Professional Documents
Culture Documents
ELECTRICAL
ENGINEERING
POWER
PRINCIPLES &
PRACTICES of
ENGINEERING
G ttC>
CD
OJD
03
CX
One-Line Diagram........................................................................................................... 37
One-Line Diagram............................................................................................................38
Fire Alarm Device Layout................................................................................................39
Fire Alarm Device Layout................................................................................................40
Light Source Selection Considering Elements Such as Type, Color, Life, Cost,
Efficiency and Application.......................................................................................41
Light Source Selection Considering Elements Such as Type, Color, Life, Cost,
Efficiency and Application...................................................................................... 42
Lighting Calculations (e.g. Lumen Method, Light at a Point).............. 43
Lighting Calculations (e.g. Lumen Method, Light at a Point).............. 44
Lighting Control................................................................................................................45
Lighting Control................................................................................................................46
Receptacle Layout.......................................................................................................... 47
Receptacle Layout.......................................................................................................... 48
Equipment and Component Selection............................................................................49
Equipment and Component Selection........................................................................... 50
Electrical Specifications.................................................................................................. 51
Communications Specifications..................................................................................... 53
*Check with your state’s Board of Engineering for exact deadline information
**tentative date, verify actual date with NCEES
CO
0)
bJO
03
Oh
INTRODUCTION
The Electrical Engineering PE Exam is administered twice annually in April and in
October. By following the advice in this manual and preparing your test day materials in
a systematic manner (i.e. not taking every resource you can find into the test) you will
be in a good position to perform well on the exam. Remember, you only have
approximately 6 minutes per question. This is not enough time to read the question,
determine what information you need to solve the problem, find the information, solve
the problem, mark your answer and move on. Some questions will be automatic and
will be answered in a minute or less. Some will require much more time than 6 minutes.
You do not have time to locate, search, read and evaluate an exhaustive “library” of
information so take the time to put together a succinct reference system ... it will serve
you well.
I wish you the best in your career and hope that you find this study guide invaluable in
preparing for your licensure examination. But additionally, that you find yourself referring
to the information contained herein throughout your career.
Sincerely,
Jeff Setzer, PE
Kansas State University
1988
NOTE
Reading and studying one manual prior to taking the Electrical
Engineering PE Exam (or any other test) is not a substitute for
actual, in-depth preparation and study.
o
yH
O)
bJO
03
CU
On the day of my Principles & Practice exam, I sat in amazement and witnessed
hundreds of people transporting what appeared to be their entire educational history
into the testing room. Literally, I saw people with hand-trucks wheeling in bookshelves
- actual bookshelves - loaded with textbooks, three-ring binders, and other assorted
reference materials. They then proceeded to “set up shop” around their table;
attempting to organize their stuff into an accessible library.
Wow!
If nothing else, it was an amusing sight to see
and it eased my test-day anxiety
As you know, there are 40 questions in the morning and 40 questions in the afternoon.
Once the direction to begin is given, you have +/- 6 minutes per question to:
(1) read the question
(2) decide what resource(s) to use (unless you already know the answer)
(3) find that resource
(4) find the information in that resource
(5) solve the problem
(6) choose the correct answer (remember, it’s multiple choice and a good deal of the
questions are structured to “find the answer closest to the following answers”)
(7) mark the answer sheet.
I worked at a comfortable, steady pace and finished with enough time to back-check
some of my answers and make sure I had all the answer bubbles filled in on the test
sheet. I did not have time to search through a multitude of textbooks, notebooks, etc. to
find an answer.
And most importantly, a copy of this study guide with each section tabbed for
______________________easy retrieval of information.______________________
ELECTRICAL SYSTEMS
The Electrical Engineering PE Exam deals extensively with topics from the National
Electrical Code - NEC (NFPA 70). Those taking the examination should be thoroughly
familiar with the NEC and especially those sections covering building construction,
occupant safety, and general design.
It would also be convenient and will help with time efficiency to have the different
articles related to these topics tabbed and be somewhat familiar with the information in
each to minimize the amount of time in searching for the correct reference.
Additionally, resources related to:
• Fault current calculations
• Power Factor Correction
• Short Circuit Analysis
• Transformers
• Voltage Drop Calculations
• Lighting Design and Control
• NFPA 72 - The National Fire Alarm and Signaling Code
These resources will be extremely beneficial to your success.
Solution:
25 KVA transformer x 2.5% heat to space = 0.625 KVA = 625 VA = 625 watts
4 625 watts x 3.413 BTU/watt = 2,133 BTUh = 0.18 tons
150 KVA transformer x 2.5% heat to space = 3.75 KVA = 3720 VA = 3750 watts
3750 watts x 3.413 BTU/watt = 12,799 BTUh = 1.07 tons
500 KVA transformer x 1.8% heat to space = 9.0 KVA = 9000 VA = 9000 watts
9000 watts x 3.413 BTU/watt = 30,717 BTUh = 2.56 tons
Total additional load due to transformers = 0.18 + 1.07 + 2.56 = 3.81 tons
Solution is “a”
a. I, II & III
b. I, III & IV
c. I only
d. I, II, III & IV
Solution:
Refer to section 403.10 - Standby Power, of the International Building Code
Solution is “a”
LO
<D
bJD
03
Oh
Solution:
Refer to section 403.12.1 - Stairway communications system, of the International
Building Code
Solution is “b”
VO
rH
0)
bJQ
03
CL,
Solution:
1. The annual cost of operating the current motor:
20 hp x 0.735 kW/hp = 14.7 kW
14.7 kW x 84 hrs/wk x 52 wks/yr x $0.0725 kW-h = $4,655.20/yr
2. The annual cost of operating the new motor:
15 hp x 0.735 kW/hp = 11.03 kW
11.03 kW x 84 hrs/wk x 52 wks/yr x $0.0725 kW-h = $3,491.40/yr
3. The annual savings would be:
$4,655.20 - $3,491.40 = $1,163.80/yr
Solution is “c”
rH
CD
bl
05
CU
Solution:
1. Old pump operating for 3 years:
$4,655.20/yr x 3 yrs = $13,965.60
2. New pump installation and operating for 3 years:
$4,500 + $3,491.40/yr x 3 yrs = $14,974.20
3. The difference (i.e. maintenance costs) would be:
($14,974.20 - $13,965.60) /3 = $336.20/yr or less
Solution is “d”
a. I
b. Ill
c. I and III
d. II and IV
Solution:
The International Building Code defines Public Way as “A street, alley, or other
parcel of land open to the outside air leading to a street, that has been deeded,
dedicated, or otherwise permanently appropriated to the public ...”
In this example, a public street and an alley maintained by the city would be
considered public ways.
The walkway adjacent to the front door and the privately-owned vacant lot are on
private property and therefore, have not been “deeded, dedicated, or otherwise
permanently appropriated to the public.”
a. II only
b. Ill only
c. II & III
d. I, II, & III
Solution:
Refer to NFPA 99, A.4.4.2.2.1 - Type 1 essential electrical systems are comprised
o f ... the Emergency System and the Equipment System
1. Equipment System
2. Life Safety Branch
3. Critical Branch
Solution is “d”
O
CN
CD
b JO
03
Ph
Solution:
Article 517.30 describes the Essential Electrical System for hospitals. This article
also indicates that in hospitals with a maximum demand on the Essential Electrical
System of more than 150kVA, each branch of the system requires its own transfer
switch. The Life Safety Branch and the Critical Branch make up the Emergency
Branch, therefore, two transfer switches are required.
Solution is “b”
Solution:
Solution is “b”
P ageZ Z
a. 230,288,80%
b. 288,230,80%
c. 230,288,51.3%
d. 288,230,51.3%
Solution:
Z= V(resistance)2 + (inductive reactance)2
= V(40)2 + (30)2 = 50 ohms
Total Current = (120 volts) Z = 120 -f 50 = 2.4 amps
Apparent Power:
(120 volts)2 t Z = (1 20)2 -t- 50 = 288 volt-amps
True Power:
(total current)2 x resistance = (2.4)2 x 40 ohms = 230.4 watts
Power Factor:
True Power Apparent Power = 230.4 * 288 = 0.8 = 80%
CO
CM
QJ
Solution is “b
Solution:
(1 ) If la = (kVA x 1000) E L-L
-T-
Solution is “c”
ln
CN
<D
b JC
as
Ph
Solution:
(1) Ifla = (kVA x 1000) - (V3 x EL-L)
= (500kVA x 1000) - (V3 x 480) = 601,4A
(2) Multiplier = 100 - Z = 100 - 5.0 = 20.0
(3) Isc = I f l a x m ultiplier
= 601.4x20.0 = 12,028A
(4) f = V 3 x L x l = V3x 100 x 12,028 = 0.0651
C x n* x EL-n 16,673 x 4 x 480
(5) M = 1 -r (1 + f) = 1 -r (1 + 0.0651) = 0.9389
(6) Isc symRMS = Isc X M
= 12,028 x 0.9389 = 11,293A
*n = n u m b e r of co n d u cto rs
Solution is “b”
Grounding Principles
Which of the following are acceptable as electrodes permitted for grounding:
I. Metal underground water pipe in direct contact with the earth for 9 feet.
II. The metal frame of the building with one structural metal member that is in
direct contact with the earth for 12 feet.
III. A #2AWG bare copper conductor ground ring encircling the building.
IV. An 8 foot long, 1” diameter, stainless steel ground rod driven into the earth.
a. I only
b. I and II
c. II, III and IV
d. IV only
Solution:
Refer to NEC Article 250.52 - Grounding Electrodes
Solution is “c”
CNI
CD
bJD
03
Oh
Grounding Principles
The National Electrical Code, Article 250 - Grounding and Bonding - covers
requirements for supplemental grounding electrodes. When is a supplemental
grounding electrode not required?
a. If the resistance to earth is 25 ohms or less
b. If the resistance to earth is 10 ohms or less
c. If the primary ground is the same size as theservice entry conductor
d. If the building has two or more ground connections tothe water service piping.
Solution:
Refer to NEC Article 250.53(2) for exceptions for supplemental grounding.
Solution is “a”
PageZo
Solution:
Refer to NEC Article 240.5(B)(2)
Solution is “b”
29
Page
Solution:
(1) As per NEC Article 430.32(A)(1):
Overload device: 28.5A x 125% = 35.625A
(2) As per NEC Article 430.52(C)(1):
Short-circuit and ground-fault protection =
28.5A x 250% = 71.25A
4 must use an 80 amp fuse
Solution is “b”
O
cn
CD
bJC
03
PU
Solution:
NEC Article 430.24 - Several Motors or a Motor(s) and Other Load(s) indicates
that “conductors supplying several motors, or a motor(s) and other load(s), shall
have an ampacity not less than 125 percent of the full-load current rating of the
highest rated motor plus the sum of the full-load current ratings of all the other
motors in the group.
Solution is “d”
Solution:
NEC Article 220.86 - Schools - outlines the following optional method for sizing of
feeders and service conductors for schools.
For the first 3VA/ft2.................................... 100%
Over 3VA/ through 20VA/ft2..........................75%
Over 20VA/ft2.................................................25%
Solution is “b”
CN
CO
b3£
0
Oh
Solution:
Secondary line voltage = (2400volts * 20:1) x V3 = 208 volts
Solution is “b”
CO
CO
b£
03
CX
Solution:
Refer to NEC Article 220.82(C) - Heating and Air-Conditioning Load
Solution is “d”
CO
CD
bJD
05
CX
Solution:
NEC Article 210.19(A)(1) - informational note 4 indicates the acceptable voltage
drop for branch circuits is 3%. In this example, 480v x 3% = 14.4V
NEC Chapter 9, Table 9 indicates the ohms to neutral per 1000 ft = 1.1 ohms
Voltage drop = (V3 x L x ohms x amps)
1000
Solution is “c”
LO
CO
CD
toJO
O5
Oh
Solution:
NEC Article 210.19(A)(1) - informational note 4 indicates the acceptable voltage
drop for branch circuits is 3%. In this example, 480v x 3% = 14.4V
NEC Chapter 9, Table 9 indicates the ohms to neutral per 1000 ft = 0.45 ohms
Voltage drop = (V3 x L x ohms x amps)
1000
Solution is “c”
vO
OO
CD
tuo
03
PL,
One-Line Diagram
The one-line diagram is a graphical representation of the electrical distribution
throughout the project. It generally starts at the main electrical service entrance,
shows routing, wire sizes, number of conductors, etc. to the main distribution
panels and transformers, then out to the distribution panels and finally to the
individual load panels.
If there is an emergency generator involved in the project, this also will be shown
on the one-line diagram along with transfer switch(es), emergency panels, etc.
The one-line diagram does not usually show distribution beyond the individual load
panels. This distribution configuration would be shown on the detailed floor plans.
One-Line Diagram
In a one-line diagram, which of the following typically represents a transformer?
a. T
b. A
Solution:
Solution is “c”
Solution:
The International Building Code section 907 - Fire Alarm and Detection Systems
outlines the requirements for Fire Alarm System submittals
Solution is “d”
Page 3 9
Solution:
The International Building Code section 907.2.13.1.2 - Duct Smoke Detection
dictates that Duct Smoke Detectors shall be located in the main return air and
exhaust air plenum of each air-conditioning system having a capacity greater than
2,000 CFM
Solution is “a”
P age40
Illuminance = the total luminous flux incident on a surface, per unit area. It is a
measure of how much the incident light illuminates the surface,
wavelength-weighted by the luminosity function to correlate with
human brightness perception.
Luminous emittance = the luminous flux per unit area emitted from a surface.
Luminous emittance is also known as Luminous exitance
Luminous Flux = the measure of the perceived power of light. It differs from
radiant flux, the measure of the total power of light emitted, in
that luminous flux is adjusted to reflect the varying sensitivity of
the human eye to different wavelengths of light. Also known as
Luminous power.
A 25 ft. x 20 ft. conference room is to have new fixtures installed. If the light output
per fixture is 3,000 lumens and the required illumination is 100 footcandles, how
many fixtures are required?
a. 24 fixtures
b. 28 fixtures
c. 36 fixtures
d. 42 fixtures
Solution:
Required Light Output/Fixture (lumens) =
(maintained illumination in footcandles x Area in sq. ft.)
(# of fixtures x CU x BF x LLF)
Solution is “c”
Solution:
The Room Cavity Ratio equation is:
RCR = [5 x H x (L + W)] t ( L x W)
Where: H = room height; L = room length; W = room width
Solution is “b”
P age43
Solution:
Once the RCR is calculated for a particular room, the designer can cross reference
it to manufacturer’s Coefficient of Utilization tables to select an appropriate fixture.
Solution is “c”
Lighting Control
Lighting controls range from very sophisticated Architectural type controls to simple
wall toggle switches and depend on the type of space, the activity within the space,
and the project budget or owner’s preference.
Lighting design and control has evolved into its own branch of engineering and
would require a great deal of explanation and demonstration to thoroughly cover
the topic. The exam cannot get into that much detail.
But, to prepare for the types of questions that may appear on the exam, it is
recommended that you visit several of the larger manufacturers (ex. Leviton,
Crestron, Lutron, etc.) websites to get an overall understanding of the different
types of controls, the terminology associated with lighting control, and where each
type of control is mostly utilized.
Lighting Control
Which of the following can be used to control lighting in a building?
Two-pole switch
A Rheostat
III. A computer
IV. Motion Detector
a.
b. I & III
c. , III, & IV
d. , II, III & IV
Solution:
A two-pole switch is a typical wall toggle switch similar to those found in houses to
turn lights on and off.
A rheostat is a dimmer switch.
Computers are typically utilized in sophisticated, high-end control systems that
require precise, preset “scenes.”
Motion-detectors or occupancy sensors are mostly used in office buildings and
other facilities as an energy savings measure to turn lights on when someone
enters and space and turn lights off after a preset time period when no motion is
detected.
Solution is “d”
CD
(DJO
o3
Oh
Receptacle Layout
New roof-mounted air handling units are to be installed on the roof of an existing
office building. The building does not have electrical outlets currently installed on
the roof so these will need to be added to the scope of the project. According to
the NEC, how close to the new equipment does a new receptacle need to be
located?
a. 25 feet
b. 50 feet
c. 10 feet
d. 2 feet
Solution:
NEC Article 210.63 - Heating, Air-Conditioning, and Refrigeration Equipment
Outlet indicates that “a 125-volt, single-phase, 15-, or 20 -ampere-rated receptacle
outlet shall be installed at an accessible location for the servicing of heating, air-
conditioning, and refrigeration equipment. The receptacle shall be located on the
same level and within 7.5 m (25 ft.) of the heating, air-conditioning, and
refrigeration equipment. The receptacle outlet shall not be connected to the load
side of the equipment disconnecting means.”
Solution is “a”
Receptacle Layout
As per the NEC, what is the maximum distance between receptacles measured
horizontally along the floor line of any wall in a dwelling unit?
a. 6 ft.
b. 8 ft.
c. 10 ft.
d. 12 ft.
Solution:
NEC Article 210.52(A)(1) indicates “receptacles shall be installed such that no
point measured horizontally along the floor line of any wall space is more than 6 ft.
from a receptacle outlet.
( <f:>
6 ft 6 ft
maximum maximum
1J2 ft
Solution is “d”
P age48
Solution:
Transformer = 400 amp x (240 volt * 1000) x V3 = 166.1 KVA 225 KVA
Solution is “c”
P age49
Solution:
Refer to NEC Article 110.26(C)(2) - Entrance to and egress from Working Space -
Large Equipment
Solution is “a”
O
LO
0
bJ)Q
05
Oh
Electrical Specifications
The following MasterSpec® sections should be reviewed and studied to become
familiar with ductwork, piping materials and insulation. If possible, a copy of these
sections could be included in the Resources for Test Day.
DIVISION 26 - ELECTRICAL
26 0519 LOW-VOLT AGE ELECTRICAL POWER CONDUCTORS AND
CABLES
Building wires, cables, connectors, splices, and terminations rated
600 V and less.
26 2413 SWITCHBOARDS
Service and distribution switchboards, 600 V and less.
26 2416 PANELBOARDS
Distribution, branch circuit, and surge-suppression panel boards
and load centers.
LO
<D
b JD
cc
cl.
Communications Specifications
The following MasterSpec® sections should be reviewed and studied to become
familiar with ductwork, piping materials and insulation. If possible, a copy of these
sections could be included in the Resources for Test Day.
DIVISION 28 - COMMUNICATIONS
28 0513 CONDUCTORS AND CABLES FOR ELECTRONIC SAFETY AND
SECURITY
UTP, fiber-optic, coaxial, RS-232, and RS-485 cables, connecting
hardware, and identification systems.
CO
LO
CD
bJO
Cd
CU
Lighting
Required Light Output/Fixture (lumens) =
(maintained illumination in footcandles x Area in sq. ft.)
(# of fixtures x CU x BF x LLF)
LO
LO
CD
bJD
03
Ph
Power
To find: 1 phase 3 phase
HP x 746 HP x 746
Amps
E x Eff x PF V3 x E x Eff x PF
KW x 1000 KW x 1 000
Amps
E x PF E x PF
kVAx 1000 kVA x 1000
Amps
E E
IxExPF IxExPF
Kilowatts
1000 1000
Ix E Ix E
Kilovolt - Amps
1000 1000
Horsepower I x E x Eff x PF I x E x Eff x PF
(output) 746 746
746 x HP 746 x HP
Efficiency
E x I x PF V3 x E x I x PF
Input Watts Input Watts
Power Factor / _
VxI V3 x E x I
VO
LD
CD
W
05)
cu
RESOURCES
ARCOM 4 Masterspec®...................................................................www.masterspec.com
00
LO
CL)
b£
03
P h
O
'sO
a>
cd
CU
rH
VO
CD
bJD
CC
cu
vO
vO
0 )
bJO
03
Oh
You can find additional resources and study material along with design,
project management and construction management resources on his
website:
www.engineeringdesignresources.com
Page / 3
CL)
b JC
cd
CL,
^ e n g in e e rin g
F")e5lgn
K e50urces
r rigi n e c ri n g|~)es ign e so u rce s .co rn
ip nfijmeering
■ R eso urces
S e tu r Mem