Professional Documents
Culture Documents
: P-T3109-EI034
SCP - JO PROCEDURE FOR INSTALLATION
LINIER HEAT DETECTOR 1 of 7
SCP - JO INDRAMAYU SPP PROJECT DOC. No:
P-T3109-EI034
PROCEDURE FOR INSTALLATION Rev. No : 00
LINIER HEAT DETECTOR 2 of 7
PROCEDURE INSTALLATION
FOR
LINIER HEAT DETECTOR
DOCUMENT NO : P-T3109-EI034
- SDCC : Original
- CNEEC : Copy
- All Dept. : Copy
TABLE OF CONTENT
NO DESCRIPTION PAGES
1 PURPOSE 3
2 REFERENCE DOCUMENT 3
3 INSTRUMENT TO BE USED 3
4 SAFETY PRECAUTION 3
5 PREPARATION TO INSTALL 3
6 PROCESS OF INSTALLATION 4
7. ATTACHMENT 6
Attachment HSE Aspects Identification, Risk Assessment
7
and Risk Control
SCP - JO INDRAMAYU SPP PROJECT DOC. No:
P-T3109-EI034
PROCEDURE FOR INSTALLATION Rev. No : 00
LINIER HEAT DETECTOR 4 of 7
1. PURPOSE
This is to assure that the requirements of installation for linier heat detector
are meets the codes requirements and contract specifications. This
procedure is to describe the minimum requirements for installation for linier
heat detector which is of prime importance for the personnel safety and fire
fighting system availability. To make sure, the works are carried out in
acceptable workmanship and follow the requirements in the quality manual.
2. REFERENCE DOCUMENT
3. INSTRUMENT TO BE USED
4. SAFETY PRECAUTION
o This detector is not fragile but crushing or pinching will injure it therefore
DO NOT over tighten the fasteners as this may breach the outer jacket or
crush the inner insulation, causing “false alarm”. All fasteners must allow
the wire to expand and contract with temperature.
o DO NOT leave the detector on the floor and walk on it or set ladders on it
during installation, it may cause “false alarm”.
o Comply with all safety requirements described in instrument equipments
manual
o Worker should be used PPE (safety gloves)
5. PREPARATION TO INSTALLATION
o Ensure that the cables are rated for 30 VaC, 42 VdC. Resistance is
approximately one ohm per five feet (1.5m) of twisted pair (two
conductors)
SCP - JO INDRAMAYU SPP PROJECT DOC. No:
P-T3109-EI034
PROCEDURE FOR INSTALLATION Rev. No : 00
LINIER HEAT DETECTOR 5 of 7
6. PROCESS OF INSTALLATION
6.3 Each end of the Proptectowire portion of every initiating circuit shall
terminate in an approved zone box, end-of-line zone box, or other
junction box provided as part of the system.
6.5 All electrical connections made within each zone box between
Protectowire and the circuit’s interconnecting copper wiring or end-of-
line device, shall be made via terminals.
6.6.1 The common cable is adopted from the module box to outside
protection area.
6.6.2 The junction box and the end resistor box ouside the room
must adopt waterproof mode
6.6.3 The linier heat cables should not be cut off in a protection area
if it must be cut off, the joint should be connected with
terminal, and the terminal box, there should be clear mark.
6.6.4 When installing the linier heat cable, the winding angle should
not be too sharp. And the cable should not be stepped on or
weighed down by heavy things. For protecting from damaging
SCP - JO INDRAMAYU SPP PROJECT DOC. No:
P-T3109-EI034
PROCEDURE FOR INSTALLATION Rev. No : 00
LINIER HEAT DETECTOR 6 of 7
6.6.6 When installing the linier heat cable in protected area of water
distinguish system, install the cable under the fire extinction
pipe net, and the distance where the steel-wire fixed is
100~150mm, and then fixed the linier heat cable with the
plastic clip. The JB should be waterproof (Figure 2).
SCP - JO INDRAMAYU SPP PROJECT DOC. No:
P-T3109-EI034
PROCEDURE FOR INSTALLATION Rev. No : 00
LINIER HEAT DETECTOR 7 of 7
7. ATTACHMENT