PT Delta Reka Invensi provided lubrication services for a shutdown at PT Riau Andalan Pulp and Paper's plant in Pekanbaru, Riau. The services included 53 normal hours and 107 overtime hours of work by millwrights. The total cost was Rp4,135,284 with normal hourly rates of Rp29,101 and overtime rates of Rp24,233 per hour.
PT Delta Reka Invensi provided lubrication services for a shutdown at PT Riau Andalan Pulp and Paper's plant in Pekanbaru, Riau. The services included 53 normal hours and 107 overtime hours of work by millwrights. The total cost was Rp4,135,284 with normal hourly rates of Rp29,101 and overtime rates of Rp24,233 per hour.
PT Delta Reka Invensi provided lubrication services for a shutdown at PT Riau Andalan Pulp and Paper's plant in Pekanbaru, Riau. The services included 53 normal hours and 107 overtime hours of work by millwrights. The total cost was Rp4,135,284 with normal hourly rates of Rp29,101 and overtime rates of Rp24,233 per hour.
Office : Jalan Mulya Sari I No 2, Tangkerang Selatan, Pekanbaru, Riau
Client : PT Riau Andalan Pulp and Paper Job : Shutdown Lubrication Area Job : Lubrikasi
Summary Progress
Time Quantity Unit Rate Total Price
No Classification Total Amount Normal (/Hours) Overtime (/Hours) Normal (/Hours) Overtime (/Hours) Normal Overtime A Manpower 1 Mill Wright 53 107 29.101 24.233 1.542.353 2.592.931 4.135.284 GRAND TOTAL 4.135.284