Description Affected areas of activity

Berm and canal construction


Tank farm backfilling Sand bedding, HDPE and gravel bedding
Pipe supports construction
Pipe supports AFC dwg Pipe supports construction

Perimeter fence along ROW 3.5m fence construction still pending

Eyewash Depends on routing

Pipe Bridge Construction of pipe bridge is pending

FDAS Ceiling closure on bldgs

Explosion proof lights Ceiling final touch up

DBC laying Driveway preparation and concreting


Remarks

K&F already started, however, compaction is not yet done

Proper detail needed prior to construction

No advise yet from SPI

Piping will be exposed if done on the later part

WSO not yet lifted

Access areas provided

Warehouse, MCC Genset and Guardhouse are ready to receive those lights

Excavation done on main route, PVC installed as well