PT FARRALD TEKNINDO

CLUSTER IV PGE GAS FIELD


SITE PT PEMA GLOBAL ENERGI
ACEH UTARA

2023 2024
Estimate Actual
No Descriptions Activity
Days Day November December January
Week 3 Week 4 Week 1 Week 2 Week 3 Week 4 Week 1 Week 2 Week 3 Week 4
A. Kick Of Meeting 1
Inspection 3 unit Panel Distribution & 2 unit Power
B.
Transformer
1 Document Review Review 1

2 FAT Verify 1

3 Site Inspection & Verification Verify 3


4 Final Verify & Witness by Inspektur Migas (If Needed) Witness 2

5 Reporting Provide 14

6 Issued COI Provide 14


PLANNING DAYS
JUMLAH
ACTUAL DAYS

Acknowledged By : Prepared By :
PT Pema Global Energi PT Farrald Teknindo

Tengku Nizarul Aslami Mulyadin


Manager Teknik & Operasi