) Line 3 396 397 398 399
4 Current (LL) Line 1 32 32 3 3
5 Current (LL) Line 2 27 27 19 10
6 Current (LL) Line 3 26 19 10 7
7 Power KW (Ave) 16.04 16.3 90.95 72.08
Number ▲
3F UPS 1 and UPS 2 Rooms Load on. Inverter. Bypass. Battery.
1 3F UPS 1 unit Load on Inverter Normal - -
2 3F UPS Battery 1 - - - Normal
3 3F UPS 2 unit Load on Inverter Normal - -
4 3F UPS Battery 2 - - - Normal
Remarks
Technician on Duty
Jhesly Asuncion/Christian Mortel/Marwin Zaraspe/Rico Gonzales
Engineer on Duty
Paul Cansino/Rose Ann Ditan