Method Statement for Excavation and

Backfilling for Underground Services

Status Code 2
Comments as Noted
1) Rename the document as "Method Statement for Excavation and Backfilling for
Underground Services"
2) For other comments refer the marked-up document
Coord PX3/P3, PX3M2
Dated 11-Apr-2015
TL/15/0709
ABU DHABI GA
AS INDUSTRIES LIMITED
(GASCO)
NEW RUWAIS OFFICE BUILDINGS
Doc : 0500604
4-MS-00-CA-0014
PROJEC
ECT No. 0500604
Method Sttatement for Road
Crossing Und
nderground Service Rev: A0 Page No. 2 of 11
Excavvation Works.

REVI
VISION CONTROL SHEET

REV. NO. DATE PAGE NO. DESCRIPTIION

A0 17-12-2014 All Issued for Review//Comments


ABU DHABI GA
AS INDUSTRIES LIMITED
(GASCO)
NEW RUWAIS OFFICE BUILDINGS
Doc : 0500604
4-MS-00-CA-0014
PROJEC
ECT No. 0500604
Method Sttatement for Road
Crossing Und
nderground Service Rev: A0 Page No. 3 of 11
Excavvation Works.

CONTENTS

1. Purpose

2. Scope

3. Definitions / Abbre
breviations

4. References

5. Responsibilities

6. HSE Requirement
nts

7. Equipment, Toolls and Tackles

8. Methodology

9. Inspection and T
Testing

10. Documentation

11. Attachments
ABU DHABI GA
AS INDUSTRIES LIMITED
(GASCO)
NEW RUWAIS OFFICE BUILDINGS
Doc : 0500604
4-MS-00-CA-0014
PROJEC
ECT No. 0500604
Method Sttatement for Road
Crossing Und
nderground Service Rev: A0 Page No. 4 of 11
Excavvation Works.
and backfilling
1. Purpose

The purpose of this document is to outline the sequences and metthods of works
intended to be used for the Road
Ro crossing excavation for underground service of new
office building.

The Contractor reserves thee right to adapt the methods of execution asa contained in
this document, modification to
t this document if required from time to tim
me according to
specific site conditions.

Engineer’s approval will b be obtained after each phase of the w works prior to
continuation of the works as per Site Inspection and Test Program (ITP))

2. Scope

The scope of work cover tthe activities related to underground workks for the New
Ruwais Office Buildings Pro oject No: 0500604 at GASCO NPB area fro om the existing
GASCO Maintenance buildiing and civil building service tie up pointt. This method
statement covers all requirem
ments for excavation, fabrication, installation
n, inspection.

3. Definitions / Abbreviations..
backfilling,compaction
COMPANY Abu Dhabi GAS Industries LTD (GASCO)
O) and reinstatement.

PROJECT New Ruwais Office Buildings Project.

CONTRACTOR M/s ACTCO GENERAL CONTRACTING


G CO., LLC.

SUBCONTRACTOR/SER
R Any company who contracts with the
VICE PROVIDER – CONTRACTOR to supply materials or execute
e work
or 3rd party service forming part of
o the main
contract.

SHALL Indicates a mandatory requirement

PICWS Person in charge at site

4. References.

The following reference docu uments, to the extent specified herein, form
m a part of this
method statement. When an n edition date is not indicated for a documment, the latest
edition in force at the time off contract award shall apply.
ABU DHABI GA
AS INDUSTRIES LIMITED
(GASCO)
NEW RUWAIS OFFICE BUILDINGS
Doc : 0500604
4-MS-00-CA-0014
PROJEC
ECT No. 0500604
Method Sttatement for Road
Crossing Und
nderground Service Rev: A0 Page No. 5 of 11
Excavvation Works.

4.1 Project Drawings.


Approved, Issued forr Construction (IFC) drawings.

4.2 Project Specificatio


ons.

DGS 1486.002 Rev..2 , 1783.001 and 1783.002

4.3 ITP AND CHECKLIST


IST

ITP for Excavation a


and Backfilling – 0500604-ITP-00-CA-001 Re
ev C0
Check List for Excavvation – 0500604#18(EXC-RE) Rev#1
Check List for Backffilling - 0500604#19(BF Form) Rev#1

5. Responsibilities.
5.1 Project Manager /Cons
struction manager

Has the responsibility to ennsuring that all the activity is done withou ut endangering
health and safety in accorda ance with the local legislation, client’s req
quirements and
stipulations laid down in thee HSE management system document. Ensure E that all
under groundwork related acccidents are reported, investigated and thatt corrective and
preventive measures are takken, the accident investigation team has the e power to stop
any work or operation underr his authority on health, safety or environm mental grounds
until effective measures have
e been taken.

5.2 HSE Engineer


Shall coordinate with the ssection managers to ensure that suitable arrangements,
including traffic signs, barrie
iers, and warning lights are in place with proper
p tools to
perform the excavation and b backfilling works in safe work manner.

We shall assign HSE offficers for performing internal inspectionss, advising to


employees on subjects and concerning
c health and safety.

5.3 Site Engineer/Supervis


sor

To ensure that all personnell are adequately trained for the relevant task;; that they are
using the correct equipment a and personal protective equipment; that alll relevant
hazards have been identifiedd; and that the respective permits to work forrmalities have
been correctly addressed, wh here required.

Responsible for providing the


e required PPE to his crew for the job as me
entioned herein
this procedure.
ABU DHABI GA
AS INDUSTRIES LIMITED
(GASCO)
NEW RUWAIS OFFICE BUILDINGS
Doc : 0500604
4-MS-00-CA-0014
PROJEC
ECT No. 0500604
Method Sttatement for Road
Crossing Und
nderground Service Rev: A0 Page No. 6 of 11
Excavvation Works.
Method Statement for
5.4 Foreman Underground
Services,Excavation,Ba
To ensure that all personnell are adequately trained for the relevant task k; that they are
using the correct equipmen ckfilling
nt and personal protective and Road th
equipment; hat all relevant
d; and that the respective Crossing
hazards have been identified permits to works.
work forrmalities have
been correctly addressed, where required. Must conduct a tool box tallk meeting with
his crews about the specifieed activities and related hazards and contro
rol measures to
prevent any kind of injury. Reesponsible for providing the required PPE to his crew for
the job as mentioned herein tthis procedure.
5.5 QA/QC Engineer
QA/QC Engineer shall be ressponsible for the implementation and contro ol of the quality
procedures as per the approvved ITP, approved project specification and drawings.
He shall ensure that all re equired inspections & tests are performe ed and are in
compliance with approved sspecifications. He shall review and ensure e that all shop
drawings and material subm mittals are presented to the COMPANY authorities
a with
adequate supporting docu uments. He shall control non-conforming products,
workmanship and implementting the required timely corrective actions. Ensure
E that the
required testing is undertake
en by approved independent laboratories.. Ensuring that
materials are inspected whenn delivered to site and it is complying with the
t COMPANY
approved specifications and d maintaining all relevant records of QA A/QC activities
related to lifting works.
5.6 HSE Supervisor / HSE Of
Officer
He shall be responsible ffor ensuring that all involved personnell are attended
COMPANY HSE induction a and following HSE regulations, safe work practices,
p safe
working environment and HIRA
IRA control measures.
He shall responsible to cond duct work site inspection to ensure that the e activities are
performing as per COMPAN ANY procedures, standards and regulatio ions. He shall
maintain all relevant valid doccuments related to the activity and involved equipments.
He shall lead HSE commun nication with workforce to encourage reporti ting of incidents
including near-miss incidentt, hazard identification, risk management and
a emergency
preparedness. He shall inve estigate and report all reportable acciden nts/incidents to
COMPANY authority and co ontractor management with recommendatition to improve
control measures for preventtion of the recurrence. He shall be the authoority to stop the
site activities due to an exxistence of unsafe condition. He shall ensure
e that all
personnel are attended HSE induction prior to the site assignment and strictly
following HSE regulations.
ABU DHABI GA
AS INDUSTRIES LIMITED
(GASCO)
NEW RUWAIS OFFICE BUILDINGS
Doc : 0500604
4-MS-00-CA-0014
PROJEC
ECT No. 0500604
Method Sttatement for Road
Crossing Und
nderground Service Rev: A0 Page No. 7 of 11
Excavvation Works.
6. HSE Requirements.
6.1 Permit to Work (PTW)
GASCO permit to work (PTW W) system shall be implemented to control the
t activities in
safe manner for the protectio
on of all personnel, assets and environment.
t.
Describe the nature of work,, involved tools and equipment, work locatio on details, start
date and time in the work permit. PICWS & Job performers shall be fully aware of
activities, regulations and th
he Permits shall be kept available at all times nearby the
work area.
6.2 Personal Protective Eq
quipments

The contractor shall provide


e personal protective equipments as require red for different
operations. All PPEs to be ussed by construction personnel shall be in goood quality and
condition.
6.3 Tool Box Talk (TBT)
ineer along with the Foreman and the Safe
Prior to start the task Engin ety officer shall
conduct toolbox. They have sk, safe activity
e to present in detail the task, potential ris
implementation and the prevventive control measures, PPE requirements, safe work
procedures, HSE regulation ns and conditions to prevent incident. All concerned
workers shall attend toolbox talk and the related records shall be maintaained.
6.4 Safe Work practices
Best operating practices shalll be used to assure the safety and integrity::

6.4.1 All activities shall be


e planned, supervised and carried out in a safe manner
under the control of a competent person, who knows the respon nsibilities.
6.4.2 Equipment operation
n and Transportation shall be carried out in safe manner
controlled by compe
etent banks man/flagman as per UAE Traffiic regulations
and COMPANY regu ulations.
6.4.3 All road movement e
equipments within site parameter shall be controlled
c by
competent banks man/flagman to ensure the speed control an nd Company
regulations.
6.4.4 Ensure always road is cleaned and maintained in good condition.
6.4.5 It is essential that allll personnel can communicate in same langu
uage.
6.4.6 Working area shall b
be maintained good housekeeping and prop
per access.
6.4.7 All equipment shall b
be suitable for the specified works
and approved by Gasco
Maintenance.
ABU DHABI GA
AS INDUSTRIES LIMITED
(GASCO)
NEW RUWAIS OFFICE BUILDINGS
Doc : 0500604
4-MS-00-CA-0014
PROJEC
ECT No. 0500604
Method Sttatement for Road
Crossing Und
nderground Service Rev: A0 Page No. 8 of 11
Excavvation Works.
7. Tools & Equipments
s Surveying instruments
safety cones,safety protective
Plant and Equipment
equipment.
`No. Description Qty
1 Asphalt cutter. (Girder disc 8’’by Dwelt) 1 no
2 Hand power tools (220 v) 2 nos.
n
3 Hand excavation too
ols 2 nos.
n
4 Hand Gloves 1set//Person
5 Hand shovel &wheel barrows 4 nos.
n
6 Hand operated breaker( 220 v. ) set/Pe
Person
7 Hand tools (non elec
ctric power) 1set//Person
8 Safety barrier As per site requirements.
r
9 Safety Helmets 1set//Person
10 Safety Shoes 1set//Person
11 Fire Extinguisher 1/Location

12. Jack Hammer


Materials
13. Compactor and roller
No. Descripti
tion Source MSD available
1. UPVC draina
age pipe COSMOPLAST co. YES
2. Polypropylene Ra
andom pipes COSMOPLAST co. YES
3. UPVC Duct for underrground service COSMOPLAST co. YES
4. GRE pipe for U..G. Service M/s TYCO co. YES
Carbon steel sc
chedule 40
5. Galvanized &redd painted for M/s TYCO co. YES
Above G. level

8. Methodology existing underground


8.1. Site Preparation.
services in the area
8.1.1 Survey work to locate a and identify the guideline of the area. The e CONTRACTOR
shall co-operate in presserving all control bench mark monuments ts and stakes,
and other markers esta ablishing lines, elevations, slopes, etc. Thee CONTRACTOR
shall replace at no coost to the COMPANY, monuments, stake es, and other
markers, which he distu
urbs or destroys during the course of his worrk.
Method Statement for
ABU DHABI GA
AS INDUSTRIES LIMITED Underground
(GASCO) Services,Excavation,Ba
NEW RUWAIS OFFICE BUILDINGS ckfilling and Road
Doc : Crossing
0500604 4-MS-00-CA-0014
works.
PROJEC
ECT No. 0500604
Method Sttatement for Road
Crossing Und
nderground Service Rev: A0 Page No. 9 of 11
Excavvation Works.
8.1.2 Ensure timely submissiion of “Inspection Notification,” other disciplline and HSE
clearance is obtained prrior to start the installation Work.

8.2 General Aspect

• Before beginning wo ork, the CONTRACTOR shall ascertain the natu


ure and location
of all existing above
e and underground services and facilities on site and in
adjacent areas by inspecting available plans or, if necess sary, by hand
excavation. The COMPANY will make available, for review, any existing layout
drawings which cove er the area of work.

• CONTRACTOR will be rresponsible for confirmation of any such info


formation given.
All construction and installation work shall be executed accordin ing to approved
design drawing, speccification and general practice for Duct pipe e work.

• Contractor shall take


e every precaution including providing tempo
orary supports,
and safety barriers tto protect the existing services and facilities
s from damage
or interference during construction.

• Prior to the commencement of all activities, necessary work permit


p shall be
obtained. Toolbox ta
talk, excavation permit along with relevantt drawings shall
be submitted in advaance.

• No material or equip
ipment shall be stored with in a distance of
o 1 meter from
the edge of the exca
avation.

• Road base and batc tch surface course materials installed underr previous work
shall be carefully exxcavated. These materials shall be replacedd in the backfill
process.

• Unsuitable /surplus materials


m are carted away to an approved d
dumping area.

• Reinstated the surfa


ace, ensuring that it is level with surrounding
g areas.

• Proper access shalll be maintained in the construction area.

• Remove all the exce ess materials and clean the surrounding arrea for GASCO
final inspection and a
approval.
ABU DHABI GA
AS INDUSTRIES LIMITED
(GASCO) Method Statement for
NEW RUWAIS OFFICE BUILDINGS Underground
Doc : 0500604 4-MS-00-CA-0014
Services,Excavation,Ba
PROJEC
ECT No. 0500604
ckfilling and Road
Method Sttatement for Road
Crossing works.
Crossing Und
nderground Service Rev: A0 Pa No. 10 of 11
Page
Excavvation Works.
8.3 Excavation of Trench for underground Duct service. manually
• Excavation work shall be performed according to common exc
cavation unless
otherwise specified.

• Before starting excavatition for cable Duct, fire hydrant and portable
e pipe duct- the
location and elevation sshall be verified and marked on the ground & inspected by
consultant, so that thee duct excavation for the pipeline can be e excavated to
correct location and elevvation.

• Make diversion plan ass permitted by GASCO HSE department,, and close the
road with proper barrica
ades, signboards and battery operated flash
hing light as per
GASCO HSE requireme ents.

• Mark the width of the rroad cutting portion as per the approved d
drawing, where
road cutting excavation to be performed.

• Ensure that the depth h and width of the road crossing trench is as per the
approved specified dimeension of proposed duct bank.

• Excavations for duct co onstruction shall conform to the locations and elevations
indicated on the consttruction drawings for power duct, fire hyd drant &portable
water line duct works. ExExcavation shall extend a sufficient distanc
ce from edge of
concrete walls to allow w for the placement and removal of co oncrete forms,
installation of undergrou
und services, and for inspection. (to be approved by
COMPANY)
• Excavations adjacent to existing foundations (where the bottom of o excavation is
lower than the bottom o
of foundation) shall be limited to a minimum distance by an
imaginary line drawn 30
0degree horizontally from the bottom cornerr of the existing
foundation to the botto
om corner of the intended excavation. If the excavation
needs to be closer than
n the minimum, adequate steps shall be ta aken to prevent
cave-in or weakening off the soil beneath the existing foundation.

• Asphalt portion shall be cutting by hand operated disc cutter ,this is only providing
small groove to the dep pth 50mm on the both side of excavation le engthwise, after
that the portion of e excavated area asphalt shall be remove by Hand jack
hammer/ hand breake er(220v. electrical hand tools).The remain ning portion of
compacted earth by pic ickaxes and hand shovel.
ABU DHABI GA
AS INDUSTRIES LIMITED
(GASCO)
Prepare bedding as per the approved specifications/ IFC drawings' details
NEW RUWAIS OFFICE BUILDINGS
Doc : 0500604
4-MS-00-CA-0014
PROJEC
ECT No. 0500604
Foundations
Method Sttatement for Road
backfilling shall be
Crossing Und
nderground Service Rev: A0 Pa No. 11 of 11
Page
addressed in a
Excavvation Works.
separate M/s
• Backfilling of foundatioions shall not be carried out until the foundations
f or
structures within the exxcavation have been cured and protected in accordance
with the Specification fo
or Concrete Construction.
Approved backfill materials to be used at site.
• All forms shall be remo oved and the excavation cleared of loose ssoil, water and
debris after approval off underground installations and just prior to backfilling.
b

• Bedding and backfill sshall be compacted by mechanical tamping wherever


possible. Hand-compaccted backfill shall be permitted only whe en mechanical
tamping is Impracticall as determined by the COMPANY. Ha and-compacted
bedding shall be place ed in loose lifts not exceeding 50 mm. Ha and-compacted
Install the protection tiles and the
backfill shall be placed in
i loose lifts not exceeding 100 mm.
indication tapes as per applicable
specifications/
• Machine-compacted backfill shall be placed in loose IFC
lifts not excee drawings
eding 200 mm.details
Machine compactors sh
hall be suitable to the type of soil to be comp
pacted.

• Upon completion, all de


ebris and surplus materials shall be disposed
d of, off Project
limits in a manner meetiting all local authority requirements.
Reinstate the area to the initial
conditions
• Remove all the excess materials and clean the surrounding area fo
or GASCO final
inspection and approvall.

9. Inspection and Testing


ng
• ITP for Excavation and
d Backfilling – 0500604-ITP-00-CA-001 Rev
v C0

• Check List for Excava


ation – 0500604#18(EXC-RE) Rev#1

• Check List for Backfilllling - 0500604#19(BF Form) Rev#1


Check list for Asphalt works.
10. Documentation
Inspection Notification Reco
ord shall be documented by the QC Engine
eer.
Indicate the documentation to be produced
11. Attachments. as part of this activity and the responsible
a) Excavation Checklist. party for the same
b) Backfilling Record Form..
Bedding checklist
ABU DHABI GAS INDUSTRIES LIMITED

NEW RUWAIS OFFICE BUILDING


PROJECT NO 0500604
BACKFILLING CHECK LIST

Location : Item :

Ref.Drawing No.: Report No. :

IN No. : Date :

Check
Check Items Date
Accept Reject

1) Materials for backfill are suitable and approved.

2) No boulders and rock fragment are included.

The thickness per loose layer is adequate (200 mm)


3)
before compaction.
Adequate water sprayed when compacting to mmet the
4)
required moisture content ±2 % of OMC
5) Samples for field density test were taken
as per specification.
* Dry density not less than 95% of MDD
*Moisture content ±2% of OMC
6) Test result of field density are above
required by specification and IFC drawings.

7) Recompose all faulted area and test.

8) Reinstate the complete area same as before.

Note :

ACTCO Engineer ACTCO QA/QC COMPANY/TPI


Name

Signature

Date

Rev#1 0500604#019 (BF Form) Page 1 of 1 11/11/2013


ABU DHABI GAS INDUSTRIES LIMITED

NEW RUWAIS OFFICE BUILDING


PROJECT NO 0500604
EXCAVATION RECORD

Project : Report No. :

Location : Item :

DWG No. : Subcon. :

Check
Sr. No Check Items Date
Accept Reject

1) The work site is cleared

2) All grasses and weeds including roots were stripped and removed.

Excavation is performed to the lines, grades and slopes as per


3)
drawings.

Slopes of all excavations were cut true and straight and loos stones
4)
and boulders were removed from the area.

Excavation is made below the elevation indicated on the IFC


5)
drawings.Working access areas are provided

Excavation is kept free of water at all times until complete of


6)
construction or backfilling.

7) Soil condition at the bottom of excavation

8) Reinstate the complete area as before.

9) Shoring Required (Yes/No); Installed (Yes/No)

Note :

ACTCO Engineer ACTCO QA/QC COMPANY/TPI


Name

Signature

Date

Rev#1 0500604#018 (EXC RE) 11/11/2013