Professional Documents
Culture Documents
E 3.1 -Consider a power system with two generating stations. The incremental production
cost characteristics for the two stations are
of
_I = (27.5 + 0.15P I )Rs / MwHr
oPI
of
_2 = (19.5 + 0.26P 2 )Rs / MwHr
OP2
Given that the minimum and maximum powers are 10 MW and 100 MW -at each plant
schedule the generation at each plant to supply a system load given by the load curve
shown in figure.
200 -------------,.---,
150
1 125
100
- - - - - - - - - -
----...---~
-r----l
I
I
I I
I I
50 t----+----r------
L -+---,
I I
o~-----~----~--~----~~--~
C Time (t) ----+ 12
6
12 a.rn 12 3 6 10 Mid
Mid night noon p.rn p.rn p.rn night
oFI = oF2 =A
OPI OP 2
27.5 + 0.15 PI == 19.5 + 0.26 P2
27.5 + 0.15 (50 - P2)== 19.5 + 0.26 P2
27.5 - 19.5 + 7.50 == 0.26 P2 + 0.15P 2
15.5 == 0.41P2; P2 == 37.8
PI = 50 - 37.8 = 12.2 MW
Economic Operation of Power Systems 109
Case PI P2 PD A.
Case (i) 12.2 37.8 50 29.33
EJ.2 The fuel input characteristics for two thermal plants are given by
1(0)
OutputMW Heat rate x 106 at plant 1 K-caVMW-h Heat rate x 106 at plant 2 K-caVMW-hr
10 1625 18.4
~ 12.48 12.8
30 11.39 11.2
40 10.96 10.6
50 10.80 10.4
ro 10.77 10.4 '
'Xl 10.82 10.,5
ro 10.92 10.7
~ II.OS" 10.93
100 112 11.2
112 Operation and Control in Power Systems
6 100 Rs
= (8 + 0.048 PI) 10 x -- 6 - -
4x 10 MwHr
= (2 + 0.012 PI) x 100 = (200 + 1.2 PI) Rs/MWHr
At 100 MW generation, the cost is
(200 + 12) = 212 Rs/MWHr
The incremental production cost is obtained by adding the maintanance costs
of 10%
Hence, the incremental production cost at plant 1
::: (200 + 1.2 PI) 1.I = (220 + 1.32 PI)
Economic Operation of Power Systems 113
E 3.3 For the plants in example E3.2 obtain the economic generation schedule. The load
curve is given in Fig. (E3 .3)
200
i ISO
100
SO -------
I I 1
12 6 12 6 12
a.m noon p.m
Time (t) - - - .
Solution:
For economic schedule
2
200MW 75 MW
Line
N~~----------------------~~N
Fig. E 3.4
o
It is observed that when a power of 75MW is imported to bus I, the loss amounted to
5MW. Find the generation needed from each plant and also the power received by the
oload, if the system A. is given by Rs.20/MWHr. The incremental fuel cost at the two
plants are given by 0
o
dC I (PI) = 0.03PI + 15Rs I Mwh
odPI
Solution:
The load is at bus I. Hence, P, will not have any effect on the line losses
Therefore B I , = B'2 =; B 2 , =0
PL = B22 pi
5 = B22 75 2
(i)
At station 2
Solution:
The cost of generation at Plant 1
dC,(P,) I
C2 = I dP - .dP2 = (32.5 + 0.4P 2 )dP 2
2
= (0.4 Pi + 32.5P2 + y) Rs/Hr.
x and yare constants of integration which need not be evaluated.
For equal distribution of generation
P t = 150MW and P2 = 150MW
The increase in cost at plant 1 by generating 175MW instead of 150MW is
1 __
2
b -2B I2 PI 1-~~-2(-0.0005)PI 0.4+0.00IP
P2 = _--'' '-0..-___ == == 2
B l1 P12 + 2B 12 P1 P2 + B22 Pi
= (0.001) x (41.7)2 + 2 (-0.0005) (41.7) (50.2)
+ (0.0024).(50.2)2 = 5.7MW
2
Total generation = PT = LP =41.7 + 50.2 =919Mw
2
i=l
Total power received
PR = PT - PL = 91.9 - 5.7 = 86.2MW.
Power
Tail
_-.::- ...race
'-- ............
Fig. 3.13 Cascaded hydro electric plants
120 Operation and Control in Power Systems
r-----~~-r----------70--------~ P
12 I------rl;=rl
Power
am
12
Load Curve
Power
p.rn supplied
·12
Let ee be the energy spent to pump water to the reservoir. By releasing this water at
peak load times the energy supplied to the load is es' The ratio (eglee) is usually of the order
60-70%. Pumped storage plants are to be operated in such a manner that due to the p~ load
chipping on the load curve, the saving in fuel cost thus achieved should exceed the pumping of
water charges.
may be more than thermal generation in some other cases it may be the other way. The
operating cost of thermal plants is high even though their capital cost is low. In case of hydro
electric plants, the running costs are very low, but the capital cost is high as construction of
dams, canals, penstocks, surge tanks and other elements of development are involved in addition
to the power house. The hydro plants can be started easily and can be assigned load in very
short time. This is not so in case of thermal plants, as it requires several hours to bring the
boiler, super heater, and turbine system ready to take the load allotment. For the reason
mentioned, the hydro plants can handle fast changing loads effectively. The thermal plants in
contrast are slow in response. For this reason, the thermal plants are more suitable to operate
as base load plants, leaving hydro plants to operate as peak load plants.
However, the exact mode of operation depends upon the type of the development, and
factors such as storage and pondage, and the amount of water that is available is the most
important consideration. A plant may be run - off river, run - off river with pondage, storage
or pumped storage type.
Whatever, may be the type of plant, it is necessary to utilize the total quantity of water
available in hydro development so that maximum economy is achieved. The economic scheduling
in the integrated operation is however, made difficult as water release policy for power is
subject to a variety of constraints. There are multiple water usages which are to be satisfied.
Determination of the so called pseudo - fuel cost or cost for water usage for use in conjunction
with incremental water rate characteristic is a formidable exercise. Nevertheless, hydro thermal
economic scheduling is possible with assumptions made wherever necessary.
In systems where there is close balance between hydro and thermal generation and in
systems where the hydro capacity is only a fraction of the total capacity, it is generally desired
to schedule generation such that thermal generating costs are minimized.
K
Hydro energy to be utilized = LPHk n K ..... (3.78)
k=l
..... (3.79)
Let the thermal plant be operated for time period less than Tmax and for number of
intervals Ks
dF(PSk )
(i.e.) -.:-=:.;.. =A for k = 1,2, ...... , Ks ..... (3.85)
dP Sk
Economic Operation of Power Systems 123
Eqn. (3.85) indicates that the steam plant must be run at constant incremental production
cost for the entire time period of its operation. Denoting this value as P~k' the schedule is
depicted in Fig. (3.15) graphically.
o
k >1
Fig. 3.15 Hydro thermal co-ordination
FT = !F(p~)nk
k=l
..... (3.88)
Further
..... (3.89)
E
T =_s
Hence, ..... (3.90)
s P~
124 Operation and Control in Power Systems
...... (3.92)
..... (3.93)
The steam unit is operated at its maximum efficiency through out the time period Ts'
This can be proved as follows:
Let fc be the fuel cost.
F(P s) = a pi + bPs + c
=fcH(Ps) ..... (3.94)
where function H denotes the heat value
The heat rate is then given by
H(Ps )
Ps
= ~[aPi + bPs +
fc Ps
c] ..... (3.95)
..... (3.96)
P =
s k-=Pso
a ..... (3.97)
Economic Operation 0/ Power Systems 125
Hydro
POWER
SYSTEM Power demand
Steam
Let the combined operation be over a period of time T. Let this time period be divided
into intervals 1, 2, ..... J to suit the load curve so that
J
Ln J =T ..... (3.98)
J=1
The total volume of water available for discharge over this time period.
. .... (3.99)
Where Wj is the water rate for interval j. The fuel cost required to be minimized over
the time period T is given as
J
FT =Lnl(Ps) ..... (3.100)
j=l
The loads are assumed to remain constant during time intervals considered. The total
value of water at the beginning and at the vend of the interval T, in the reservoir are Wi and Wf
respectively.
During this period of scheduling the head of water is assumed to remain constant.
The input - output characteristic for the equivalent hydro plant is given by
w = w(PH) •...• (3.102)
126 Operation and Control in Power Systems
The Lagrange function for minimization of eqn. (3.100) subject to the constraints (3.99)
and (3.101) is \
solution to above two equations gives the economic generations at steam and hydro plants over
any time interval. The incremental production cost at the steam plants must be the same as
incremental production cost at the hydro plants. For simplicity nk may be taken one unit.
So that
dFs =A
dPs
dw
and y.-=A ... :.(3.106)
dPH
..... (3.108)
Economic Operation 0/ Power Systems 127
dWk aPLk
and ynk --(PHk)+Yk - - = A.k
dPHk aPHk
since k is chosen arbitrarily, and by considering the time period nk = 1
The equations reduce to
dw(PHk ) aPL
and Y dP +A. aP = A. for k = 1,2, ........ , nH ••••• (3.112)
Hk Hk
the above equations are called coordination equations, the solution to which will give tlle
economic schedule for Psi and PHk.
s n
+2:£ :£ P, B ..
i=l j=s+1 51 1J
l1Ii~ ..... (3.114)
_ dFI Rsl
- dP. IMwhr ..... (3.116)
51
The incremental transmission losses at steam and hydro plants are given respectively by
__ J m
_
Ow·
- OP
% sec ..... (3.117)
Hj
The total power received by the loads,
s n
P=LP+ LP.-I\. ..... (3.118)
R i=l 51 j=s+l HJ
It is desired to make the total input to the system over a period T a minimum.
From Calculus of variations for FT to be a minimum over the time period T, the first
variation of eq. (3.118) must be set equal to zero.
s n s· 8PL n oPL
L op·+ L OP.- L -- 0 p. - ~ --8PHJ = 0 ..... (3.119)
i=l SI j=s+l HJ i=l apsi SI j=s+lOPHj
T
f
[ FTdt + J=~+l Y
n
J f 1
T
wjdt ..... (3.121)
..... (3.122)
Economic Operation 0/ Power Systems 129
s 17FT n Owj
i.e., L - ap L r·--aPH· - 0 ..... (3.123)
i=1 aPsi si + j=s+1 J aPHj J - ......
Where OPsi and aPHj are the variations in steam power generation and hydro power
generation respectively.
From equation (3.119)
~i=1(1- aPsi - -1
aPL 1Opsi + Ln [ 1 -171\ a~j=o ... (3.124)
j=s+l a~j
For a small variation of oPHm at the mth hydro plant eqn. (3.124) can be split into the
following form.
~l
[ 1 - ~ ap11m = - ±[1 - oPoP.
1=1
L
] ap -.
51
~
J=s+l
(1 - 0It. )aPHi"
OllIJ
..... (3.125)
j*m
Again, eqn. (3.123) can be rewritten as
..... (3.126)
Hence
Ow C1 aF n Ow
Ym-_m apHm =- L _T ap -Y L _J aPH
ap'Hm 1=1 ap.. 51 J J=5+1 8P, ~ ..... (3.127)
p'm HJ
-y. ~
l ~=s+1
Ow; aP (ll- 8PL ")
8P,Hl. Hi~ 8P ...... (3.128)
l"m m
(1- a~ J8PHm is replaced by the quantity on the right hand side of eqn. (3.124) we
~
obtam.
.. .... (3.129)
130 Operation and Control in Power Systems
soFT
=-I:-oP
I=IOP
( OPL 1
51 ll--)-Y
oRlim JJ"m
J=s+1
Ow J
I:n -oR [OPL
ORHJ. H C 1:iD.._.
-- 1 ....... (3.130)
Sl V~ l1J
+ I:n
~=s+ 1
Owj
r· -
J OPHj
OItl
- [ 1 - - - oPJij-
Ol\Ij
J~m
~ Ow m ( OPL 1
~=s+l Ym ~ll- oP. ) oPHj = 0 ..... (3.131)
J~m lim Hj
Eqn. (3.131) can be put as
+ f
1=5+1
Ow j l(l- oPL 1)
YJ Ym OR OR
-A. m OP.
Ow m l(l- ap.
OPL 1)op'Hj =0 ..•••(3.132)
J"m Hj lim lim lim
Note that Opsi and OpHj are the variations in powers at steam and hydro plants respectively
and hence are finite. Then, to make the equation (3.128) satisfied, each of the coefficients of
the variations must be zero. .
and Yj
Ow, ( _ aPL
oP II 1 Ow m (
OR ) - Ym - - 1 - - - =0
0It) ..... (3.134)
Hi lim OPHm 0I\un
In other words,
OF
_T
oW m
Owi
ap OP aPHj
(1- ~PJ) = Ym (ll _ ;PL 1) = Yj (ll _ OPL 1)
l op.. OPHj oPHj
= constant ..... (3.135)
Economic Operation of Power Systems 131
The partial derivatives in the above equation are also the total derivatives. It may also be
recognized that each of the term in the eq. 3.13 5 is also the incremental cost of the received
. .... (3.136)
Ow ( 1 ')
r -)
) apH,j
l-j
1-~
=A.
Also
..... (3.137)
dWj
and -dP = c· PH· + d. ..... (3.139)
Hj J J J
where a and c are the slopes of the incremental cost curves and b and d are the intercepts.
..... (3.142)
132 Operation and Control in Power Systems
Rewriting the third term on the left side of both the above equations, as
S
L Bki P k = BIZ',PSI' + ..... (3.143)
K=1 S
n n
and L BjkI1Ik =B. Ph' + L BkiP k ..... (3.144)
K=s+1 1) ~ K=s+1 s .
K~j
..... (3.145)
and
d) n s
l-"i - L 2B)kPHk - L 2B)IPsl
k=s+1 1=1
..... (3.146)
These two equations (3.145) and (3,146) can be solved iteratively till convergence is obtained
assuming suitable values for A. and Yj .
E 3.7 The input - output data for a particular hydro - plant is given in Fig. E 3.7.1. Find the
incremental water rate characteristic and convert it into an equivalent incremental
production cost characteristic taking the cost of water as 1Q-3Rs.lm3.
r--
""'
'"
1600
1400
1200
'"'e- ' 1000
800
~
.c 600
~ 400
i5
~
200
Solution: The incremental water rate is obtained by finding the slope of the given input -
output curve at different points. A straight line segment approximation of incremental water
rate is obtained as in Fig. E 3.7.2.
4.0
I
~
3.5
3.0
:::E
----
...,rIl
2.5
5 2.0
c:G
~ 1.5
I
1.0
~ Q.
"0"0
I 0.5
-l--+--I--+----l'---+-4--L..+--I---- M W
0 100 200 300 400 500 600 700 800
P ---.
Fig. 3.7.2 Incremental Water rate
Loads:
L1 160 MW
L2 35 MW
L3 72.5 MW
Total Load = 267.5 MW
Base Voltage = 220kV
Base MVA = 100
The B - coefficient matrix is given as
G1 G2 G3
B = G 1 [0.0210
G2 0.0034 0.02497
0.0034 0181
0.0.003 1
G3 0.0181 0.003 0.050
Characteristics of steam and hydro plants
GI - thermal station :
Calorific value of coal 5125 kcal/kg
Cost of coal Rs.45 per ton
Incremental fuel cost at near no - load Rs.21/MWh
Incremental fuel cost at 40MW Rs.23/MWh
Slope of incremental cost curve 0.05
Intercept on y-axis 21
260
260
240 236 230
215
220
1
~
200
178
187
~ 180
o 6 12 16 20 22 24
Time (h) ----.
Fig. E 3.8 Load Curve
Economic Operation of Power Systems 135
G2 - thermal station :
Calorific value of coal 4600 kcallkg
Cost of coal Rs.48 per ton
Incremental fuel cost at near no - load Rs.25/MWh
Incremental fuel cost at 40MW Rs.31.6/MWh
Slope of incremental cost curve 0.094
Intercept on y-axis 21
dF2
- = 0.094PS2 + 21
dP 2
G 3 - Hydro electric plant
Assuming Y3 = 1.0 paise/IOO m3 of water at 104 MW output, the incremental plant
cost = Rs.19.5 per MW h and at 120 MW output the incremental plant cost = Rs.36
per MWh. Slope of the incremental cost curve
y = 16.5 =1.03
-16
Intercept on y-axis = - 88
dWl
Y1
-
=--'
dP
= 19.5;0 $ PH3 $104MW
H3
= 1.03PH3 - 88;
104 $ PH3 $120MW
The system daily load curve is given in Fig. E 3.8 as shown. Obtain the economic
schedules.
Solution:
The scheduling equations are given from eqs. (6. 102) and (6.103) as
1-~-0.000068P2 -0.000362P
PI = ___A~___________________3
0.05 + 0.00042
A
21
1-- - 0.000068 PI - 0.000060 P3
A
P2=--~--------------------
-
0.094 + 0.0004994
A
88
I + - - 0.000362 PI - 0.000060 P2
P3 = A
1.03 + 0.00 I 0
A
136 Operation and Control in Power Systems
in order to schedule for a specified received load, the values of I are computed from
equation as
+ (p(d)
1.(1-1) 1.(1-2) 1
1.(1) = 1.(1-1)
R
_ p(I-I)
R
Where F and P are fuel in put in K-cal/hr and unit output in MW respectively. The daily
load cycle is given as follows.
Time Load
12 midnight 6 am 50MW
6 am to 6 pm 150MW
6 pm to 12 midnight 50MW
Give the economic schedule for the three periods of the day
Solution:
Let the cost of the fuel be the same at both the plants.
dF
_I = (7 + 0.06PI )10 6 K-cal/MWhr
dPI
If C is cost of fuel in Rs/K-cal.
The incremental production cost at plant 1
dC I 6
=-=(7+0.06PI )10 xC Rs per MWhr
dP I
dC 2 6
similarly =- = (5 + 0.IP 2 )10 xC Rs per MWhr
dP 2
For economy
dP I dP 2
and P I +P 2 = 50 MW (i)
(7 + 0.06 PI) \06 xC = (5 + 0.1 P2 )106 xC (ii)
solving (i) and (ii) for PI and P2
PI = 18.75 MW
P2 = 31.25 MW
For PI + P2 = 150MW