METHOD STATEMENT
FOR
LAYING PIPES IN DUCT BANKS, CONDUITS IN
SAIPEM S.p.A.
THIS DOCUMENT IS THE PROPERTY OF ABUDHABI GAS DEVELOPMENT COMPANY LIMITED AND CONTAINS INFORMATION WHICH IS PROPRIETARY. THIS INFORMATION
TO BE HELD IN CONFIDENCE. NO DISCLOSURE OR OTHER USE OF THIS DOCUMENT IS TO BE MADE WITHOUT THE PRIOR WRITTEN CONSENT OF ABUDHABI GAS
DEVELOPMENT COMPANY LIMITED
CLIENT JOB UNIT
Abu Dhabi Gas Development Company Ltd. 032090 200
PLANT LOCATION DES.DOC.No AUH/1341/QA&QC/
Abu Dhabi - Emirates C/MS-05
Saipem No.: 0200-CA-E-2D0005
PROJECT TITLE Rev.
SHAH PROCESS PLANT – EPC2
Sht. 2 of 10
B1 B2
Doc. No. MP02-0200-14-MES-2D0005
INDEX
1. PURPOSE
3. SCOPE
4. REFERENCES
5. DEFINITIONS / ABBREVIATIONS
6. RESPONSIBILITIES
9. SAFETY
10. QA&QC
11. JHA
MP02-0200-14-MES-2D0005_B2.doc
File name: DES. REF.FORM NO.
THIS DOCUMENT IS THE PROPERTY OF ABUDHABI GAS DEVELOPMENT COMPANY LIMITED AND CONTAINS INFORMATION WHICH IS PROPRIETARY. THIS INFORMATION
TO BE HELD IN CONFIDENCE. NO DISCLOSURE OR OTHER USE OF THIS DOCUMENT IS TO BE MADE WITHOUT THE PRIOR WRITTEN CONSENT OF ABUDHABI GAS
DEVELOPMENT COMPANY LIMITED
CLIENT JOB UNIT
Abu Dhabi Gas Development Company Ltd. 032090 200
PLANT LOCATION DES.DOC.No AUH/1341/QA&QC/
Abu Dhabi - Emirates C/MS-05
Saipem No.: 0200-CA-E-2D0005
PROJECT TITLE Rev.
SHAH PROCESS PLANT – EPC2
Sht. 3 of 10
B1 B2
Doc. No. MP02-0200-14-MES-2D0005
1. PURPOSE:
The purpose of this method statement is to clarify the works to be carried out for the pipe laying in
duct banks, conduits in concrete and buried conduits in areas specified in approved drawings and
specifications.
3. SCOPE
The scope of this method statement covers pipe laying in duct banks, conduits in concrete
and buried conduits to be done in Shah Gas Development Project for the Plant units
U726,U727,U740,U742 and General Area Unit 0230.
4. REFERENCES
Specification:-
MP02-0200-14-MES-2D0005_B2.doc
File name: DES. REF.FORM NO.
THIS DOCUMENT IS THE PROPERTY OF ABUDHABI GAS DEVELOPMENT COMPANY LIMITED AND CONTAINS INFORMATION WHICH IS PROPRIETARY. THIS INFORMATION
TO BE HELD IN CONFIDENCE. NO DISCLOSURE OR OTHER USE OF THIS DOCUMENT IS TO BE MADE WITHOUT THE PRIOR WRITTEN CONSENT OF ABUDHABI GAS
DEVELOPMENT COMPANY LIMITED
CLIENT JOB UNIT
Abu Dhabi Gas Development Company Ltd. 032090 200
PLANT LOCATION DES.DOC.No AUH/1341/QA&QC/
Abu Dhabi - Emirates C/MS-05
Saipem No.: 0200-CA-E-2D0005
PROJECT TITLE Rev.
SHAH PROCESS PLANT – EPC2
Sht. 4 of 10
B1 B2
Doc. No. MP02-0200-14-MES-2D0005
o Addendum to Specification for on site bund construction (MP02-0230-14-ADD-086003)
o BS – British Standard
5. DEFINITIONS / ABBREVIATIONS
Contractor SAIPEM
CM Construction Manager
CE Civil Engineer
6. RESPONSIBILITIES
MP02-0200-14-MES-2D0005_B2.doc
File name: DES. REF.FORM NO.
THIS DOCUMENT IS THE PROPERTY OF ABUDHABI GAS DEVELOPMENT COMPANY LIMITED AND CONTAINS INFORMATION WHICH IS PROPRIETARY. THIS INFORMATION
TO BE HELD IN CONFIDENCE. NO DISCLOSURE OR OTHER USE OF THIS DOCUMENT IS TO BE MADE WITHOUT THE PRIOR WRITTEN CONSENT OF ABUDHABI GAS
DEVELOPMENT COMPANY LIMITED
CLIENT JOB UNIT
Abu Dhabi Gas Development Company Ltd. 032090 200
PLANT LOCATION DES.DOC.No AUH/1341/QA&QC/
Abu Dhabi - Emirates C/MS-05
Saipem No.: 0200-CA-E-2D0005
PROJECT TITLE Rev.
SHAH PROCESS PLANT – EPC2
Sht. 5 of 10
B1 B2
Doc. No. MP02-0200-14-MES-2D0005
Area CE will ensure that the excavation and backfilling activities are conducted according
to this method statement, latest approved Project drawings & relevant specifications for the
activities and will be directly reporting to CM.
CE & surveyor will ensure that location & levels of the excavations are as per approved
drawings.
QA&QC civil will ensure that all work is executed according to ITP and that requirements of
quality dossier are fulfilled.
Safety and Construction supervision will be carried out by Subcontractor under supervision
of Contractor.
7.1 EXCAVATION
Before starting the activity, site surveyor shall mark the coordinates as per approved latest
drawings.
Excavation area shall be marked by a qualified and competent surveyor.
All the Excavation works will be carried out as per the following Method Statements:
Excavation shall be done with help of suitable equipment as per site conditions with a proper
Contractor permit to work System.
If any underground services / utilities found; only hand excavation shall be carried
After the Blinding concrete and water proofing activities, the Surveyor shall mark the positions of
the approved PVC Pipes on the lean concrete.
MP02-0200-14-MES-2D0005_B2.doc
File name: DES. REF.FORM NO.
THIS DOCUMENT IS THE PROPERTY OF ABUDHABI GAS DEVELOPMENT COMPANY LIMITED AND CONTAINS INFORMATION WHICH IS PROPRIETARY. THIS INFORMATION
TO BE HELD IN CONFIDENCE. NO DISCLOSURE OR OTHER USE OF THIS DOCUMENT IS TO BE MADE WITHOUT THE PRIOR WRITTEN CONSENT OF ABUDHABI GAS
DEVELOPMENT COMPANY LIMITED
CLIENT JOB UNIT
Abu Dhabi Gas Development Company Ltd. 032090 200
PLANT LOCATION DES.DOC.No AUH/1341/QA&QC/
Abu Dhabi - Emirates C/MS-05
Saipem No.: 0200-CA-E-2D0005
PROJECT TITLE Rev.
SHAH PROCESS PLANT – EPC2
Sht. 6 of 10
B1 B2
Doc. No. MP02-0200-14-MES-2D0005
Reinforcement at the bottom shall be placed first and then the PVC pipes shall be placed as per final
position.
External side be installed and properly supported as per dimension indicated into the drawings.
Tie-ins proper the conduit to avoid moving and to avoid uplifting during concrete pouring.
7.2.2 CONCRETING
The PVC pipe levels and positions will be checked and upon approval by the QC inspector, the
pouring of concrete shall be in accordance with the following Method Statements:
After the excavation of the trench has been completed, the base of the trench shall be compacted,
cleaned at the required level. Surveyor shall mark the positions of the PVC Pipes on the soil.
Proper sand bed shall be done as indicated into the approved latest drawings.
Laying of the PVC pipes on the sand bed and backfilled with suitable material as per approved
drawings.
Warning tiles shall be placed above the PVC pipes as per approved project drawings.
The backfill material shall be sourced from suitable stockpile or from excavated material if
suitable for the project.
The CE shall ensure that particular area/structure has been released for backfilling
by QC department.
MP02-0200-14-MES-2D0005_B2.doc
File name: DES. REF.FORM NO.
THIS DOCUMENT IS THE PROPERTY OF ABUDHABI GAS DEVELOPMENT COMPANY LIMITED AND CONTAINS INFORMATION WHICH IS PROPRIETARY. THIS INFORMATION
TO BE HELD IN CONFIDENCE. NO DISCLOSURE OR OTHER USE OF THIS DOCUMENT IS TO BE MADE WITHOUT THE PRIOR WRITTEN CONSENT OF ABUDHABI GAS
DEVELOPMENT COMPANY LIMITED
CLIENT JOB UNIT
Abu Dhabi Gas Development Company Ltd. 032090 200
PLANT LOCATION DES.DOC.No AUH/1341/QA&QC/
Abu Dhabi - Emirates C/MS-05
Saipem No.: 0200-CA-E-2D0005
PROJECT TITLE Rev.
SHAH PROCESS PLANT – EPC2
Sht. 7 of 10
B1 B2
Doc. No. MP02-0200-14-MES-2D0005
The backfill material will be placed in layers according to the specification (DGS-1486-001&
MP02-0230-14-ADD-086001)
Backfill will be tested by the test laboratory and frequency of test will be according to
agreed QCP (MP02-0230-92-SPE-0D9612).
8.1 EXECUTION
All equipment shall be inspected and approved by the Contractor before attempting work on
site and have valid certificates & inspection sticker.
A register of all machinery & equipment shall be maintained and held available for
inspection. Equipment shall be visually checked prior to each major work and validity of
inspection status will be verified.
All equipment shall have their type & capacity clearly indicated with a permanent stamp
or an approved identification alternative.
Should additional or different equipment be required during the course of the works,
they will be mobilized as necessary.
Excavator/JCB
Dump Truck
Compactor / Roller
Plate Compactor
Water Tanker
8.2. SAFETY
Safety helmet
MP02-0200-14-MES-2D0005_B2.doc
File name: DES. REF.FORM NO.
THIS DOCUMENT IS THE PROPERTY OF ABUDHABI GAS DEVELOPMENT COMPANY LIMITED AND CONTAINS INFORMATION WHICH IS PROPRIETARY. THIS INFORMATION
TO BE HELD IN CONFIDENCE. NO DISCLOSURE OR OTHER USE OF THIS DOCUMENT IS TO BE MADE WITHOUT THE PRIOR WRITTEN CONSENT OF ABUDHABI GAS
DEVELOPMENT COMPANY LIMITED
CLIENT JOB UNIT
Abu Dhabi Gas Development Company Ltd. 032090 200
PLANT LOCATION DES.DOC.No AUH/1341/QA&QC/
Abu Dhabi - Emirates C/MS-05
Saipem No.: 0200-CA-E-2D0005
PROJECT TITLE Rev.
SHAH PROCESS PLANT – EPC2
Sht. 8 of 10
B1 B2
Doc. No. MP02-0200-14-MES-2D0005
Safety Shoes
Gloves
Safety Glasses
Sieves
9. SAFETY INSTRUCTIONS
All personnel involved shall use necessary PPE as required such as safety helmet, glasses,
coverall, shoes, gloves, ear plugs etc.
The workers shall be made aware of safety requirements related to this activity through
daily tool box and safety talk.
All required work permits shall be acquired and kept available at respective work site
hanged clearly in plastic folders.
All stages of work and testing shall be documented in accordance with the appoved
QCP(MP02-0230-92-SPE-0D9612)
11 JHA
MP02-0200-14-MES-2D0005_B2.doc
File name: DES. REF.FORM NO.
THIS DOCUMENT IS THE PROPERTY OF ABUDHABI GAS DEVELOPMENT COMPANY LIMITED AND CONTAINS INFORMATION WHICH IS PROPRIETARY. THIS INFORMATION
TO BE HELD IN CONFIDENCE. NO DISCLOSURE OR OTHER USE OF THIS DOCUMENT IS TO BE MADE WITHOUT THE PRIOR WRITTEN CONSENT OF ABUDHABI GAS
DEVELOPMENT COMPANY LIMITED
CLIENT JOB UNIT
Abu Dhabi Gas Development Company Ltd. 032090 200
PLANT LOCATION DES.DOC.No AUH/1341/QA&QC/
Abu Dhabi - Emirates C/MS-05
Saipem No.: 0200-CA-E-2D0005
PROJECT TITLE Rev.
SHAH PROCESS PLANT – EPC2
Sht. 9 of 10
B1 B2
Doc. No. MP02-0200-14-MES-2D0005
MP02-0200-14-MES-2D0005_B2.doc
File name: DES. REF.FORM NO.
THIS DOCUMENT IS THE PROPERTY OF ABUDHABI GAS DEVELOPMENT COMPANY LIMITED AND CONTAINS INFORMATION WHICH IS PROPRIETARY. THIS INFORMATION
TO BE HELD IN CONFIDENCE. NO DISCLOSURE OR OTHER USE OF THIS DOCUMENT IS TO BE MADE WITHOUT THE PRIOR WRITTEN CONSENT OF ABUDHABI GAS
DEVELOPMENT COMPANY LIMITED
CLIENT JOB UNIT
Abu Dhabi Gas Development Company Ltd. 032090 200
PLANT LOCATION DES.DOC.No AUH/1341/QA&QC/
Abu Dhabi - Emirates C/MS-05
Saipem No.: 0200-CA-E-2D0005
PROJECT TITLE Rev.
SHAH PROCESS PLANT – EPC2
Sht. 10 of 10
B1 B2
Doc. No. MP02-0200-14-MES-2D0005
Steps Hazards Control Measures to be Enforced Remarks/
Action
MP02-0200-14-MES-2D0005_B2.doc
File name: DES. REF.FORM NO.
THIS DOCUMENT IS THE PROPERTY OF ABUDHABI GAS DEVELOPMENT COMPANY LIMITED AND CONTAINS INFORMATION WHICH IS PROPRIETARY. THIS INFORMATION
TO BE HELD IN CONFIDENCE. NO DISCLOSURE OR OTHER USE OF THIS DOCUMENT IS TO BE MADE WITHOUT THE PRIOR WRITTEN CONSENT OF ABUDHABI GAS
DEVELOPMENT COMPANY LIMITED
CLIENT JOB UNIT
Abu Dhabi Gas Development Company Ltd. 032090 200
PLANT LOCATION DES.DOC.No AUH/1341/QA&QC/
Abu Dhabi - Emirates C/MS-05
Saipem No.: 0200-CA-E-2D0005
PROJECT TITLE Rev.
SHAH PROCESS PLANT – EPC2
Sht. 11 of 10
B1 B2
Doc. No. MP02-0200-14-MES-2D0005
condition commencement of job. Authorized Gas
Ensure Gas testing is carried Tester
out prior to enter in to the
trench
Gas tester performed his
testing by using long probe
without entering the confined
space.
Take gas test on different
location and depths.
People should trained and
aware about the confined
space hazards
Evacuation procedure shall be
in place and explained to
everybody.
Ambulance and male nurse
shall be available at site.
Emergency Telephone No.
shall be displayed at site.
Appropriate barricade to be
Pipe fixing and Fall into maintained till the completion of Site
leveling excavation job fully. Supervisor
Collapse of Sign boards/ hazards blinking
trenches lights (for night) to be provided
Physical injury till the completion of work.
No vehicle will be permitted to
drive within 5 meter of the pit.
All workers are to wear
appropriate PPE.
Proper access to work should
be made.
MP02-0200-14-MES-2D0005_B2.doc
File name: DES. REF.FORM NO.
THIS DOCUMENT IS THE PROPERTY OF ABUDHABI GAS DEVELOPMENT COMPANY LIMITED AND CONTAINS INFORMATION WHICH IS PROPRIETARY. THIS INFORMATION
TO BE HELD IN CONFIDENCE. NO DISCLOSURE OR OTHER USE OF THIS DOCUMENT IS TO BE MADE WITHOUT THE PRIOR WRITTEN CONSENT OF ABUDHABI GAS
DEVELOPMENT COMPANY LIMITED
CLIENT JOB UNIT
Abu Dhabi Gas Development Company Ltd. 032090 200
PLANT LOCATION DES.DOC.No AUH/1341/QA&QC/
Abu Dhabi - Emirates C/MS-05
Saipem No.: 0200-CA-E-2D0005
PROJECT TITLE Rev.
SHAH PROCESS PLANT – EPC2
Sht. 12 of 10
B1 B2
Doc. No. MP02-0200-14-MES-2D0005
MP02-0200-14-MES-2D0005_B2.doc
File name: DES. REF.FORM NO.
THIS DOCUMENT IS THE PROPERTY OF ABUDHABI GAS DEVELOPMENT COMPANY LIMITED AND CONTAINS INFORMATION WHICH IS PROPRIETARY. THIS INFORMATION
TO BE HELD IN CONFIDENCE. NO DISCLOSURE OR OTHER USE OF THIS DOCUMENT IS TO BE MADE WITHOUT THE PRIOR WRITTEN CONSENT OF ABUDHABI GAS
DEVELOPMENT COMPANY LIMITED
13 of 13
THIS DOCUMENT IS THE PROPERTY OF ABUDHABI GAS DEVELOPMENT COMPANY LIMITED AND CONTAINS INFORMATION WHICH IS PROPRIETARY. THIS INFORMATION TO
BE HELD IN CONFIDENCE. NO DISCLOSURE OR OTHER USE OF THIS DOCUMENT IS TO BE MADE WITHOUT THE PRIOR WRITTEN CONSENT OF ABUDHABI GAS
DEVELOPMENT COMPANY LIMITED.