You are on page 1of 1

DUQM Refinery Project

EPC Package 1 Process Units


Contract No.: CNT – 11100-1000-006

LMRA - DAILY TOOLBOX TALK MEETING ATTENDANCE SHEET


PLACE PTW
UNIT-340 COMPANY: ELECO
: #
CONDUCTED
DATE: / / 2022
BY:
E&I CABLE ARRANGEMENT, PULLING, DRESSING, CABLE TRAY
TBT TOPIC
,TUBING
INSTALLATION

HOT WORKS SPARKS, PINCH POINT, HAND / EYE INJURY WHILE


POTENTIAL RISK
GRINDER USING.

CONTROL TOOLS INSPECTED , HOUSEKEPING , FIRE EXTINGUISHER , FIRE BLANKET ,


MEASURES PPE

S
NAME POSITION PROJECT ID SIGNATURE
N

1 M ZAHID INSPECTOR 110233

2 M ALI HUSSAIN ELECTRICIAN 127545

3 AMIRUL ISLAM HELPER 127550

9
1
0
1
1
1
2
1
3
1
4
1
5

Last Minute Risk Assessment (LMRA) is an easy to use (paperless) continuous risk assessment system that should be performed 24/7 by all workers and during Tool box
talks with the help of the Job Safety Analysis in the beginning of a new task and start of shift. Three steps before work starts: - Assess the risk: What’s the worst that can
happen? - Analyze: How can I reduce the risks? - Act: Start work implementing the safe preventive measures as established in the JSA, PTW and procedures
DRP001-PUC-PRO-Z-000-010/6. PAGE 1 OF 1