993 section of new NH-39 (Old NH-75E)(Design Length 105.593 km to four lane
Name of Project
paved shoulders on through Engineering, Procurement & Construction (EPC) mode under NH (O) in the state of Madhya Pradesh.
Employer Ministry of Road Transport & Highway
Client M.P. Road Development Corporation Ltd.
Authority Engineer
EPC Contractor Tirupati Build-con Pvt. Ltd.
RFI SUMMARY 2022 (HIGHWAY)
Date of Submission : 12/Nov/21
S.No RFI NO. Item Description Chainage Length Side Details of Inspection Status
From To Date Time
1 NH-39/HW/1 Checking of C&G Existing Road 156+030 156+380 350.00 RHS 13-11-21 9.00 AM
2 NH-39/HW/2 Checking of C&G Existing Road 156+030 156+380 350.00 LHS 13-11-21 10.00 AM
3 NH-39/HW/3 Checking of C&G Existing Road 156+900 157+245 345.00 RHS 13-11-21 11.00AM
4 NH-39/HW/4 Checking of C&G Existing Road 156+900 157+245 345.00 LHS 13-11-21 12.00AM
5 NH-39/HW/5 Checking of C&G Existing Road 163+100 163+250 150.00 LHS 13-11-21 1.00PM
6 NH-39/HW/6 Checking of C&G Existing Road 163+350 163+600 250.00 RHS 13-11-21 3.00PM
7 NH-39/HW/7 Checking of C&G Existing Road 168+170 168+575 405.00 LHS 13-11-21 3.30PM
8 NH-39/HW/8 Checking of C&G Existing Road 168+170 168+575 405.00 RHS 13-11-21 4.00PM
9 NH-39/HW/9 Checking of C&G Existing Road 169+000 169+150 150.00 LHS 13-11-21 4.30PM
10 NH-39/HW/10 Checking of C&G Existing Road 169+000 169+150 150.00 RHS 13-11-21 5.00PM
11 NH-39/HW/11
12 NH-39/HW/12
13 NH-39/HW/13
14 NH-39/HW/14
15 NH-39/HW/15 Checking of C&G Existing Road 163+100 163+250 150.00 RHS 14-11-21 9.00AM
16 NH-39/HW/16 Checking of C&G Existing Road 163+350 163+600 250.00 LHS 14-11-21 10.00AM
17 NH-39/HW/17 Checking of C&G Existing Road 165+600 165+800 200.00 RHS 14-11-21 10.30AM
18 NH-39/HW/18 Checking of C&G Existing Road 165+600 165+800 200.00 LHS 14-11-21 10.45AM
19 NH-39/HW/19 Checking of C&G Existing Road 156+700 156+850 150.00 RHS 14-11-21 11.00AM
20 NH-39/HW/20 Checking of C&G Existing Road 156+700 156+850 150.00 LHS 14-11-21 11.00AM
21 NH-39/HW/21 Checking of C&G Existing Road 177+580 177+900 320.00 RHS 14-11-21 12.00AM
22 NH-39/HW/22 Checking of C&G Existing Road 177+580 177+900 320.00 LHS 14-11-21 12.30AM
NH-39/HW/23 Checking of Benching &OGL Level And FDD for Embankment 177+580 177+900 RHS 14-11-21 8.30AM
23 Construction 320.00
NH-39/HW/24 Checking of Benching &OGL Level And FDD for Embankment 177+580 177+900 LHS 14-11-21 9.00AM
24 Construction 320.00
25 NH-39/HW/25 Checking of Emb.1st layer FDD test 177+580 177+900 320.00 RHS 14-11-21 3.00PM
26 NH-39/HW/26 Checking of Emb.1st layer FDD test 177+580 177+900 320.00 LHS 14-11-21 4.00PM
NH-39/HW/27 Checking of Benching &OGL Level And FDD for Embankment 156+900 157+245 RHS 14-11-21 4.30PM
27 Construction 345.00
NH-39/HW/28 Checking of Benching &OGL Level And FDD for Embankment 156+900 157+245 LHS 14-11-21 5.00PM
28 Construction 345.00
NH-39/HW/29 Checking of Benching &OGL Level And FDD for Embankment 163+100 163+250 RHS 14-11-21 5.30PM
29 Construction 150.00
NH-39/HW/30 Checking of Benching &OGL Level And FDD for Embankment 163+100 163+250 LHS 14-11-21 5.45PM
30 Construction 150.00
1673 NH-39/HW/1661 Application of Prime coat for DBM laying (Truck Lay Bye) 157+860 158+100 240 LHS 23-01-22 8.10 AM
1674 NH-39/HW/1662 Application of Prime coat for DBM laying 170+900 171+160 260 RHS 23-01-22 8.20AM
1675 NH-39/HW/1663 FDD Checking for WMM 1st layer 172+280 172+400 120 LHS 23-01-22 08.30AM
1676 NH-39/HW/1664 FDD Checking for WMM TOP layer Truck Lay Bye 157+860 158+100 240 LHS 23-01-22 09.30AM
1677 NH-39/HW/1665 Level & FDD Checking for SG Top layer 156+073 156+460 387 LHS 23-01-22 10.00AM
1678 NH-39/HW/1666 Level & FDD Checking for SG Top layer 157+470 157+490 20 LHS 23-01-22 10.20 AM
1679 NH-39/HW/1667 Level & FDD Checking for GSB Top layer 152+880 153+050 170 RHS 23-01-22 10.40 AM
1680 NH-39/HW/1668 Application of Tack coat for DBM laying (Truck Lay Bye) 157+860 158+100 240 LHS 23-01-22 11.10 AM
1681 NH-39/HW/1669 Checking of DBM Laying (Truck Lay Bye) 157+860 158+100 240 LHS 23-01-22 11.10 AM
1834 NH-39/HW/1822 Application of Tack coat for DBM laying (over lay section) 161+900 162+970 1070 RHS 27-01-22 8.10 AM
1835 NH-39/HW/1823 Application of Tack coat for DBM laying (over lay section) 165+250 165+580 330 RHS 27-01-22 08.30AM
1899 NH-39/HW/1887 Application of Tack coat for DBM laying (over lay section) 147+300 148+200 RHS 27-01-22
1900 NH-39/HW/1888 Checking of DBM Laying (Over Lay Section) 147300 148200 RHS 27-01-22
1901 NH-39/HW/1889 Level & FDD Checking for GSB Top (Service Road) layer 100+810 101+300 490 RHS 27-01-22
1902 NH-39/HW/1890 Level & FDD Checking for GSB Top (Service Road) layer 110+042 110+130 88 RHS 27-01-22
1903 NH-39/HW/1891 27-01-22
1904 NH-39/HW/1892 27-01-22
1905 NH-39/HW/1893 Application of Tack coat for DBM laying 163232 163360 LHS 128 27-01-22
1906 NH-39/HW/1894 Application of Tack coat for DBM laying 167540 168000 LHS 460 27-01-22
1907 NH-39/HW/1895 Checking of DBM Laying 163232 163360 LHS 128 27-01-22
1908 NH-39/HW/1896 Checking of DBM Laying 167540 168000 LHS 460 27-01-22
NH-39/HW/1897
1910 NH-39/HW/1898
1911 NH-39/HW/1899
1912 NH-39/HW/1900
2237 NH-39/HW/2225
2238 NH-39/HW/2226
2239 NH-39/HW/2227
2240 NH-39/HW/2228
2241 NH-39/HW/2229
2242 NH-39/HW/2230
2243 NH-39/HW/2231 FDD Checking of Emb.31st layer 169+080 169+180 100 LHS 26-02-22
2244 NH-39/HW/2232 Application of Prime Coat for DBM Laying 108+630 109+000 370 LHS 26-02-22
2245 NH-39/HW/2233 level & FDD Checking for WMM Top layer 171+160 171+260 100 RHS 26-02-22
2246 NH-39/HW/2234 FDD Checking of Emb.31st layer 169+080 169+180 100 RHS 26-02-22
2247 NH-39/HW/2235 level & FDD Checking for WMM Top layer 109+000 109+144 144 RHS 26-02-22
2248 NH-39/HW/2236 level & FDD Checking for WMM Top layer 109+184 109+260 76 RHS 26-02-22
2249 NH-39/HW/2237 Kerb Over Laping 151+000 152+000 1000 LHS 26-02-22
2250 NH-39/HW/2238
2251 NH-39/HW/2239
2252 NH-39/HW/2240
2253 NH-39/HW/2241
2254 NH-39/HW/2242
2021 NH-39/HW/2009 Application of Prime coat for DBM laying 157+000 157+490 490 RHS 07-02-22
2256 NH-39/HW/2244
3510 NH-39/HW/3498 Level & FDD Checking of Emb.top layer (Truck lay bye bay) 83+650 83+890 240 LHS
26-05-22 27-05-22 9.30am
3511 NH-39/HW/3499 Level & FDD Checking of SG Top layer (Truck lay bye bay) 83+680 83+920 240 RHS
26-05-22 27-05-22 10.00am
3512 NH-39/HW/3500 Level &FDD Checking for GSB TOP layer 83+220 83+600 380 RHS 26-05-22 27-05-22 11.30am
3513 NH-39/HW/3501 Checking of C&G Existing Road 106+700 107+200 500 RHS 26-05-22 27-05-22 12.30pm
3514 NH-39/HW/3502 FDD Checking of SG 1st layer 83+650 83+890 240 LHS 26-05-22 27-05-22 2.30pm
3515 NH-39/HW/3503
3516 NH-39/HW/3504
3517 NH-39/HW/3505
3518 NH-39/HW/3506
3519 NH-39/HW/3507
3520 NH-39/HW/3508
3521 NH-39/HW/3509
3522 NH-39/HW/3510
3523 NH-39/HW/3511
3524 NH-39/HW/3512
3525 NH-39/HW/3513 FDD Checking of SG 2nd layer (Truck lay bye bay) 83+650 83+890 240 LHS 27-05-22 28-05-22 10.30pm
3526 NH-39/HW/3514 Level & FDD Checking of SG Top layer (Truck lay bye bay) 83+650 83+890 240 LHS
27-05-22 28-05-22 3.30pm
3527 NH-39/HW/3515
3528 NH-39/HW/3516
3529 NH-39/HW/3517
3530 NH-39/HW/3518
3531 NH-39/HW/3519
3532 NH-39/HW/3520
3533 NH-39/HW/3521
3534 NH-39/HW/3522
Tirupati Build-con Pvt. Ltd.Sub-Contractor Highway RFI Authority Engineer
RFI SUMMARY 2022 (HIGHWAY)
Date of Submission : 12/Nov/21
S.No RFI NO. Item Description Chainage Length Side Details of Inspection Status
From To Date Time
3535 NH-39/HW/3523
3536 NH-39/HW/3524 Pote Hole Repair for WMM material 179+000 183+000 4000 BHS 28-05-22 29-05-22 10.00AM
3537 NH-39/HW/3525 Pote Hole Repair for WMM material 107+500 108+000 500 BHS 28-05-22 29-05-22 10.30AM
3538 NH-39/HW/3526
3539 NH-39/HW/3527
3540 NH-39/HW/3528
3541 NH-39/HW/3529
3542 NH-39/HW/3530
3543 NH-39/HW/3531
3544 NH-39/HW/3532
3545 NH-39/HW/3533
3546 NH-39/HW/3534
3547 NH-39/HW/3535
3548 NH-39/HW/3536
3549 NH-39/HW/3537
3550 NH-39/HW/3538
3551 NH-39/HW/3539 Pote Hole Repair for GSB material 183+000 185+000 2000 BHS 29-05-22 30-05-22 9.00AM
3552 NH-39/HW/3540 Pote Hole Repair for WMM material 183+000 185+000 2000 BHS 29-05-22 30-05-22 2.30PM
3553 NH-39/HW/3541
3554 NH-39/HW/3542
3555 NH-39/HW/3543
3556 NH-39/HW/3544
3557 NH-39/HW/3545
3558 NH-39/HW/3546
3559 NH-39/HW/3547
3560 NH-39/HW/3548 FDD Checking of SG 1st layer 184+370 184+750 380 LHS 30-05-22 31-05-22 11.00am
3561 NH-39/HW/3549 FDD Checking of SG 1st layer 184+900 184+980 80 LHS 30-05-22 31-05-22 12.00pm
3562 NH-39/HW/3550 Checking of C&G Existing Road (Bus bay) 92+820 93+060 240 LHS 30-05-22 31-05-22 9.00AM
3563 NH-39/HW/3551 Pote Hole Repair for GSB material (Sajhar) 132+000 134+000 2000 BHS 30-05-22 31-05-22 10.00AM
3564 NH-39/HW/3552 Pote Hole Repair for WMM material (Sajhar) 132+000 134+000 2000 BHS 30-05-22 31-05-22 11.30PM
3565 NH-39/HW/3553 30-05-22
3566 NH-39/HW/3554 30-05-22
3567 NH-39/HW/3555 30-05-22
3568 NH-39/HW/3556 31-05-22
3569 NH-39/HW/3557 31-05-22
3570 NH-39/HW/3558 Level & FDD Checking of SG top layer 179+980 180+450 470 RHS 31-05-22 01-06-22 8.00am
3571 NH-39/HW/3559 FDD Checking of SG 1st layer (Bus bay) 92+820 93+060 240 LHS 31-05-22 01-06-22 8.20am
3572 NH-39/HW/3560 FDD Checking of SG 1st layer (Bus bay) 92+680 92+920 240 RHS 31-05-22 01-06-22 8.40am
3573 NH-39/HW/3561 FDD Checking of SG 2nd layer 105+800 106+000 200 RHS 31-05-22 01-06-22 9.10am
NH-39/HW/3628 Application of Prime Coat for Patch Repair with DBM 178+500 181+100 2600 04-06-22 05-06-22 10.00am
3640 material
3641 NH-39/HW/3629 Level & FDD Checking of WMM top layer 184+370 184+750 380 LHS 04-06-22 05-06-22
3642 NH-39/HW/3630 Level & FDD Checking of WMM top layer 184+900 184+980 80 LHS 04-06-22 05-06-22
3643 NH-39/HW/3631 FDD Checking of WMM 1st layer 179+980 180+450 RHS 05-06-22 06-06-22
3644 NH-39/HW/3632 Checking of Drilling & Excavation For Hill area 140+800 140+950 150 LHS 05-06-22 06-06-22 11.00AM
3645 NH-39/HW/3633 Checking of Drilling & Excavation For Hill area 140+950 141+100 150 LHS 05-06-22 06-06-22 12.00PM
3646 NH-39/HW/3634 Checking of Drilling & Excavation For Hill area 143+800 144+000 200 LHS 05-06-22 06-06-22 12.00PM
3647 NH-39/HW/3635 Checking of Drilling & Excavation For Hill area 144+000 144+200 200 LHS 05-06-22 06-06-22 12.00PM
3648 NH-39/HW/3636 Application of Tack Coat for Patch Repair with DBM material 178+500 181+100 2600 06-06-22 07-06-22 10.00am
3649 NH-39/HW/3637 Checking of Patch Repair with DBM material 178+500 181+100 2600 06-06-22 07-06-22 10.30am
3750 NH-39/HW/3738 Pote Hole Repair for WMM material 180+500 185+000 4500 BHS 30-06-22 01-07-22 8.30am
3751 NH-39/HW/3739 Pote Hole Repair for WMM material 82+460 94+000 11540 LHS 30-06-22 01-07-22 9.00am
3752 NH-39/HW/3740 FDD Checking of WMM 1st layer 180+000 180+420 420 RHS 30-06-22 01-07-22 3.00pm
3753 NH-39/HW/3741 Pote Hole Repair for WMM material 94+000 110+000 16000 RHS 01-07-22 02-07-22 9.30AM
3754 NH-39/HW/3742 Pote Hole Repair for WMM material 132+000 138+000 6000 BHS 03-07-22 04-07-22 10.00am
3755 NH-39/HW/3743 FDD Checking of Sugrade 1st layer 108+240 108+360 120 LHS 13-07-22 14-07-22 10.00am
3756 NH-39/HW/3744 Application of Tack Coat for DBM Laying 172+400 172+550 150 RHS 15-07-22 15-07-22 11.30am
3757 NH-39/HW/3745 Checking of DBM Over lay laying 172+400 172+550 150 RHS 15-07-22 15-07-22 12.00 Pm
3758 NH-39/HW/3746 FDD Checking of SG 2nd layer 108+220 108+360 140 LHS 15-07-22 16-07-22 9.30AM
3824 NH-39/HW/3812 Checking of Excavation up to GSB layer 146+290 146+305 15 LHS 03-08-22 04-08-22
NH-39/HW/3812 Checking of Excavation up to GSB layer 146+220 146+240 20 RHS 03-08-22 04-08-22
NH-39/HW/3812 Checking of Excavation up to GSB layer 146+340 146+355 15 RHS 03-08-22 04-08-22
NH-39/HW/3812 Checking of Excavation up to GSB layer 146+420 146+432 12 RHS 03-08-22 04-08-22 10.00am
NH-39/HW/3812 Checking of Excavation up to GSB layer 146+570 146+581 11 RHS 03-08-22 04-08-22
NH-39/HW/3812 Checking of Excavation up to GSB layer 146+720 146+733 13 RHS 03-08-22 04-08-22
NH-39/HW/3812 Checking of Excavation up to GSB layer 146+845 146+860 15 RHS 03-08-22 04-08-22
3825 NH-39/HW/3813 Level & FDD Checking of GSB Top layer 146+290 146+305 15 LHS 03-08-22 04-08-22
NH-39/HW/3813 Level & FDD Checking of GSB Top layer 146+220 146+240 20 RHS 03-08-22 04-08-22
NH-39/HW/3813 Level & FDD Checking of GSB Top layer 146+340 146+355 15 RHS 03-08-22 04-08-22
NH-39/HW/3813 Level & FDD Checking of GSB Top layer 146+420 146+432 12 RHS 03-08-22 04-08-22 11.30am
NH-39/HW/3813 Level & FDD Checking of GSB Top layer 146+570 146+581 11 RHS 03-08-22 04-08-22
NH-39/HW/3813 Level & FDD Checking of GSB Top layer 146+720 146+733 13 RHS 03-08-22 04-08-22
NH-39/HW/3813 Level & FDD Checking of GSB Top layer 146+845 146+860 15 RHS 03-08-22 04-08-22
3826 NH-39/HW/3814 FDD Checking of WMM 1st layer (Patch work) 146+290 146+305 15 LHS 03-08-22 04-08-22
NH-39/HW/3814 FDD Checking of WMM 1st layer (Patch work) 146+220 146+240 20 RHS 03-08-22 04-08-22
NH-39/HW/3814 FDD Checking of WMM 1st layer (Patch work) 146+340 146+355 15 RHS 03-08-22 04-08-22
NH-39/HW/3814 FDD Checking of WMM 1st layer (Patch work) 146+420 146+432 12 RHS 03-08-22 04-08-22 12.30pm
NH-39/HW/3814 FDD Checking of WMM 1st layer (Patch work) 146+570 146+581 11 RHS 03-08-22 04-08-22
NH-39/HW/3814 FDD Checking of WMM 1st layer (Patch work) 146+720 146+733 13 RHS 03-08-22 04-08-22
NH-39/HW/3814 FDD Checking of WMM 1st layer (Patch work) 146+845 146+860 15 RHS 03-08-22 04-08-22
3827 NH-39/HW/3815 Level & FDD Checking of WMM Top layer 146+290 146+305 15 LHS 03-08-22 04-08-22
NH-39/HW/3815 Level & FDD Checking of WMM Top layer 146+220 146+240 20 RHS 03-08-22 04-08-22
NH-39/HW/3815 Level & FDD Checking of WMM Top layer 146+340 146+355 15 RHS 03-08-22 04-08-22
NH-39/HW/3815 Level & FDD Checking of WMM Top layer 146+420 146+432 12 RHS 03-08-22 04-08-22 2.30pm
NH-39/HW/3815 Level & FDD Checking of WMM Top layer 146+570 146+581 11 RHS 03-08-22 04-08-22
NH-39/HW/3815 Level & FDD Checking of WMM Top layer 146+720 146+733 13 RHS 03-08-22 04-08-22
4.00am
Tirupati Build-con Pvt. Ltd.Sub-Contractor Highway RFI Authority Engineer
RFI SUMMARY 2022 (HIGHWAY)
Date of Submission : 12/Nov/21
S.No RFI NO. Item Description Chainage Length Side Details of Inspection Status
From To Date Time
4012 NH-39/HW/3918 Checking of DBM lay laying (patch work) 96+174 96+176 1.5 RHS
4.00am
4013 NH-39/HW/3918 Checking of DBM lay laying (patch work) 96+189 96+193 3.6 RHS
4014 NH-39/HW/3918 Checking of DBM lay laying (patch work) 96+279 96+284 4.6 RHS
4015 NH-39/HW/3918 Checking of DBM lay laying (patch work) 96+321 96+323 1.8 RHS
4016 NH-39/HW/3918 Checking of DBM lay laying (patch work) 96+391 96+404 12.4 RHS
4017 NH-39/HW/3919 Checking of DBM lay laying (patch work) 96+411 96+420 8.9 RHS 06-08-22 07-08-22
4018 NH-39/HW/3919 Checking of DBM lay laying (patch work) 96+423 96+427 4.2 RHS
4019 NH-39/HW/3919 Checking of DBM lay laying (patch work) 96+440 96+442 1.5 RHS
4020 NH-39/HW/3919 Checking of DBM lay laying (patch work) 96+485 96+500 14.7 RHS
4.20pm
4021 NH-39/HW/3919 Checking of DBM lay laying (patch work) 96+504 96+506 2.5 RHS
4022 NH-39/HW/3919 Checking of DBM lay laying (patch work) 96+517 96+519 1.5 RHS
4023 NH-39/HW/3919 Checking of DBM lay laying (patch work) 96+531 96+542 11.8 RHS
4024 NH-39/HW/3919 Checking of DBM lay laying (patch work) 96+543 96+546 3.3 RHS
4025 NH-39/HW/3920 Checking of DBM lay laying (patch work) 96+563 96+572 9 RHS 06-08-22 07-08-22
4026 NH-39/HW/3920 Checking of DBM lay laying (patch work) 96+574 96+590 16.6 RHS
4027 NH-39/HW/3920 Checking of DBM lay laying (patch work) 96+655 96+662 6.6 RHS
4028 NH-39/HW/3920 Checking of DBM lay laying (patch work) 96+742 96+743 1.5 RHS
4.30pm
4029 NH-39/HW/3920 Checking of DBM lay laying (patch work) 96+850 96+853 3.35 RHS
4030 NH-39/HW/3920 Checking of DBM lay laying (patch work) 96+881 96+884 3.45 RHS
4031 NH-39/HW/3920 Checking of DBM lay laying (patch work) 96+902 96+915 13.3 RHS
4032 NH-39/HW/3920 Checking of DBM lay laying (patch work) 96+922 96+930 7.6 RHS
4033 NH-39/HW/3921 FDD Checking of SG 1st layer 103+150 103+740 590 LHS 06-08-22 07-08-22 5.00pm
4034 NH-39/HW/3922 FDD Checking of SG 2nd layer 103+150 103+740 590 LHS 07-08-22 08-08-22 9.00am
4035 NH-39/HW/3923 Application of Prime Coat for DBM Laying (patch work) 97+181 97+185 4.25 RHS 07-08-22 08-08-22
4036 NH-39/HW/3923 Application of Prime Coat for DBM Laying (patch work) 97+185 97+219 33.6 RHS
4037 NH-39/HW/3923 Application of Prime Coat for DBM Laying (patch work) 97+260 97+278 18.3 RHS
4038 NH-39/HW/3923 Application of Prime Coat for DBM Laying (patch work) 97+286 97+313 27.4 RHS
10.00am
4039 NH-39/HW/3923 Application of Prime Coat for DBM Laying (patch work) 97+345 97+351 6 RHS
4040 NH-39/HW/3923 Application of Prime Coat for DBM Laying (patch work) 97+402 97+405 2.8 RHS
4041 NH-39/HW/3923 Application of Prime Coat for DBM Laying (patch work) 97+491 97+495 4.2 RHS
4042 NH-39/HW/3923 Application of Prime Coat for DBM Laying (patch work) 97+665 97+668 2.7 RHS
4161 NH-39/HW/3987 Application of Tack Coat for DBM over Laying 138+350 138+700 350 LHS 16-08-22 17-08-22 11.30am
4162 NH-39/HW/3988 Checking of DBM over lay laying 138+350 138+700 350 LHS 16-08-22 17-08-22 12.30Pm
4163 NH-39/HW/3989 16-08-22 17-08-22
4164 NH-39/HW/3990 FDD Checking for WMM 1st Layer 158+740 158+900 160 LHS 16-08-22 17-08-22
4165 NH-39/HW/3991 FDD Checking for WMM 1st Layer 145+570 146+100 530 LHS 16-08-22 17-08-22
4166 NH-39/HW/3992 16-08-22 17-08-22
4167 NH-39/HW/3993 FDD & Level Checking for WMM Top Layer 92+200 92+610 410 RHS 16-08-22 17-08-22
4168 NH-39/HW/3994 FDD & Level Checking for WMM Top Layer 105+780 106+210 430 RHS 16-08-22 17-08-22
4169 NH-39/HW/3995 FDD Checking for WMM 1st Layer 106+210 106+515 305 RHS 16-08-22 17-08-22
4170 NH-39/HW/3996 FDD Checking for WMM 1st Layer 106+535 107+030 495 RHS 16-08-22 17-08-22
4171 NH-39/HW/3997 Application of Tack Coat for DBM over Laying 138+700 139+300 600 LHS 17-08-22 18-08-22
4172 NH-39/HW/3998 Checking of DBM over lay laying 138+700 139+300 600 LHS 17-08-22 18-08-22
4173 NH-39/HW/3999 17-08-22 18-08-22
4174 NH-39/HW/4000 FDD & Level Checking for WMM Top Layer 158+740 158+900 160 LHS 17-08-22 18-08-22
4175 NH-39/HW/4001 FDD & Level Checking for WMM Top Layer 145+570 146+100 530 LHS 17-08-22 18-08-22
GSB Top Level & FDD Checking for Extra Widening due to
4176 NH-39/HW/4002 short width of existing MCW
140+000 140+620 620 LHS 17-08-22 18-08-22 8.30am
4177 NH-39/HW/4003 Application of Tack Coat for DBM Laying (patch work) 140+030 140+032 2 RHS 17-08-22 18-08-22
4178 NH-39/HW/4003 Application of Tack Coat for DBM Laying (patch work) 140+040 140+080 40 RHS
4179 NH-39/HW/4003 Application of Tack Coat for DBM Laying (patch work) 139+100 139+115 15 RHS 9.30am
4180 NH-39/HW/4003 Application of Tack Coat for DBM Laying (patch work) 139+115 139+119 4 LHS
4192 NH-39/HW/4010 Application of Tack Coat for DBM over Laying 138+642 139+350 708 LHS 18-08-22 19-08-22 09.30am
4193 NH-39/HW/4011 Checking of DBM over lay laying 138+642 139+350 708 LHS 18-08-22 19-08-22 10.30am
WMM Top Level & FDD Checking for Extra Widening due to
4194 NH-39/HW/4012 short width of existing MCW
140+000 140+620 620 LHS 18-08-22 19-08-22 4.30pm
4195 NH-39/HW/4013 Application of Tack Coat for DBM over Laying 96+060 97+000 940 RHS 18-08-22 19-08-22
4196 NH-39/HW/4014 Checking of DBM over lay laying 96+060 97+000 940 RHS 18-08-22 19-08-22
4197 NH-39/HW/4015 18-08-22 19-08-22
4198 NH-39/HW/4016 18-08-22 19-08-22
4199 NH-39/HW/4017 Level & FDD Checking of WMM Top layer 88+250 88+340 90 RHS 19-08-22 20-08-22 10.30am
4200 NH-39/HW/4018 Application of Tack Coat for DBM over Laying 138+642 139+350 708 LHS 19-08-22 20-08-22 11.30AM
4201 NH-39/HW/4019 Checking of DBM over lay laying 138+642 139+350 708 LHS 19-08-22 20-08-22 12.30PM
4202 NH-39/HW/4020 Level & FDD Checking of WMM Top layer 84+500 85+300 800 RHS 19-08-22 20-08-22 4.30PM
4203 NH-39/HW/4021 Application of Prime Coat for DBM Extra Widening due to 140+000 140+620 620 LHS 19-08-22 20-08-22
short width of existing MCW
4204 NH-39/HW/4022 19-08-22 20-08-22
4205 NH-39/HW/4023 FDD Checking for WMM 1st Layer 107+030 107+350 320 RHS 19-08-22 20-08-22
4206 NH-39/HW/4024 19-08-22 20-08-22
4207 NH-39/HW/4025 Application of Tack Coat for DBM Extra Widening due to short 140+000 140+620 620 LHS 20-08-22 21-08-22
width of existing MCW
4208 NH-39/HW/4026 Checking of DBM Extra Widening due to short width of 140+000 140+620 620 LHS 20-08-22 21-08-22
existing MCW
4209 NH-39/HW/4027 20-08-22 21-08-22
4210 NH-39/HW/4028 FDD & Level Checking for WMM Top Layer 107+030 107+350 320 RHS 20-08-22 21-08-22
GSB Top Level & FDD Checking for Extra Widening due to
4240 NH-39/HW/4058 short width of existing MCW
140+000 140+620 620 RHS 24-08-22 24-08-22 5.30PM
4241 NH-39/HW/4059
4242 NH-39/HW/4060 24-08-22 25-08-22 10.00am
4243 NH-39/HW/4061 FDD Checking of EMB 6th layer 142+350 142+500 150 LHS 24-08-22 25-08-22 10.30am
4244 NH-39/HW/4062 Application of Tack Coat for DBM over Laying 99+800 100+000 200 RHS 24-08-22 25-08-22 11.30am
4247 NH-39/HW/4065 Application of Tack Coat for DBM over Laying 101+300 101+600 300 RHS 24-08-22 25-08-22 2.30pm
4248 NH-39/HW/4066 Checking of DBM over lay laying 101+300 101+600 300 RHS 24-08-22 25-08-22 3.30pm
4249 NH-39/HW/4067 FDD Checking of EMB 7th layer 142+350 142+500 150 LHS 25-08-22 26-08-22 10.00am
4250 NH-39/HW/4068 Application of Tack Coat for DBM over Laying 101+600 102+000 400 RHS 25-08-22 26-08-22 11.30am
4251 NH-39/HW/4069 Checking of DBM over lay laying 101+600 102+000 400 RHS 25-08-22 26-08-22 12.30pm
WMM Top Level & FDD Checking for Extra Widening due to
4252 NH-39/HW/4070 short width of existing MCW
140+000 140+620 620 RHS 25-08-22 26-08-22 4.30 pm
4261 NH-39/HW/4079 Application of Tack Coat for DBM over Laying 99+800 100+000 200 RHS 28-08-22 28-08-22
4262 NH-39/HW/4080 Checking of DBM over lay laying 99+800 100+000 200 RHS 28-08-22 28-08-22
4263 NH-39/HW/4081 Application of Tack Coat for DBM over Laying 138+700 139+135 435 RHS 28-08-22 28-08-22
4264 NH-39/HW/4082 Checking of DBM over lay laying 138+700 139+135 435 RHS 28-08-22 28-08-22
4265 NH-39/HW/4083
4266 NH-39/HW/4084 Tree Plantation Work 29-08-22 29-08-22
4267 NH-39/HW/4085 FDD Checking of EMB 9th layer 142+350 142+500 150 LHS 29-08-22 29-08-22 10.00am
4268 NH-39/HW/4086 FDD Checking of EMB 10th layer 142+350 142+500 150 LHS 29-08-22 30-08-22 10.00am
4269 NH-39/HW/4087 Application of Tack Coat for DBM over Laying 97+000 97+400 400 LHS 29-08-22 30-08-22 11.00am
4270 NH-39/HW/4088 Checking of DBM over lay laying 97+000 97+400 400 LHS 29-08-22 30-08-22 12.00pm
4271 NH-39/HW/4089 Application of Tack Coat for DBM over Laying 137+740 138+540 800 RHS 29-08-22 30-08-22
4272 NH-39/HW/4090 Checking of DBM over lay laying 137+740 138+540 800 RHS 29-08-22 30-08-22
4273 NH-39/HW/4091 Application of Tack Coat for DBM over Laying 97+600 98+000 400 LHS 29-08-22 30-08-22
4274 NH-39/HW/4092 Checking of DBM over lay laying 97+600 98+000 400 LHS 29-08-22 30-08-22
SG Top Level & FDD Checking for Extra Widening due to short
4275 NH-39/HW/4093 width of existing MCW
101+500 102+000 500 RHS 30-08-22 30-08-22
4276 NH-39/HW/4094 Application of Tack Coat for DBM over Laying 98+000 98+500 500 LHS 30-08-22 31-08-22
4277 NH-39/HW/4095 Checking of DBM over lay laying 98+000 98+500 500 LHS 30-08-22 31-08-22
GSB Top Level & FDD Checking for Extra Widening due to
4278 NH-39/HW/4096 short width of existing MCW
101+500 102+000 500 RHS 30-08-22 31-08-22
GSB Top Level & FDD Checking for Extra Widening due to
4292 NH-39/HW/4110 short width of existing MCW
102+000 102+300 300 RHS 31-08-22 01-09-22
SG Top Level & FDD Checking for Extra Widening due to short
4293 NH-39/HW/4111 width of existing MCW
102+300 102+800 500 RHS 01-09-22 02-09-22
4294 NH-39/HW/4112 FDD Checking of EMB 11th layer 142+350 142+500 150 LHS 01-09-22 02-09-22
WMM 1st & FDD Checking for Extra Widening due to short
4295 NH-39/HW/4113 width of existing MCW
101+390 101+500 110 RHS 01-09-22 02-09-22
WMM 1st & FDD Checking for Extra Widening due to short
4296 NH-39/HW/4114 width of existing MCW
102+000 102+300 300 RHS 01-09-22 02-09-22
WMM 1st & FDD Checking for Extra Widening due to short
4297 NH-39/HW/4115 width of existing MCW
101+500 102+000 500 RHS 01-09-22 02-09-22
4298 NH-39/HW/4116 FDD & Level Checking for Sub Grade Top 134+640 134+680 40 LHS 02-09-22 03-09-22
GSB Top Level & FDD Checking for Extra Widening due to
4299 NH-39/HW/4117 short width of existing MCW
102+300 102+800 500 RHS 02-09-22 03-09-22
WMM Top level & FDD Checking for Extra Widening due to
4300 NH-39/HW/4118 short width of existing MCW
101+390 101+500 110 RHS 02-09-22 03-09-22
WMM Top level & FDD Checking for Extra Widening due to
4301 NH-39/HW/4119 short width of existing MCW
102+000 102+300 300 RHS 02-09-22 03-09-22
WMM Top level & FDD Checking for Extra Widening due to
4302 NH-39/HW/4120 short width of existing MCW
101+500 102+000 500 RHS 02-09-22 03-09-22
SG Top Level & FDD Checking for Extra Widening due to short
4303 NH-39/HW/4121 width of existing MCW
102+800 103+050 250 RHS 02-09-22 03-09-22
4304 NH-39/HW/4122 WMM Top level & FDD Checking 97+180 97+400 0+220 LHS 02-09-22 03-09-22
4305 NH-39/HW/4123 Checking of Center line 137+600 137+700 100 RHS 02-09-22 03-09-22
GSB Top Level & FDD Checking for Extra Widening due to
4308 NH-39/HW/4126 short width of existing MCW
102+800 103+050 250 RHS 03-09-22 04-09-22
4309 NH-39/HW/4127 FDD & Level Checking for GSB Top 134+640 134+680 40 LHS 05-09-22 06-09-22
WMM Top level & FDD Checking for Extra Widening due to
4310 NH-39/HW/4128 short width of existing MCW
102+300 102+800 500 RHS 05-09-22 06-09-22
WMM 1st & FDD Checking for Extra Widening due to short
4311 NH-39/HW/4129 width of existing MCW
102+800 103+050 250 RHS 05-09-22 06-09-22
4312 NH-39/HW/4130 Application of Tack Coat for DBM over Laying 138+500 139+135 635 RHS 08-09-22 09-09-22
4313 NH-39/HW/4131 Checking of DBM over lay laying 138+500 139+135 635 RHS 08-09-22 09-09-22
WMM Top level & FDD Checking for Extra Widening due to
4314 NH-39/HW/4132 short width of existing MCW
102+800 103+050 250 RHS 08-09-22 09-09-22
4315 NH-39/HW/4133 FDD Checking of EMB 14th layer 142+350 142+500 150 LHS 08-09-22 09-09-22
4316 NH-39/HW/4134 Application of Tack Coat for DBM over Laying 137+500 137+900 400 RHS 09-09-22 10-09-22
4317 NH-39/HW/4135 Checking of DBM over lay laying 137+500 137+900 400 RHS 09-09-22 10-09-22
4318 NH-39/HW/4136 FDD Checking for Wmm 1st 134+640 134+680 40 LHS 09-09-22 10-09-22
4319 NH-39/HW/4137 FDD Checking of EMB 15th layer 142+350 142+500 150 LHS 10-09-22 11-09-22
4322 Application of Prime Coat for DBM Laying (patch work) 96+400 96+420 20 LHS 12-09-22 13-09-22
4323 NH-39/HW/4138 Application of Prime Coat for DBM Laying (patch work) 96+300 96+310 10 LHS 12-09-22 13-09-22
4324 Application of Prime Coat for DBM Laying (patch work) 96+700 96+704 4 LHS 12-09-22 13-09-22
NH-39/HW/4139 Application of Tack Coat for DBM over Laying 96+100 96+410 310 LHS 12-09-22 13-09-22
NH-39/HW/4140 Checking of DBM over lay laying 96+100 96+410 310 LHS 12-09-22 13-09-22
4325 Application of Tack Coat for DBM Laying (patch work) 96+400 96+420 20 LHS 12-09-22 13-09-22
4326 NH-39/HW/4141 Application of Tack Coat for DBM Laying (patch work) 96+300 96+310 10 LHS 12-09-22 13-09-22
Application of Tack Coat for DBM Laying (patch work) 96+700 96+704 4 LHS 12-09-22 13-09-22
Checking of DBM lay laying (patch work) 96+400 96+420 20 LHS 12-09-22 13-09-22
NH-39/HW/4142 Checking of DBM lay laying (patch work) 96+300 96+310 10 LHS 12-09-22 13-09-22
Checking of DBM lay laying (patch work) 96+700 96+704 4 LHS 12-09-22 13-09-22
NH-39/HW/4143 Site Clearance 146+325 146+840 515 RHS 13-09-22 14-09-22
NH-39/HW/4144 Site Clearance 175+345 175+980 635 RHS 13-09-22 14-09-22
NH-39/HW/4145 FDD Checking for Wmm Top Layer 134+640 134+680 40 LHS 13-09-22 14-09-22
NH-39/HW/4146 Application of Tack Coat for DBM over Laying 138+415 138+433 18 RHS 14-09-22 15-09-22
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
4.00
4.00
4
4
4
4
4
4
4
4
Remarks
4
4
4
4
4
Remarks
4
4
4
4
4
4
4
4
4
4
Remarks
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
Tirupati Build-con Pvt. Ltd.Sub-Contractor Highway RFI Authority Engineer
ARY 2022 (HIGHWAY)
Remarks
4
4
4
4
4
4
4
4
4
4
4
4
4
4
Tirupati Build-con Pvt. Ltd.Sub-Contractor Highway RFI Authority Engineer
ARY 2022 (HIGHWAY)
Remarks
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
4
Remarks
4
4
4
4
4
4
4
4
4
4
IPC-3
IPC-3
Remarks
IPC-3
4
4
NOT DONE
Remarks
Remarks
Not
Remarks
NOT DONE
NOT DONE
Remarks
Remarks
NOT DONE
Remarks
NOT DONE
NOT DONE
NOT DONE
NOT DONE
NOT DONE
NOT DONE
NOT DONE
NOT DONE
NOT DONE
Remarks
NOT DONE
NOT DONE
NOT DONE
NOT DONE
NOT DONE
NOT DONE
Remarks
Remarks
6
6
6
6
Remarks
6
6
Remarks
Remarks
6
6
6
6
Remarks
Remarks
Remarks
6
6
6
6
Remarks
6
6
6
6
6
Remarks
Remarks
Remarks
ipc-7
ipc-7
ipc-7
ipc-7
Remarks
Remarks
Remarks
Remarks
Remarks
IPC-7
IPC-7
Remarks
IPC-7
IPC-7
IPC-7
IPC-7
IPC-7
IPC-7
IPC-7
IPC-7
IPC-7
IPC-7
IPC-7
IPC-7
IPC-7
IPC-7
IPC-7
IPC-7
IPC-7
IPC-7
IPC-7
IPC-7
IPC-7
Remarks
IPC-7
IPC-7
IPC-7
IPC-7
IPC-7
IPC-7
IPC-7
IPC-7
IPC-7
IPC-7
IPC-7
IPC-7
IPC-7
IPC-7
IPC-7
IPC-7
IPC-7
IPC-7
IPC-7
IPC-7
Remarks
IPC-7
IPC-7
IPC-7
IPC-7
IPC-7
IPC-7
IPC-7
IPC-7
IPC-7
IPC-7
IPC-7
IPC-7
IPC-7
IPC-7
IPC-7
IPC-7
IPC-7
IPC-7
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
re
re
re
Remarks
Remarks
Remarks
re
Remarks
not done
not done
not done
Remarks
Remarks
Remarks
Remarks
done
3
3
3RD
Remarks
Remarks
not done
Remarks
not done
SPOT RFI
SPOT RFI
UP
UP
Remarks
UP
Remarks
not done
not done
Remarks
not done
Remarks
done
not done
not done
not done
Remarks
not done
not done
not done
done
not done
not done
not done
not done
done
not done
not done
not done
done
done
done
not done
not done
done
done
not done
done
done
done
not done
in progres
not done
not done
not done
not done
not done
not done
not done
not done
not done
not done
done
done
not done
not done
Remarks
not done
not done
not done
not done
not done
not done
not done
not done
not done
not done
not done
not done
not done
not done
not done
not done
not done
not done
not done
done
done
in progres
in progres
not done
not done
done
done
not done
not done
not done
not done
not done
not done
not done
not done
done
done
Remarks
not done
not done
done
done
not done
not done
not done
not done
not done
not done
not done
not done
not done
not done
not done
not done
not done
not done
not done
not done
not done
not done
done
not done
done
not done
done
done
not done
done
done
NOT DONE
done
done
done
done
NOT DONE
NOT DONE
NOT DONE
Remarks
NOT DONE
NOT DONE
NOT DONE
done
done
NOT DONE
NOT DONE
done
done
done
done
done
NOT DONE
NOT DONE
done
NOT DONE
NOT DONE
NOT DONE
NOT DONE
NOT DONE
done
done
done
done
in progres
done
NOT DONE
done
done
in progres
in progres
in progres
in progres
done
NOT DONE
done
done
done
NOT DONE
Remarks
NOT DONE
done
NOT DONE
NOT DONE
in progres
done
previous con.
done
previous con.
done
done
previous con.
done
previous con.
done
previous con.
done
previous con.
done
previous con.
done
done
done
previous con.
in progres
in progres
done
done
done
Done
Done
Done
Done
Done
Remarks
Done
Done
Done
Done
Not done
Not done
Not done
Not done
Done
Done
Done
Done
Done
Done
Done
Done
Done
Done
Not done
Not done
Not done
Not done
Remarks
Not done
Not done
Not done
Done
Done
Not done
Not done
Done
Done
Not done
Not done
Not done
Not done
Done
Done
Not done
Not done
Not done
Not done
Done
Done
Done
Done
Not done
Not Done
Remarks
Done
Remarks
Not Done
Not Done
Remarks
Done
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Remarks
Done
Done
Remarks
Remarks
Remarks
Done
Done
Remarks
Not
Not
Not
Not
Remarks
Sopt
Sopt
Sopt
Remarks
Remarks
Remarks
NOT Done
Remarks
Spot RFI
Spot RFI
Spot RFI
Spot RFI
Remarks
Spot RFI
Spot RFI
Spot RFI
Spot RFI
Spot RFI
Spot RFI
Spot RFI
Spot RFI
Spot RFI
Spot RFI
Remarks
Remarks
Date of Submission :
Details of
S.No RFI NO. Item Description Chainage Side Length Status
Inspection
Remarks
2 NH-39/Lab/02 Sampling&Testing of Duaaree Stone Quarry stone for 3rd Party testing 96+500 LHS 3.0KM DONE 21/Sep/21 12.00PM Complete
3 NH-39/Lab/03 Sampling&Testing of Borrow Area no-01(Selected EMB/SG Soil) 163+500 LHS 1.500KM DONE 9-Oct-21 9.00 AM Complete
4 NH-39/Lab/04 Sampling&Testing of Borrow Area no-02(Selected EMB/SG Soil) 169+500 RHS 1.00KM DONE 22-Oct-21 10.00AM Complete
5 NH-39/Lab/05 Sampling & Testing of Borrow Area no-03(Selected EMB/SG Soil) 169+500 RHS 1.0KM DONE 22-Oct-21 10.30AM Complete
6 NH-39/Lab/06 Sampling & Testing of Borrow Area no-04(Selected EMB/SG Soil) 174+000 LHS 0.500KM DONE 22-Oct-21 2.30PM Complete
7 NH-39/Lab/07 Sampling &Testing of Borrow Area no-05(Selected EMB/SG Soil) 176+000 RHS 0.100KM DONE 22-Oct-21 4.00PM Complete
8 NH-39/Lab/08 Sampling & testing of Borrow Area no-06(Selected EMB/SG Soil) 170+000 LHS 0.100KM DONE 11-Nov-21 11.30AM Complete
9 NH-39/Lab/09 Sampling & testing of Borrow Area no-07(Selected EMB/SG Soil) 161+100 LHS 0.150KM DONE 13-Nov-21 12.30PM Complete
10 NH-39/Lab/10 Sampling & testing of Borrow Area no-08(Selected EMB/SG Soil) 158+900 RHS 0.150KM DONE 13-Nov-21 1.00PM Complete
11 NH-39/Lab/11 Sampling & testing of Borrow Area no-09(Selected EMB/SG Soil) 165+800 LHS 1.5 KM DONE 18-Nov-21 3.00PM Complete
12 NH-39/Lab/12 Sampling & testing of Borrow Area no-08 A(Selected EMB/SG Soil) 158+900 RHS 0.150KM DONE 23-Nov-21 9.00AM
13 NH-39/Lab/13 Sampling & testing of Borrow Area no-10 (Selected EMB/SG Soil) 159+300 RHS 0.5 km 27-Nov-21 10.00AM
14 NH-39/Lab/14 Sampling & testing of Borrow Area no-11 (Selected EMB/SG Soil) 165+800 LHS 1 KM 27-Nov-21 11.00AM
15 NH-39/Lab/15
16 NH-39/Lab/16
17 NH-39/Lab/17
18 NH-39/Lab/18
19 NH-39/Lab/19
20 NH-39/Lab/20
21 NH-39/Lab/21
22 NH-39/Lab/22 Existing Soil Sampling 179+500 182+000 BHS 2.5KM 8-Dec-21 10.30AM
23 NH-39/Lab/23
24 NH-39/Lab/24 Existing Soil Sampling 178+500 179+500 BHS 1000 9-Dec-21 11.00AM
25 NH-39/Lab/25
26 NH-39/Lab/26 Sampling & testing of Borrow Area no-12 (Selected EMB/SG Soil) 159+300 LHS 12-Dec-21 11.30AM
27 NH-39/Lab/27
28 NH-39/Lab/28 Calibration of Hot Mix Plant (DBM) 158+500 RHS 14-Dec-21 10.30AM
29 NH-39/Lab/29 Calibration of Batching Plant (RMC) 158+500 RHS 14-Dec-21 11.30AM
30 NH-39/Lab/30
31 NH-39/Lab/31 Calibration of Batching Plant (RMC) 158+500 RHS 16-Dec-21 12.00PM
32 NH-39/Lab/32
33 NH-39/Lab/33
34 NH-39/Lab/34 Preparation of DBM G-2 mix design 158+500 RHS 18-Dec-21 10.05am
35 NH-39/Lab/35 Preparation of DBM G-1 mix design 158+500 RHS 18-Dec-21 10.50am
36 NH-39/Lab/36 Re-Sampling & testing of Borrow Area no-02 (Selected EMB/SG Soil) 169+500 RHS 18-Dec-21 11.30am
37 NH-39/Lab/37 Re-Sampling & testing of Borrow Area no-06 (Selected EMB/SG Soil) 170+000 LHS 18-Dec-21 12.20pm
38 NH-39/Lab/38
39 NH-39/Lab/39 Preparation of WMM mix design 158+500 RHS 20-Dec-21 9.30AM
40 NH-39/Lab/40
41 NH-39/Lab/41
42 NH-39/Lab/42
43 NH-39/Lab/43 Sampling & testing of Borrow Area no-13(Selected EMB/SG Soil) 158+500 LHS 27-Dec-21 9.00am
44 NH-39/Lab/44 Preparation of concrete mix m-25 design 152+120 RHS 27-Dec-21 9.20am
45 NH-39/Lab/45 Preparation of concrete mix m-30 design 152+120 RHS 27-Dec-21 9.30am
46 NH-39/Lab/46
47 NH-39/Lab/47 Calibration of WMM plant 158+500 RHS 1/Jan/22 9.00am
48 NH-39/Lab/48 Preparation of concrete mix m-35 design 158+500 RHS 1/Jan/22 9.30am
49 NH-39/Lab/49 Preparation of concrete mix m-40 design 158+500 RHS 1/Jan/22 10.00am
52 NH-39/Lab/50 Core Cutting of DBM Over Lay 147300 147800 LHS 500 03-01-22
53 NH-39/Lab/51 Core Cutting of DBM Over Lay 148000 149420 LHS 1,420 03-01-22
55 NH-39/Lab/52 Core Cutting of DBM Over Lay 149710 149740 LHS 30 04-01-22
56 NH-39/Lab/52 Core Cutting of DBM Over Lay 152800 153360 LHS 560 04-01-22
57 NH-39/Lab/52 Core Cutting of DBM Over Lay 153530 153780 LHS 250 04-01-22
58 NH-39/Lab/52 Core Cutting of DBM Over Lay 153880 153970 LHS 90 04-01-22
61 NH-39/Lab/53 NDT test for (MNB) slab A1 & P1 146+938 BHS 10/Jan/22 9.30AM
62 NH-39/Lab/54 NDT test for (MNB) slab A1 & P1 167+454 BHS 10/Jan/22 10.00AM
63 NH-39/Lab/55 NDT test for (ROB) slab A1 & P1 156+958 BHS 10/Jan/22 10.20AM
64 NH-39/Lab/56 Core Cutting of DBM Over Lay 154+480 155+700 LHS 1220 10/Jan/22
65 NH-39/Lab/56 Core Cutting of DBM Over Lay 156+460 156+660 LHS 200 10/Jan/22
65 NH-39/Lab/57 NDT test for (MNB) slab 141+600 LHS 11/Jan/22 3.00PM
66 NH-39/Lab/58 NDT test for (VUP) slab 165+868 BHS 11/Jan/22 4.30PM
67 NH-39/Lab/59 NDT test for (MNB) slab 177+849 BHS 11/Jan/22 5.30PM
68 NH-39/Lab/60 Sampling & testing of Borrow Area no-14(Selected EMB/SG Soil) 113+300 RHS 12/Jan/22 8.00AM
69 NH-39/Lab/61 Sampling & testing of Borrow Area no-15(Selected EMB/SG Soil) 97+600 RHS 12/Jan/22 8.30AM
70 NH-39/Lab/62 NDT test for (ROB-i) Girder 156+958 LHS 12/Jan/22 9.00AM
71 NH-39/Lab/63 NDT test for (ROB-ii) Girder 169+221 RHS 12/Jan/22 10.20AM
72 NH-39/Lab/64 NDT test for (ROB-iii) Girder 178+252 BHS 12/Jan/22 11.20AM
73 NH-39/Lab/65 NDT test for (MNB) Girder 141+600 RHS 12/Jan/22 12.00PM
74 NH-39/Lab/66 NDT test for (MNB) Girder 176+077 BHS 12/Jan/22 12.50PM
75 NH-39/Lab/67 NDT test for (MNB) Girder 182+490 BHS 12/Jan/22 2.10PM
76 NH-39/Lab/68 NDT test for (MJB) Girder 120+740 RHS 12/Jan/22 3.00PM
77 NH-39/Lab/69 NDT test for (MNB) Girder 137+640 RHS 12/Jan/22 3.50PM
78 NH-39/Lab/70 NDT test for (MNB) slab 177+849 BHS 12/Jan/22 4.30PM
80 NH-39/Lab/71 NDT test for (MNB) slab 136+664 BHS 12/Jan/22 5.10PM
82 NH-39/Lab/72 NDT test for (MJB) slab 120+740 BHS 12/Jan/22 5.40PM
83 NH-39/Lab/73 NDT test for (MJB) slab 130+326 LHS 12/Jan/22 6.10pm
84 NH-39/Lab/74 Calibration of WMM plant (Kubri) 94+500 LHS 12/Jan/22 3.00AM
86 NH-39/Lab/75 12/Jan/22
87 NH-39/Lab/76 12/Jan/22
88 NH-39/Lab/77 NDT test for (ROB-i) Girder 156+958 LHS 13/Jan/22 9.00AM
89 NH-39/Lab/78 NDT test for (ROB-ii) Girder 169+221 RHS 13/Jan/22 10.20AM
90 NH-39/Lab/79 NDT test for (MNB) Girder 141+600 RHS 13/Jan/22 11.30am
91 NH-39/Lab/80 NDT test for (MNB) Girder 182+490 BHS 13/Jan/22 12.30pm
92 NH-39/Lab/81 NDT test for (MJB) Girder 120+740 RHS 13/Jan/22 2.10pm
93 NH-39/Lab/82 NDT test for (MNB) Girder 137+640 RHS 13/Jan/22 3.00pm
94 NH-39/Lab/83 NDT test for (MNB) slab 136+664 BHS 13/Jan/22 3.45pm
95 NH-39/Lab/84 NDT test for (MJB) slab 120+740 BHS 13/Jan/22 4.30pm
96 NH-39/Lab/85 NDT test for (MJB) slab 130+326 LHS 13/Jan/22 5.10pm
97 NH-39/Lab/86 13/Jan/22
98 NH-39/Lab/87 13/Jan/22
99 NH-39/Lab/88 13/Jan/22
100 NH-39/Lab/89 NDT test for (MNB) Girder 137+640 RHS 14/Jan/22 9.00AM
101 NH-39/Lab/90 NDT test for (MJB) Girder 120+740 RHS 14/Jan/22 10.20AM
102 NH-39/Lab/91 NDT test for (MJB) Girder 114+443 BHS 14/Jan/22 11.30am
103 NH-39/Lab/92 NDT test for (MNB) Girder 109+162 LHS 14/Jan/22 12.30pm
104 NH-39/Lab/93 NDT test for (MNB) Girder 93+840 RHS 14/Jan/22 2.10pm
105 NH-39/Lab/94 NDT test for (MNB) slab 136+664 BHS 14/Jan/22 3.00pm
106 NH-39/Lab/95 NDT test for (MJB) slab 130+326 LHS 14/Jan/22 3.45pm
107 NH-39/Lab/96 NDT test for (MJB) slab 120+740 BHS 14/Jan/22 4.30pm
108 NH-39/Lab/97 NDT test for (MJB) slab 114+443 BHS 14/Jan/22 5.10pm
109 NH-39/Lab/98 NDT test for (MNB) slab 91+371 RHS 14/Jan/22 5.40PM
110 NH-39/Lab/99 14/Jan/22
111 NH-39/Lab/100 14/Jan/22
112 NH-39/Lab/101 14/Jan/22
113 NH-39/Lab/102 14/Jan/22
114 NH-39/Lab/103 NDT test for (MNB) slab 91+371 RHS 1/15/2022 9.00AM
115 NH-39/Lab/104 NDT test for (MNB) slab 136+664 BHS 1/15/2022 10.20AM
116 NH-39/Lab/105 NDT test for (MNB) Girder 93+845 RHS 1/15/2022 11.30am
117 NH-39/Lab/106 NDT test for (MJB) Girder 109+162 LHS 1/15/2022 12.30pm
118 NH-39/Lab/107 NDT test for (MJB) slab 114+443 BHS 1/15/2022 2.10pm
119 NH-39/Lab/108 NDT test for (MJB) slab 114+443 BHS 1/15/2022 3.00pm
120 NH-39/Lab/109 1/15/2022
121 NH-39/Lab/110 1/15/2022
122 NH-39/Lab/111 93+840 1/15/2022
123 NH-39/Lab/112 1/15/2022
124 NH-39/Lab/113 Core Cutting of DBM Over Lay 157300 157470 LHS 170 16-01-22
125 NH-39/Lab/114 Core Cutting of DBM Over Lay 157660 158320 LHS 660 16-01-22
126 NH-39/Lab/115 Core Cutting of DBM Over Lay 158550 158740 LHS 190 19-01-22
127 NH-39/Lab/115 Core Cutting of DBM Over Lay 158900 159300 LHS 400 19-01-22
128 NH-39/Lab/116 Core Cutting of DBM Over Lay 161250 161550 LHS 300 19-01-22
129 NH-39/Lab/117 Preparation of BC Mix Design 158+500 21/Jan/22 10.00AM
130 NH-39/Lab/118 Core Cutting of DBM Over Lay 148200 149200 RHS 1,000 22-01-22
131 NH-39/Lab/118 Core Cutting of DBM Over Lay 149900 150730 RHS 830 22-01-22
132 NH-39/Lab/119 Preparation of concrete mix m-45 design 158+500 RHS 24/Jan/22 10.00am
133 NH-39/Lab/120 24/Jan/22
134 NH-39/Lab/121 24/Jan/22
135 NH-39/Lab/122 Core Cutting of DBM Over Lay 151740 152880 RHS 1,140 24-01-22
136 NH-39/Lab/123 Core Cutting of DBM Over Lay 153050 153180 RHS 130 24-01-22
137 NH-39/Lab/124 Core Cutting of DBM Over Lay 153864 154780 RHS 916 24-01-22
138 NH-39/Lab/125 Core Cutting of DBM Over Lay 150730 151740 RHS 1,010 24-01-22
139 NH-39/Lab/126
140 NH-39/Lab/127
141 NH-39/Lab/128
142 NH-39/Lab/129 Core Cutting of DBM Over Lay 154+780 155+700 RHS 920 25-01-22
143 NH-39/Lab/130 Core Cutting of DBM Over Lay 156460 156660 RHS 200 25-01-22
144 NH-39/Lab/131
145 NH-39/Lab/132
146 NH-39/Lab/133
147 NH-39/Lab/134
148 NH-39/Lab/135
149 NH-39/Lab/136
150 NH-39/Lab/137
151 NH-39/Lab/138
152 NH-39/Lab/139
153 NH-39/Lab/140
154 NH-39/Lab/141 Core Cutting of DBM Over Lay 157490 157540 RHS 50 27-01-22
155 NH-39/Lab/142 Core Cutting of DBM Over Lay 157660 158740 RHS 1,080 27-01-22
156 NH-39/Lab/143 Core Cutting of DBM Over Lay 158900 160000 RHS 1,100 27-01-22
157 NH-39/Lab/144 28-01-22
158 NH-39/Lab/145 28-01-22
159 NH-39/Lab/146 28-01-22
160 NH-39/Lab/147 28-01-22
161 NH-39/Lab/148
162 NH-39/Lab/149
163 NH-39/Lab/150 Core Cutting of DBM Over Lay 147300 148200 RHS 900 29-01-22
164 NH-39/Lab/151
165 NH-39/Lab/152
166 NH-39/Lab/153
167 NH-39/Lab/154
168 NH-39/Lab/155
169 NH-39/Lab/156
170 NH-39/Lab/157
171 NH-39/Lab/158
172 NH-39/Lab/159
173 NH-39/Lab/160
174 NH-39/Lab/161 Sampling & testing of Borrow Area no-16(Selected EMB/SG Soil) 112200 RHS 31-01-21
175 NH-39/Lab/162 Sampling & testing of Borrow Area no-17(Selected EMB/SG Soil) 109600 RHS 31-01-21
176 NH-39/Lab/163 Preparation of concrete mix design M20 Grade (Kerb) 158200 RHS 31-01-21
177 NH-39/Lab/164
178 NH-39/Lab/165
179 NH-39/Lab/166
180 NH-39/Lab/167
181 NH-39/Lab/168
182 NH-39/Lab/169 Preparation of DLC mix design 158200 RHS 15-02-22
183 NH-39/Lab/170 Preparation of PQC M-40 mix design 158200 RHS 15-02-22
184 NH-39/Lab/171
185 NH-39/Lab/172
186 NH-39/Lab/173
187 NH-39/Lab/174
188 NH-39/Lab/175
189 NH-39/Lab/176
190 NH-39/Lab/177
191 NH-39/Lab/178
192 NH-39/Lab/179
193 NH-39/Lab/180 Joint Sampling of GSB 96000 LHS 03-03-22
194 NH-39/Lab/181
195 NH-39/Lab/182
196 NH-39/Lab/183 Joint Re-Sampling of GSB 96000 LHS 03-03-22
197 NH-39/Lab/184
198 NH-39/Lab/185
199 NH-39/Lab/186
200 NH-39/Lab/187
201 NH-39/Lab/188
202 NH-39/Lab/189
203 NH-39/Lab/190
204 NH-39/Lab/191
205 NH-39/Lab/192 Calibration of RMC Plant 94500 LHS 07-03-22
206 NH-39/Lab/193 Calibration of Hot Mix Plant 94500 LHS 07-03-22
207 NH-39/Lab/194
208 NH-39/Lab/195
209 NH-39/Lab/196
210 NH-39/Lab/197
211 NH-39/Lab/198
212 NH-39/Lab/199
213 NH-39/Lab/200
214 NH-39/Lab/201
215 NH-39/Lab/202
216 NH-39/Lab/203
217 NH-39/Lab/204 Sampling & testing of Borrow Area no-18(Selected EMB/SG Soil) 120100 LHS 26-3-22 12.00pm
218 NH-39/Lab/205 Sampling & testing of Borrow Area no-19(Selected EMB/SG Soil) 121300 RHS 26-3-22 12.30pm
219 NH-39/Lab/206
220 NH-39/Lab/207
221 NH-39/Lab/208
222 NH-39/Lab/209
223 NH-39/Lab/210
224 NH-39/Lab/211
225 NH-39/Lab/212
226 NH-39/Lab/213
227 NH-39/Lab/214 Preparation of WMM mix design 94500 LHS 3/15/2022
228 NH-39/Lab/215 Preparation of Concrete Mix Design M15 Grade 94500 LHS 3/15/2022
229 NH-39/Lab/216 Preparation of Concrete Mix Design M20 Grade 94500 LHS 3/15/2022
230 NH-39/Lab/217 Preparation of Concrete Mix Design M25 Grade 94500 LHS 3/15/2022
231 NH-39/Lab/218 Preparation of Concrete Mix Design M30 Grade 94500 LHS 3/15/2022
232 NH-39/Lab/219
233 NH-39/Lab/220
234 NH-39/Lab/221
235 NH-39/Lab/222
236 NH-39/Lab/223
237 NH-39/Lab/224
238 NH-39/Lab/225
239 NH-39/Lab/226
240 NH-39/Lab/227
241 NH-39/Lab/228
242 NH-39/Lab/229
243 NH-39/Lab/230
244 NH-39/Lab/231
245 NH-39/Lab/232
246 NH-39/Lab/233 Preparation of DBM Mix Design G-1 94+500 LHS 05-04-22 10.00AM
247 NH-39/Lab/234 Preparation of DBM Mix Design G-2 94+500 LHS 05-04-22 10.30AM
248 NH-39/Lab/235 Preparation of BC Mix Design G-2 94+500 LHS 05-04-22 11.00AM
249 NH-39/Lab/236 Sampling & testing of Borrow Area no-20(Selected EMB/SG Soil) 83+500 LHS 05-04-22 12.00PM
250 NH-39/Lab/237
251 NH-39/Lab/238 Core Cutting of DBM Over Lay 169+300 170+030 RHS 14-04-22 IPC-08
252 NH-39/Lab/239
253 NH-39/Lab/240
254 NH-39/Lab/241 Core Cutting of DBM Over Lay 170+030 170+700 RHS 16-04-22 IPC-08
255 NH-39/Lab/242
256 NH-39/Lab/243 Sampling & testing of Borrow Area no-21(Selected EMB/SG Soil) 91+200 LHS 23-04-22 9.00AM
257 NH-39/Lab/244 Preparation of Concrete Mix Design M-35 94+500 LHS 23-04-22 9.30AM
258 NH-39/Lab/245 Preparation of Concrete Mix Design M-40 94+500 LHS 23-04-22 10.00AM
259 NH-39/Lab/246 Preparation of Concrete Mix Design M-45 94+500 LHS 23-04-22 10.30AM
260 NH-39/Lab/247 Core Cutting of DBM Over Lay 169+300 170+010 LHS 24-04-22 IPC-08
261 NH-39/Lab/248 Core Cutting of DBM Over Lay 170+010 170+700 LHS 25-04-22 IPC-08
262 NH-39/Lab/249 26-04-22
263 NH-39/Lab/250 Core Cutting of DBM Over Lay 171+490 172+400 RHS 27-04-22 IPC-08
264 NH-39/Lab/251
265 NH-39/Lab/252
266 NH-39/Lab/253
267 NH-39/Lab/254
268 NH-39/Lab/255
269 NH-39/Lab/256
270 NH-39/Lab/257
271 NH-39/Lab/258
272 NH-39/Lab/259
273 NH-39/Lab/260
274 NH-39/Lab/261
275 NH-39/Lab/262
276 NH-39/Lab/263
277 NH-39/Lab/264
278 NH-39/Lab/265 Preparation of concrete Mix Design M35(pile) 155+800 RHS 01-05-22 9.30am
279 NH-39/Lab/266
280 NH-39/Lab/267
281 NH-39/Lab/268
282 NH-39/Lab/269
283 NH-39/Lab/270
284 NH-39/Lab/271
285 NH-39/Lab/272
286 NH-39/Lab/273
287 NH-39/Lab/274
288 NH-39/Lab/275
289 NH-39/Lab/276
290 NH-39/Lab/277
291 NH-39/Lab/278 Rebound Hammer NDT test of Initially Partially completed existing structure 169+006 LHS 05-05-22 9.00am
VUP
292 NH-39/Lab/279 Rebound Hammer NDT test of Initially Partially completed existing structure 169+221 BHS 05-05-22 9.30AM
ROB
293 NH-39/Lab/280 Sampling & testing of Borrow Area no-22(Selected EMB/SG Soil) 87+200 RHS 05-05-22 10.00AM
294 NH-39/Lab/281
295 NH-39/Lab/282
Tirupati Build-con Pvt. Ltd.Sub-Contractor LN Malviya Infra Projects Ltd Authority Engineer
RFI SUMMARY 2021 (HIGHWAY)
Date of Submission :
Details of
S.No RFI NO. Item Description Chainage Side Length Status
Inspection
Remarks
2 NH-39/Lab/02 Sampling&Testing of Duaaree Stone Quarry stone for 3rd Party testing 96+500 LHS 3.0KM DONE 21/Sep/21 12.00PM Complete
3 NH-39/Lab/03 Sampling&Testing of Borrow Area no-01(Selected EMB/SG Soil) 163+500 LHS 1.500KM DONE 9-Oct-21 9.00 AM Complete
296 NH-39/Lab/283
297 NH-39/Lab/284
298 NH-39/Lab/285
299 NH-39/Lab/286
300 NH-39/Lab/287
301 NH-39/Lab/288
302 NH-39/Lab/289
303 NH-39/Lab/290
304 NH-39/Lab/291
305 NH-39/Lab/292
306 NH-39/Lab/293
307 NH-39/Lab/294
308 NH-39/Lab/295 Sampling & testing of Borrow Area no-23(Selected EMB/SG Soil) 93+000 94+000 RHS 15-05-22 10.00AM
309 NH-39/Lab/296
310 NH-39/Lab/297
311 NH-39/Lab/298
312 NH-39/Lab/299
313 NH-39/Lab/300
314 NH-39/Lab/301
315 NH-39/Lab/302
316 NH-39/Lab/303
317 NH-39/Lab/304
318 NH-39/Lab/305
319 NH-39/Lab/306
320 NH-39/Lab/307 Sampling & testing of Borrow Area no-24(Selected EMB/SG Soil) 94+600 LHS 18-05-22 10.00AM
321 NH-39/Lab/308
322 NH-39/Lab/309
323 NH-39/Lab/310
324 NH-39/Lab/311
325 NH-39/Lab/312 Sampling & testing of Borrow Area no-25(Selected EMB/SG Soil) 106+300 LHS 04-06-22 10.00AM
326 NH-39/Lab/313 Sampling & testing of Borrow Area no-26(Selected EMB/SG Soil) 109+000 RHS 04-06-22 10.30am
327 NH-39/Lab/314 NDT of Partially Complited existing Bridge 95+938 04-06-22
328 NH-39/Lab/315 NDT of Partially Complited existing Bridge 99+750 04-06-22
329 NH-39/Lab/316 NDT of Partially Complited existing Bridge 110+030 04-06-22
330 NH-39/Lab/317 NDT of Partially Complited existing Bridge 112+250 04-06-22
331 NH-39/Lab/318 NDT of Partially Complited existing Bridge 91+371 05-06-22 8.30am
332 NH-39/Lab/319 NDT of Partially Complited existing Bridge 93+846 05-06-22 9.00.
333 NH-39/Lab/320 NDT of Partially Complited existing Bridge 95+938 05-06-22
334 NH-39/Lab/321 NDT of Partially Complited existing Bridge 99+750 05-06-22
335 NH-39/Lab/322 NDT of Partially Complited existing Bridge 110+030 05-06-22
336 NH-39/Lab/323 NDT of Partially Complited existing Bridge 112+250 05-06-22
337 NH-39/Lab/324 NDT of Partially Complited existing Bridge 100+790 05-06-22
338 NH-39/Lab/325 NDT of Partially Complited existing Bridge 106+523 05-06-22
339 NH-39/Lab/326 NDT of Partially Complited existing Bridge 95+938 05-06-22
340 NH-39/Lab/327 NDT of Partially Complited existing Bridge 99+750 06-06-22
341 NH-39/Lab/328 NDT of Partially Complited existing Bridge 110+030 06-06-22
342 NH-39/Lab/329 NDT of Partially Complited existing Bridge 91+371 MNB 06-06-22 8.30am
343 NH-39/Lab/330 NDT of Partially Complited existing Bridge 93+846 MNB 06-06-22 9.00.
344 NH-39/Lab/331 NDT of Partially Complited existing Bridge 95+938 MNB 06-06-22
345 NH-39/Lab/332 NDT of Partially Complited existing Bridge 99+750 MNB 06-06-22
346 NH-39/Lab/333 NDT of Partially Complited existing Bridge 110+030 MNB 06-06-22
347 NH-39/Lab/334 NDT of Partially Complited existing Bridge 112+250 MNB 06-06-22
348 NH-39/Lab/335 NDT of Partially Complited existing Bridge 100+790 MNB 06-06-22
349 NH-39/Lab/336 NDT of Partially Complited existing Bridge 106+523 MNB 06-06-22
350 NH-39/Lab/337 NDT of Partially Complited existing Bridge 106+523 MNB 06-06-22
351 NH-39/Lab/338 NDT of Partially Complited existing Bridge 109+162 MNB 06-06-22
352 NH-39/Lab/339 NDT of Partially Complited existing Bridge 120+740 MNB 06-06-22
353 NH-39/Lab/340 NDT of Partially Complited existing Bridge 137+640 MNB 06-06-22
354 NH-39/Lab/341 NDT of Partially Complited existing Bridge 106+523 MNB 07-06-22
355 NH-39/Lab/342 NDT of Partially Complited existing Bridge 109+162 MNB 07-06-22
356 NH-39/Lab/343 NDT of Partially Complited existing Bridge 120+740 MNB 07-06-22
357 NH-39/Lab/344 NDT of Partially Complited existing Bridge 137+640 MNB 07-06-22
358 NH-39/Lab/345 NDT of Partially Complited existing Bridge 141+600 MNB 07-06-22
359 NH-39/Lab/346 NDT of Partially Complited existing Bridge 164+144 MNB 07-06-22
360 NH-39/Lab/347 NDT of Partially Complited existing Bridge 169+006 MNB 08-06-22
361 NH-39/Lab/348 NDT of Partially Complited existing Bridge 141+600 MNB 08-06-22
362 NH-39/Lab/349 NDT of Partially Complited existing Bridge 164+144 MNB 08-06-22
363 NH-39/Lab/350 NDT of Partially Complited existing Bridge 169+006 MNB 08-06-22
364 NH-39/Lab/351 Calibration of RMC Plant 158+500 08-06-22
365 NH-39/Lab/352 Sampling & testing of Borrow Area no-27 96+400 08-06-22
366 NH-39/Lab/353 Sampling & testing of Borrow Area no-28 114+443 08-06-22
367 NH-39/Lab/354 NDT of Partially Complited existing Bridge 182+492 08-06-22
368 NH-39/Lab/355 Core Cutting of DBM Over Lay 184900 185100 RHS 200 08-06-22
369 NH-39/Lab/356 Core Cutting of DBM Over Lay 184+980 185+205 LHS 225 09-06-22
370 NH-39/Lab/357 NDT of Partially Complited existing Bridge 94+500 LHS 09-06-22
371 NH-39/Lab/358 NDT of Partially Complited existing Bridge 158+500 RHS 09-06-22
372 NH-39/Lab/359 NDT of Partially Complited existing Bridge 178+252 ROB 09-06-22
373 NH-39/Lab/360 NDT of Partially Complited existing Bridge 178+405 VUP 09-06-22
374 NH-39/Lab/361 NDT of Partially Complited existing Bridge 114+443 MJB RHS 09-06-22
375 NH-39/Lab/362 Calibration of RMC Plant 94+500 LHS 9.00AM 10-06-22
376 NH-39/Lab/363 Calibration of RMC Plant 158+500 RHS 9.30AM 10-06-22
377 NH-39/Lab/364 NDT of Partially Complited existing Bridge 178+252 ROB 10.30AM 10-06-22
378 NH-39/Lab/365 NDT of Partially Complited existing Bridge 178+405 VUP 11.00AM 10-06-22
379 NH-39/Lab/366 NDT of Partially Complited existing Bridge ABT 114+443 MJB LHS 10-06-22
380 NH-39/Lab/367 NDT of Partially Complited existing Bridge Pear 114+443 MJB LHS 10-06-22
381 NH-39/Lab/368 NDT of Partially Complited existing Bridge ABT 114+443 MJB RHS 11-06-22
382 NH-39/Lab/369 NDT of Partially Complited existing Bridge Pear 114+443 MJB RHS 11-06-22
383 NH-39/Lab/370 NDT of Partially Complited existing Bridge 169+006 MJB LHS 11-06-22
384 NH-39/Lab/371 NDT of Partially Complited existing Bridge 182+492 MNB 11.00AM 11-06-22
385 NH-39/Lab/372 Core Cutting of DBM Lay 184+510 184+750 LHS 12-06-22
386 NH-39/Lab/373 NDT of Partially Complited existing Bridge 182+492 MNB 11.00AM 13-06-22
387 NH-39/Lab/374 NDT of Partially Complited existing Bridge 144+443 MJB 10.00AM 14-06-22
388 NH-39/Lab/375 NDT of Partially Complited existing Bridge 144+443 MJB 10.00AM 15-06-22
389 NH-39/Lab/376 Sampling & testing of Borrow Area no-27(Selected EMB/SG Soil) 96+400 RHS 16-06-22 10.30am
390 NH-39/Lab/377 Sampling & testing of Borrow Area no-28(Selected EMB/SG Soil) 114+443 LHS 16-06-22
391 NH-39/Lab/378 NDT of Partially Complited existing Bridge 114+443 MJB LHS 16-06-22
392 NH-39/Lab/379 Core Cutting of DBM Lay 184+510 184+750 LHS 240 16-06-22
393 NH-39/Lab/380 Core Cutting of DBM Lay 184+900 184+980 LHS 80 16-06-22
394 NH-39/Lab/381 Core Cutting of Over DBM Lay 184+750 184+900 LHS 150 16-06-22
395 NH-39/Lab/382 NDT of Partially Complited existing Bridge 114+443 LHS MJB 17-06-22
396 NH-39/Lab/383 Preparation of Concrete Mix Design M15 Grade (Ultra tech) 158+500 17-06-22
397 NH-39/Lab/384 Preparation of Concrete Mix Design M20 Grade (Ultra tech) 158+500 17-06-22
398 NH-39/Lab/385 Preparation of Concrete Mix Design M25 Grade (Ultra tech) 158+500 RHS 20-06-22
399 NH-39/Lab/386 Preparation of Concrete Mix Design M30 Grade (Ultra tech) 158+500 RHS 20-06-22
400 NH-39/Lab/387 Preparation of Concrete Mix Design M35 Grade (Ultra tech) 158+500 RHS 20-06-22
401 NH-39/Lab/388 Preparation of Concrete Mix Design M35 Grade (Ultra tech) 158+500 RHS 21-06-22
402 NH-39/Lab/389 Preparation of Concrete Mix Design M40 Grade (Ultra tech) 158+500 RHS 21-06-22
403 NH-39/Lab/390 NDT of Partially Complited existing Bridge 169+221 ROB-II 21-06-22
404 NH-39/Lab/391 Checking of existing soil sampling 140+000 145+000 BHS 21-06-22
405 NH-39/Lab/392 Preparation of Concrete Mix Design M45 Grade (Ultra tech) 158+500 RHS 22-06-22
406 NH-39/Lab/393 NDT of Partially Complited existing Bridge 169+221 ROB-II 22-06-22
407 NH-39/Lab/394 Preparation of DBM Mix Design G-1 94+500 LHS 29-06-22
408 NH-39/Lab/395 Preparation of DBM Mix Design G-2 94+500 LHS 29-06-22
409 NH-39/Lab/396 Core Cutting of DBM Over Lay 172+400 172+550 RHS 22-07-22
410 NH-39/Lab/397 Core Cutting of DBM Over Lay 172+550 173+120 RHS 22-07-22
411 NH-39/Lab/398 Core Cutting of DBM Over Lay 173+120 173+900 RHS 22-07-22
412 NH-39/Lab/399 Core Cutting of DBM Over Lay 173+800 174+100 LHS 22-07-22
413 NH-39/Lab/400 Core Cutting of DBM Over Lay 173+900 174+100 RHS 22-07-22
NH-39/Lab/400A Preparation of GSB Mix Design G-V 158+500 RHS 22-07-22
414 NH-39/Lab/401 Core Cutting of DBM Over Lay 173+100 173+800 LHS 28-07-22 9.00AM
415 NH-39/Lab/402 Core Cutting of DBM Over Lay 172+685 173+100 LHS 28-07-22 9.30AM
416 NH-39/Lab/403 Core Cutting of DBM Over Lay 172+430 172+690 LHS 28-07-22 10.00AM
417 NH-39/Lab/404 Core Cutting of DBM Over Lay 172+180 172+280 LHS 28-07-22 10.30AM
418 NH-39/Lab/405 Core Cutting of DBM Over Lay 171+630 172+180 LHS 28-07-22 11.00AM
419 NH-39/Lab/406 Preparation of GSB Mix Design G-V 96+000 RHS 01-08-22 10.00AM
420 NH-39/Lab/407 Calibration of WMM Plant 94+500 LHS 10.30am
421 NH-39/Lab/408 Core Cutting of DBM Over Lay 175+350 175+900 LHS 9.00AM
422 NH-39/Lab/409 Core Cutting of DBM Over Lay 175+345 175+456 RHS 9.40AM
423 NH-39/Lab/410 Core Cutting of DBM Over Lay 175+481 175+980 RHS 10.30AM
424 NH-39/Lab/411 Core Cutting of DBM Over Lay 93+594 96+615 RHS 06-08-22
425 NH-39/Lab/412 Core Cutting of DBM Over Lay 93+539 93+594 RHS 06-08-22
426 NH-39/Lab/413 Core Cutting of DBM Over Lay 93+465 93+539 RHS 06-08-22
427 NH-39/Lab/414 Core Cutting of DBM Over Lay 93+210 93+465 RHS 06-08-22
428 NH-39/Lab/415 Core Cutting of DBM Over Lay 93+058 93+210 RHS 06-08-22
429 NH-39/Lab/416 Core Cutting of DBM Over Lay 146+325 146+840 RHS 07-08-22
430 NH-39/Lab/417 Core Cutting of DBM Over Lay 146+325 146+840 LHS 07-08-22
431 NH-39/Lab/418 Core Cutting of DBM Over Lay 137+740 138+250 LHS 19-08-22
432 NH-39/Lab/419 Core Cutting of DBM Over Lay 138+250 138+323 LHS 19-08-22
433 NH-39/Lab/420 Core Cutting of DBM Over Lay 138+420 138+642 LHS 19-08-22
434 NH-39/Lab/421
435 NH-39/Lab/422
436 NH-39/Lab/423
437 NH-39/Lab/424
438 NH-39/Lab/425
439 NH-39/Lab/426
440 NH-39/Lab/427
441 NH-39/Lab/428
442 NH-39/Lab/429
443 NH-39/Lab/430
444 NH-39/Lab/431 Core Cutting of DBM Over Lay 93+003 93+058 RHS 20-08-22
445 NH-39/Lab/432 Core Cutting of DBM Over Lay 92+935 93+003 RHS 20-08-22
446 NH-39/Lab/433 Core Cutting of DBM Over Lay 92+633 92+935 RHS 20-08-22
447 NH-39/Lab/434 Core Cutting of DBM Over Lay 91+470 92+200 RHS 20-08-22
448 NH-39/Lab/435 Core Cutting of DBM Over Lay 138+642 139+255 LHS 24-08-22
449 NH-39/Lab/436 Core Cutting of DBM Over Lay 139+255 139+950 LHS 24-08-22
450 NH-39/Lab/437 Core Cutting of DBM Over Lay 96+100 96+480 RHS 25-08-22
451 NH-39/Lab/438 Core Cutting of DBM Over Lay 96+490 96+675 RHS 25-08-22
452 NH-39/Lab/439 Core Cutting of DBM Over Lay 96+675 96+918 RHS 26-08-22
453 NH-39/Lab/440 Core Cutting of DBM Over Lay 139+965 140+630 LHS 27-08-22
454 NH-39/Lab/441 Core Cutting of DBM Over Lay 139+860 140+600 RHS 28-08-22
455 NH-39/Lab/442 Core Cutting of DBM Over Lay 139+135 139+860 RHS 28-08-22
456 NH-39/Lab/443
457 NH-39/Lab/444
458 NH-39/Lab/445
459 NH-39/Lab/446
460 NH-39/Lab/447
461 NH-39/Lab/448
462 NH-39/Lab/449
463 NH-39/Lab/450 NDt Test For MJB P7-P8 114+443 LHS 15-09-22
464 NH-39/Lab/451 NDt Test For MJB P7-P8 114+443 LHS 18-09-22
465 NH-39/Lab/452
466 NH-39/Lab/453 Core Cutting of DBM Over Lay 138+500 19+135 RHS 20-09-22
467 NH-39/Lab/454 Core Cutting of DBM Over Lay 138+050 138+500 RHS 20-09-22
468 NH-39/Lab/455 Core Cutting of DBM Over Lay 137+740 138+050 RHS 20-09-22
469 NH-39/Lab/456 Core Cutting of DBM Over Lay 137+080 137+540 LHS 20-09-22
NH-39/Lab/457 20-09-22
NH-39/Lab/458 Core Cutting of DBM Over Lay 138+540 139+135 RHS 26-09-22
NH-39/Lab/459 Core Cutting of DBM Over Lay 138+050 138+540 RHS 26-09-22
NH-39/Lab/460 Core Cutting of DBM Over Lay 137+080 137+540 LHS 26-09-22
NH-39/Lab/461 Core Cutting of DBM Over Lay 136+920 136+950 LHS 26-09-22
NH-39/Lab/462 Core Cutting of DBM Over Lay 136+664 136+854 LHS 26-09-22
NH-39/Lab/463 Core Cutting of DBM Over Lay 136+250 136+664 LHS 26-09-22
NH-39/Lab/464 Core Cutting of DBM Over Lay 135+750 136+250 LHS 26-09-22
NH-39/Lab/465 Core Cutting of DBM Over Lay 135+550 135+750 LHS 26-09-22
NH-39/Lab/466 26-09-22
NH-39/Lab/467 26-09-22
NH-39/Lab/468 Core Cutting of DBM Over Lay 135+080 135+550 LHS 27-09-22
NH-39/Lab/469 27-09-22
Tirupati Build-con Pvt. Ltd.Sub-Contractor LN Malviya Infra Projects Ltd Authority Engineer
Balance work for Rehabilitation and up-gradation of Sidhi-Singrouli from km 82.400 to km 187.993 section of new NH-39 (Old NH-75E)(Design
Name of Project Length 105.593 km to four lane with paved shoulders on through Engineering, Procurement & Construction (EPC) mode under NH (O) in the
state of Madhya Pradesh.
Date of Submission :
S.No RFI NO. Item Description Details of Inspection Chainage Side Length Status Remarks
Date Time From To
1 NH-39/Survey/01 TBM Checking Fixing 23-Nov-21 8.00AM 178+000 181+000 BHS 3000
2 NH-39/Survey/02 TBM Checking Fixing 24-Nov-21 9.45AM 155+400 158+900 BHS 3500
4 NH-39/Survey/03 Checking of Center Line Marking 25-Nov-21 10.00AM 155+000 160+000 BHS 5000
5 NH-39/Survey/04 Checking of Center Line Marking 26-Nov-21 10.30AM 178+000 181+000 BHS 3000
7 NH-39/Survey/05
8 NH-39/Survey/06
10 NH-39/Survey/07 TBM Checking Fixing 28-Nov-21 11.30AM 165+000 168+400 BHS 3400
11 NH-39/Survey/08
13 NH-39/Survey/09 TBM Checking Fixing 1-Dec-21 171+500 179+000 BHS 7500
14 NH-39/Survey/10 TBM Checking Fixing 4-Dec-21 179+400 183+500 BHS 4100
16 NH-39/Survey/11
17 NH-39/Survey/12
19 NH-39/Survey/13 TBM Checking Fixing 6-Dec-21 171+200 173+700 BHS 2500
20 NH-39/Survey/14
22 NH-39/Survey/15
23 NH-39/Survey/16 TBM Checking & Fixing 7-Dec-21 173+700 176+450 BHS 2750
25 NH-39/Survey/17
26 NH-39/Survey/18
28 NH-39/Survey/19
29 NH-39/Survey/20 TBM Checking & Fixing 10-Dec-21 176+450 178+450 BHS 2000
31 NH-39/Survey/21
32 NH-39/Survey/22 TBM Checking & Fixing 12-Dec-21 178+450 185+000 BHS 6550
34 NH-39/Survey/23
35 NH-39/Survey/24 TBM Checking & Fixing 13-Dec-21 158+000 165+000 BHS 7000
37 NH-39/Survey/25
38 NH-39/Survey/26 TBM Checking & Fixing 15-Dec-21 151+000 155+000 BHS 4000
40 NH-39/Survey/27
41 NH-39/Survey/28 TBM Checking & Fixing 16-Dec-21 149+000 151+000 BHS 2000
Date of Submission :
S.No RFI NO. Item Description Details of Inspection Chainage Side Length Status Remarks
Date Time From To
1 NH-39/Survey/01 TBM Checking Fixing 23-Nov-21 8.00AM 178+000 181+000 BHS 3000
2 NH-39/Survey/02 TBM Checking Fixing 24-Nov-21 9.45AM 155+400 158+900 BHS 3500
43 NH-39/Survey/29
44 NH-39/Survey/30 TBM Checking 21-12-21 11.30am 145000 149000 BHS 4000
S.No RFI NO. Item Description Chainage Length Side NOS Width Height Qty Unit Details of Inspection
From To Date Time
1 NH-39/STR/01 Curtain Wall Filter midia laying & Stone pitching 162+367 LHS 27/12/21 09.30 AM
2 NH-39/STR/02 Curtain Wall Filter midia laying & Stone pitching 162+367 RHS 27/12/21 09.45 AM
3 NH-39/STR/03 Curtain Wall Filter midia laying & Stone pitching 165+794 LHS 27/12/21 10.00AM
4 NH-39/STR/04 Curtain Wall Filter midia laying & Stone pitching 165+794 RHS 27/12/21 10.30AM
5 NH-39/STR/05 Curtain Wall Filter midia laying & Stone pitching 154+222 U/S 27/12/21 11.00AM
6 NH-39/STR/06 Curtain Wall Filter midia laying & Stone pitching 154+222 D/S 27/12/21 11.30AM
7 NH-39/STR/07 Curtain Wall Filter midia laying & Stone pitching 155+064 LHS 27/12/21 12.00PM
8 NH-39/STR/08 Curtain Wall Filter midia laying & Stone pitching 155+064 RHS 27/12/21 12.30PM
9 NH-39/STR/09 Curtain Wall Filter midia laying & Stone pitching 162+800 LHS 27/12/21 1.00PM
10 NH-39/STR/10 Curtain Wall Filter midia laying & Stone pitching 162+800 RHS 27/12/21 2.00PM
11 NH-39/STR/11 Curtain Wall Filter midia laying & Stone pitching 158+822 LHS 22/12/21 09.30 AM
12 NH-39/STR/12 Curtain Wall Filter midia laying & Stone pitching 158+822 RHS 22/12/21 09.45 AM
13 NH-39/STR/13 Curtain Wall Filter midia laying & Stone pitching 159+322 LHS 22/12/21 10.00AM
14 NH-39/STR/14 Curtain Wall Filter midia laying & Stone pitching 159+322 RHS 22/12/21 10.30AM
15 NH-39/STR/15 Curtain Wall Filter midia laying & Stone pitching 159+854 LHS 22/12/21 11.00AM
16 NH-39/STR/16 Curtain Wall Filter midia laying & Stone pitching 159+854 RHS 22/12/21 11.30AM
17 NH-39/STR/17 Curtain Wall Filter midia laying & Stone pitching 162+826 LHS 22/12/21 12.00PM
18 NH-39/STR/18 Curtain Wall Filter midia laying & Stone pitching 162+826 RHS 22/12/21 12.30PM
19 NH-39/STR/19 Curtain Wall Filter midia laying & Stone pitching 161+577 LHS 22/12/21 1.00PM
20 NH-39/STR/20 Curtain Wall Filter midia laying & Stone pitching 161+577 RHS 22/12/21 2.00PM
21 NH-39/STR/21 Curtain Wall Filter midia laying & Stone pitching 157+453 LHS 17/12/21 11.30AM
22 NH-39/STR/22 Curtain Wall Filter midia laying & Stone pitching 157+453 RHS 17/12/21 12.00PM
23 NH-39/STR/23 Curtain Wall Filter midia laying & Stone pitching 158+855 LHS 17/12/21 12.30PM
24 NH-39/STR/24 Curtain Wall Filter midia laying & Stone pitching 158+855 RHS 17/12/21 1.00PM
25 NH-39/STR/25 Curtain Wall Filter midia laying & Stone pitching 158+145 LHS 17/12/21 2.00PM
26 NH-39/STR/26 Curtain Wall Filter midia laying & Stone pitching 158+145 RHS 17/12/21 10.45AM
27 NH-39/STR/27 Curtain Wall Filter midia laying & Stone pitching 158+340 LHS 17/12/21 3.00 PM
28 NH-39/STR/28 Curtain Wall Filter midia laying & Stone pitching 158+340 RHS 17/12/21 3.30PM
29 NH-39/STR/45 Toe Wall Layout & excavation 156+650 156+850 RHS 10/12/21 09.30 AM
30 NH-39/STR/46 Toe Wall Layout & excavation 156+770 156+870 LHS 10/12/21 09.45 AM
31 NH-39/STR/47 Toe Wall Layout & excavation 157+020 157+170 RHS 10/12/21 10.00AM
32 NH-39/STR/48 Toe Wall Bed PCC 156+650 156+850 200 RHS 1.150 0.150 34.50 Cum 11/12/21 09.30 AM
33 NH-39/STR/49 Toe Wall Bed PCC 156+770 156+870 100 LHS 1.150 0.150 17.25 Cum 11/12/21 09.45 AM
34 NH-39/STR/50 Toe Wall Bed PCC 157+020 157+170 150 RHS 1.150 0.150 25.88 Cum 11/12/21 10.00AM
35 NH-39/STR/51 Toe Wall Layout & excavation 169+300 169+481 LHS 12/11/2021
10.45AM
36 NH-39/STR/52 Toe Wall Layout & excavation 169+300 169+418 RHS 12/11/2021
11.30AM
37 NH-39/STR/53 Toe Wall Raft 156+650 156+850 200 RHS 12/12/2021
1 0.4 80 Cum 09.00AM
38 NH-39/STR/54 Toe Wall Raft 156+770 156+870 100 LHS 12/12/2021
1 0.4 40 Cum 09.30 AM
39 NH-39/STR/55 Toe Wall Raft 157+020 157+170 150 RHS 12/12/2021
1 0.4 60 Cum 10.00AM
40 NH-39/STR/56 Toe Wall Bed PCC 169+300 169+500 200 LHS 12/12/2021
1.15 0.15 34.5 Cum 10.30AM
41 NH-39/STR/57 Toe Wall Bed PCC 169+300 169+425 125 RHS 12/12/2021
1.15 0.15 21.5625 Cum 11.00AM
42 NH-39/STR/58 Layout checking and excavation of Box Culvert Curtain Wall 157+600 D/S 12/12/2021
11.30AM
43 NH-39/STR/59 Layout checking and excavation of Box Culvert Curtain Wall 157+600 U/S 12/12/2021
12.00PM
44 NH-39/STR/60 Layout checking and excavation of Box Culvert Curtain Wall 158+145 D/S 12/12/2021
12.30PM
45 NH-39/STR/61 Layout checking and excavation of Box Culvert Curtain Wall 158+145 U/S 12/12/2021
1.00PM
46 NH-39/STR/62 Layout checking and excavation of Box Culvert Curtain Wall 159+322 D/S 12/12/2021
1.30PM
47 NH-39/STR/63 Layout checking and excavation of Box Culvert Curtain Wall 159+322 U/S 12/12/2021
2.0PM
RFI SUMMARY (STRUCTURE)
S.No RFI NO. Item Description Chainage Length Side NOS Width Height Qty Unit Details of Inspection
From To Date Time
48 NH-39/STR/64 Layout checking and excavation of Box Culvert Curtain Wall 159+854 D/S 12/12/2021
2.30PM
49 NH-39/STR/65 Layout checking and excavation of Box Culvert Curtain Wall 159+854 U/S 12/12/2021
3.00PM
50 NH-39/STR/66 Toe Wall Wall Casting 156+650 156+850 200 RHS 12/13/2021
0.45 1 0.45 Cum 9.00AM
51 NH-39/STR/67 Toe Wall Wall Casting 156+770 156+870 100 LHS 12/13/2021
0.45 1 0.45 Cum 09.30 AM
52 NH-39/STR/68 Toe Wall Wall Casting 157+020 157+170 150 RHS 12/13/2021
0.45 1 0.45 Cum 09.45 AM
53 NH-39/STR/69 Toe Wall Raft 169+300 169+500 200 LHS 12/13/2021
1 0.4 80 Cum 10.00AM
54 NH-39/STR/70 Toe Wall Raft 169+300 169+425 125 RHS 12/13/2021
1 0.4 50 Cum 10.30AM
55 NH-39/STR/71 Curtain wall Bed Pcc 158+855 14 D/S 12/13/2021
1.3 0.1 0.13 Cum 11.00AM
56 NH-39/STR/72 Curtain wall Bed Pcc 158+855 14 U/S 12/13/2021
1.3 0.1 0.13 Cum 11.30AM
57 NH-39/STR/73 Curtain wall Bed Pcc 158+145 10 D/S 12/13/2021
1.3 0.1 0.13 Cum 12.00PM
58 NH-39/STR/74 Curtain wall Bed Pcc 158+145 10 U/S 12/13/2021
1.3 0.1 0.13 Cum 12.30PM
59 NH-39/STR/75 Curtain wall Bed Pcc 159+322 11 D/S 12/13/2021
1.3 0.1 0.13 Cum 1.00PM
60 NH-39/STR/76 Curtain wall Bed Pcc 159+322 11 U/S 12/13/2021
1.3 0.1 0.13 Cum 2.00PM
61 NH-39/STR/77 Curtain wall Bed Pcc 159+854 11 D/S 12/13/2021
1.3 0.1 0.13 Cum 2.30PM
62 NH-39/STR/78 Curtain wall Bed Pcc 159+854 11 U/S 12/13/2021
1.3 0.1 0.13 Cum 3.00PM
63 NH-39/STR/79 Toe Wall Wall Casting 169+300 169+481 181 LHS 12/14/2021
0.45 1 0.45 Cum 09.30 AM
64 NH-39/STR/80 Toe Wall Wall Casting 169+300 169+500 200 RHS 12/14/2021
0.45 1 0.45 Cum 09.45 AM
65 NH-39/STR/81 Curtain Wall First Lift 158+855 14 D/S 12/14/2021
1.2 0.6 0.72 Cum 10.00AM
66 NH-39/STR/82 Curtain Wall First Lift 158+855 14 U/S 12/14/2021
1.2 0.6 0.72 Cum 10.30AM
67 NH-39/STR/83 Curtain Wall First Lift 158+145 10 D/S 12/14/2021
1.2 0.6 0.72 Cum 11.00AM
68 NH-39/STR/84 Curtain Wall First Lift 158+145 10 U/S 12/14/2021
1.2 0.6 0.72 Cum 11.30AM
69 NH-39/STR/85 Curtain Wall First Lift 159+322 11 D/S 12/14/2021
1.2 0.6 0.72 Cum 12.00PM
70 NH-39/STR/86 Curtain Wall First Lift 159+322 11 U/S 12/14/2021
1.2 0.6 0.72 Cum 12.30PM
71 NH-39/STR/87 Curtain Wall First Lift 159+854 11 D/S 12/14/2021
1.2 0.6 0.72 Cum 1.00PM
72 NH-39/STR/88 Curtain Wall First Lift 159+854 11 U/S 12/14/2021
1.2 0.6 0.72 Cum 2.00PM
73 NH-39/STR/89 Toe Wall Filter Midia 156+650 156+850 RHS 12/15/2021
09.30 AM
74 NH-39/STR/90 Toe Wall Filter Midia 156+770 156+870 LHS 12/15/2021
09.45 AM
75 NH-39/STR/91 Toe Wall Filter Midia 157+020 157+170 RHS 12/15/2021
10.00AM
76 NH-39/STR/92 Toe Wall Wall Casting 169+300 169+500 200 LHS 12/15/2021
0.45 1 0.45 Cum 10.30AM
77 NH-39/STR/93 Toe Wall Wall Casting 169+300 169+425 125 RHS 12/15/2021
0.45 1 0.45 Cum 11.00AM
78 NH-39/STR/94 Curtain Wall 2nd Lift 158+855 14 D/S 12/15/2021
0.825 1 0.825 Cum 11.30AM
79 NH-39/STR/95 Curtain Wall 2nd Lift 158+855 14 U/S 12/15/2021
0.825 1 0.825 Cum 12.00PM
80 NH-39/STR/96 Curtain Wall 2nd Lift 158+145 10 D/S 12/15/2021
0.825 1 0.825 Cum 12.30PM
81 NH-39/STR/97 Curtain Wall 2nd Lift 158+145 10 U/S 12/15/2021
0.825 1 0.825 Cum 1.00PM
82 NH-39/STR/98 Curtain Wall 2nd Lift 159+322 11 D/S 12/15/2021
0.825 1 0.825 Cum 2.00PM
83 NH-39/STR/99 Curtain Wall 2nd Lift 159+322 11 U/S 12/15/2021
0.825 1 0.825 Cum 10.45AM
84 NH-39/STR/100 Curtain Wall 2nd Lift 159+854 11 D/S 12/15/2021
0.825 1 0.825 Cum 3.00 PM
RFI SUMMARY (STRUCTURE)
S.No RFI NO. Item Description Chainage Length Side NOS Width Height Qty Unit Details of Inspection
From To Date Time
S.No RFI NO. Item Description Chainage Length Side NOS Width Height Qty Unit Details of Inspection
From To Date Time
S.No RFI NO. Item Description Chainage Length Side NOS Width Height Qty Unit Details of Inspection
From To Date Time
159 NH-39/STR/175 Layout checking and excavation of Box Culvert Curtain Wall 153+829 U/S 12/22/2021
1.00PM
160 NH-39/STR/176 Layout checking and excavation of Box Culvert Curtain Wall 153+829 D/S 12/22/2021
2.00PM
161 NH-39/STR/177 Curtain Wall Bed Pcc 160+826 11 U/S 12/23/2021
1.3 0.1 0.13 Cum 09.30 AM
162 NH-39/STR/178 Curtain Wall Bed Pcc 160+826 11 D/S 12/23/2021
1.3 0.1 0.13 Cum 09.45 AM
163 NH-39/STR/179 Curtain Wall Bed Pcc 161+577 14 U/S 12/23/2021
1.3 0.1 0.13 Cum 10.00AM
164 NH-39/STR/180 Curtain Wall Bed Pcc 161+577 14 D/S 12/23/2021
1.3 0.1 0.13 Cum 10.30AM
165 NH-39/STR/181 Curtain Wall Bed Pcc 165+794 14 U/S 12/23/2021
1.3 0.1 0.13 Cum 11.00AM
166 NH-39/STR/182 Curtain Wall Bed Pcc 165+794 14 D/S 12/23/2021
1.3 0.1 0.13 Cum 11.30AM
167 NH-39/STR/183 Curtain Wall Bed Pcc 155+064 13 U/S 12/23/2021
1.3 0.1 0.13 Cum 12.00PM
168 NH-39/STR/184 Curtain Wall Bed Pcc 155+064 13 D/S 12/23/2021
1.3 0.1 0.13 Cum 12.30PM
169 NH-39/STR/185 Curtain Wall Bed Pcc 153+829 13 U/S 12/23/2021
1.3 0.1 0.13 Cum 1.00PM
170 NH-39/STR/186 Curtain Wall Bed Pcc 153+829 13 D/S 12/23/2021
1.3 0.1 0.13 Cum 2.00PM
171 NH-39/STR/187 Curtain Wall First Lift 160+826 11 U/S 12/24/2021
1.2 0.6 0.72 Cum 09.30 AM
172 NH-39/STR/188 Curtain Wall First Lift 160+826 11 D/S 12/24/2021
1.2 0.6 0.72 Cum 09.45 AM
173 NH-39/STR/189 Curtain Wall First Lift 161+577 14 U/S 12/24/2021
1.2 0.6 0.72 Cum 10.00AM
174 NH-39/STR/190 Curtain Wall First Lift 161+577 14 D/S 12/24/2021
1.2 0.6 0.72 Cum 10.30AM
175 NH-39/STR/191 Curtain Wall First Lift 165+794 14 U/S 12/24/2021
1.2 0.6 0.72 Cum 11.00AM
176 NH-39/STR/192 Curtain Wall First Lift 165+794 14 D/S 12/24/2021
1.2 0.6 0.72 Cum 11.30AM
177 NH-39/STR/193 Curtain Wall First Lift 155+064 13 U/S 12/24/2021
1.2 0.6 0.72 Cum 12.00PM
178 NH-39/STR/194 Curtain Wall First Lift 155+064 13 D/S 12/24/2021
1.2 0.6 0.72 Cum 12.30PM
179 NH-39/STR/195 Curtain Wall First Lift 153+829 13 U/S 12/24/2021
1.2 0.6 0.72 Cum 1.00PM
180 NH-39/STR/196 Curtain Wall First Lift 153+829 13 D/S 12/24/2021
1.2 0.6 0.72 Cum 2.00PM
181 NH-39/STR/197 Curtain Wall 2nd Lift 160+826 11 U/S 12/25/2021
0.825 1 0.825 Cum 09.30 AM
182 NH-39/STR/198 Curtain Wall 2nd Lift 160+826 11 D/S 12/25/2021
0.825 1 0.825 Cum 09.45 AM
183 NH-39/STR/199 Curtain Wall 2nd Lift 161+577 14 U/S 12/25/2021
0.825 1 0.825 Cum 10.00AM
184 NH-39/STR/200 Curtain Wall 2nd Lift 161+577 14 D/S 12/25/2021
0.825 1 0.825 Cum 10.30AM
185 NH-39/STR/201 Curtain Wall 2nd Lift 165+794 14 U/S 12/25/2021
0.825 1 0.825 Cum 11.00AM
186 NH-39/STR/202 Curtain Wall 2nd Lift 165+794 14 D/S 12/25/2021
0.825 1 0.825 Cum 11.30AM
187 NH-39/STR/203 Curtain Wall 2nd Lift 155+064 13 U/S 12/25/2021
0.825 1 0.825 Cum 12.00PM
188 NH-39/STR/204 Curtain Wall 2nd Lift 155+064 13 D/S 12/25/2021
0.825 1 0.825 Cum 12.30PM
189 NH-39/STR/205 Curtain Wall 2nd Lift 153+829 13 U/S 12/25/2021
0.825 1 0.825 Cum 1.00PM
190 NH-39/STR/206 Curtain Wall 2nd Lift 153+829 13 D/S 12/25/2021
0.825 1 0.825 Cum 2.00PM
191 NH-39/STR/207 Curtain Wall Final Lift 160+826 11 U/S 12/26/2021
0.675 0.9 0.6075 Cum 09.30 AM
192 NH-39/STR/208 Curtain Wall Final Lift 160+826 11 D/S 12/26/2021
0.675 0.4 0.27 Cum 09.45 AM
193 NH-39/STR/209 Curtain Wall Final Lift 161+577 14 U/S 12/26/2021
0.675 0.9 0.6075 Cum 10.00AM
194 NH-39/STR/210 Curtain Wall Final Lift 161+577 14 D/S 12/26/2021
0.675 0.4 0.27 Cum 10.30AM
195 NH-39/STR/211 Curtain Wall Final Lift 165+794 14 U/S 12/26/2021
0.675 0.4 0.27 Cum 11.00AM
RFI SUMMARY (STRUCTURE)
S.No RFI NO. Item Description Chainage Length Side NOS Width Height Qty Unit Details of Inspection
From To Date Time
203 NH-39/STR/219 Foundation Bed PCC MNB for Service road section MNB 155+800 RHS 1/2/2022
204 NH-39/STR/220 Foundation Bed PCC MNB for MCW MNB 155+800 RHS 1/2/2022
207 NH-39/STR/223 Reinforcement Checking for Service road portion MNB 155+800 RHS 1/3/2022
208 NH-39/STR/224 Shuttering Checcking & Concrete pourring for Raft Service road portion MNB 155+800 RHS 1/3/2022
209 NH-39/STR/225 Reinforcement Checking for MCW MNB 155+800 RHS 1/3/2022
210 NH-39/STR/226 Shuttering Checcking & Concrete pourring for Raft MCW MNB 155+800 RHS 1/3/2022
211 NH-39/STR/227 Toe Wall Layout & excavation 156+650 156+940 LHS 1/4/2022
Cum
212 NH-39/STR/228 Toe Wall Layout & excavation 156+940 157+280 LHS 1/4/2022
Cum
213 NH-39/STR/229 Reinforcement Checking for MCW MNB 155+800 RHS 1/4/2022
214 NH-39/STR/230 Shuttering Checcking & Concrete pourring for Raft MCW MNB 155+800 RHS 1/4/2022
216 NH-39/STR/232 Toe Wall Layout & excavation 162+950 163+250 LHS 1/5/2022
Cum
217 NH-39/STR/233 Toe Wall Layout & excavation 163+250 163+510 LHS 1/5/2022
Cum
218 NH-39/STR/234 1/5/2022
220 NH-39/STR/236 Toe Wall Bed PCC 156+650 156+940 290 LHS 1/6/2022
1.15 0.15 50.025 Cum
221 NH-39/STR/237 Toe Wall Bed PCC 156+940 157+280 340 LHS 1/6/2022
1.15 0.15 58.65 Cum
222 NH-39/STR/238 Reinforcement Checking for MCW MNB 155+800 RHS 1/6/2022
223 NH-39/STR/239 Shuttering Checcking & Concrete pourring for Raft MCW MNB 155+800 RHS 1/6/2022
224 NH-39/STR/240 Toe Wall Layout & excavation 156+850 157+020 RHS 1/8/2022
Cum
225 NH-39/STR/241 Toe Wall Layout & excavation 157+170 157+280 RHS 1/8/2022
Cum
226 NH-39/STR/242 1/8/2022
228 NH-39/STR/244 Toe Wall Bed PCC 162+950 163+250 300 LHS 1/9/2022
1.15 0.15 51.75 Cum
229 NH-39/STR/245 Toe Wall Bed PCC 163+250 163+510 260 LHS 1/9/2022
1.15 0.15 44.85 Cum
230 NH-39/STR/246 Curtain wall Excavation Box Culvert 154+031 10 D/S 1/9/2022
1.3 0.1 0.13 Cum
231 NH-39/STR/247 1/9/2022
S.No RFI NO. Item Description Chainage Length Side NOS Width Height Qty Unit Details of Inspection
From To Date Time
233 NH-39/STR/249 Toe Wall Layout & excavation 162+950 163+250 RHS 1/10/2022
Cum
234 NH-39/STR/250 Toe Wall Layout & excavation 163+250 163+510 RHS 1/10/2022
Cum
235 NH-39/STR/251 Toe Wall Layout & excavation 169+425 169+530 RHS 1/10/2022
Cum
236 NH-39/STR/252 Curtain wall Excavation Box Culvert 154+031 10 U/S 1/10/2022
1.3 0.1 0.13 Cum
237 NH-39/STR/253 Curtain wall Excavation Box Culvert 154+222 14 U/S 1/10/2022
1.3 0.1 0.13 Cum
238 NH-39/STR/254 Curtain wall Excavation Box Culvert 154+623 10 U/S 1/10/2022
1.3 0.1 0.13 Cum
239 NH-39/STR/255 1/10/2022
240 NH-39/STR/256 Reinforcement Checking for MCW MNB 155+800 RHS 1/10/2022
241 NH-39/STR/257 Shuttering Checcking & Concrete pourring for Raft MCW MNB 155+800 RHS 1/10/2022
243 NH-39/STR/259 Toe Wall Raft 156+650 156+940 290 LHS 1/11/2022
1 0.4 116 Cum
244 NH-39/STR/260 Toe Wall Raft 156+940 157+280 340 LHS 1/11/2022
1 0.4 136 Cum
245 NH-39/STR/261 Curtain wall Excavation Box Culvert 154+222 14 D/S 1/11/2022
1.3 0.1 0.13 Cum
246 NH-39/STR/262 Curtain wall Bed Pcc Box Culvert 154+031 10 D/S 1/11/2022
1.3 0.1 0.13 Cum
247 NH-39/STR/263 Excavation of MNB for Service road section MNB 155+800 LHS 1/11/2022
249 NH-39/STR/265 Toe Wall Bed PCC 156+850 157+020 170 RHS 1/12/2022
1.15 0.15 29.325 Cum
250 NH-39/STR/266 Toe Wall Bed PCC 157+170 157+280 110 RHS 1/12/2022
1.15 0.15 18.975 Cum
251 NH-39/STR/267 Excavation of MNB for Service road section MNB 156+156 LHS 1/12/2022
Cum
252 NH-39/STR/268 Foundation Bed PCC MNB for Service road section MNB 155+800 LHS 1/12/2022
254 NH-39/STR/270 Toe Wall Wall Casting 156+650 156+940 290 LHS 1/13/2022
0.45 1 0.45 Cum
255 NH-39/STR/271 Toe Wall Wall Casting 156+940 157+280 340 LHS 1/13/2022
0.45 1 0.45 Cum
256 NH-39/STR/272 Curtain wall Excavation Box Culvert 154+623 10 D/S 1/13/2022
1.3 0.1 0.13 Cum
257 NH-39/STR/273 Curtain wall Bed Pcc Box Culvert 154+222 14 D/S 1/13/2022
1.3 0.1 0.13 Cum
258 NH-39/STR/274 Curtain wall Excavation Box Culvert 154+770 11 U/S 1/13/2022
1.3 0.1 0.13 Cum
259 NH-39/STR/275 Curtain wall Excavation Box Culvert 155+277 11 U/S 1/13/2022
1.3 0.1 0.13 Cum
260 NH-39/STR/276 Curtain wall 1st lift Box Culvert 154+031 10 D/S 1/13/2022
1.2 0.6 0.72 Cum
261 NH-39/STR/277 1/13/2022
263 NH-39/STR/279 Toe Wall Bed PCC 162+950 163+250 300 RHS 1/14/2022
1.15 0.15 51.75 Cum
264 NH-39/STR/280 Toe Wall Bed PCC 163+250 163+510 260 RHS 1/14/2022
1.15 0.15 44.85 Cum
265 NH-39/STR/281 Toe Wall Bed PCC 169+425 169+530 105 RHS 1/14/2022
1.15 0.15 18.1125 Cum
266 NH-39/STR/282 Toe Wall Raft 162+950 163+250 300 LHS 1/14/2022
1 0.4 120 Cum
267 NH-39/STR/283 Toe Wall Raft 163+250 163+510 260 LHS 1/14/2022
1 0.4 104 Cum
268 NH-39/STR/284 Curtain wall Bed Pcc Box Culvert 154+031 10 U/S 1/14/2022
1.3 0.1 0.13 Cum
269 NH-39/STR/285 Curtain wall Bed Pcc Box Culvert 154+222 14 U/S 1/14/2022
1.3 0.1 0.13 Cum
RFI SUMMARY (STRUCTURE)
S.No RFI NO. Item Description Chainage Length Side NOS Width Height Qty Unit Details of Inspection
From To Date Time
270 NH-39/STR/286 Curtain wall Bed Pcc Box Culvert 154+623 10 U/S 1/14/2022
1.3 0.1 0.13 Cum
271 NH-39/STR/287 Reinforcement Checking for Service road portion MNB 155+800 LHS 1/14/2022
272 NH-39/STR/288 Shuttering Checcking & Concrete pourring for Raft Service road portion MNB 155+800 LHS 1/14/2022
274 NH-39/STR/290 Filter midia laying below Stone pitching 156+650 156+850 200 RHS 1/15/2022
2.5 0.15 0.375 Cum
275 NH-39/STR/291 Filter midia laying below Stone pitching 157+020 157+170 150 RHS 1/15/2022
2.5 0.15 0.375 Cum
276 NH-39/STR/292 Curtain wall Excavation Box Culvert 154+770 11 D/S 1/15/2022
1.3 0.1 0.13 Cum
277 NH-39/STR/293 Curtain wall Excavation Box Culvert 155+277 11 D/S 1/15/2022
1.3 0.1 0.13 Cum
278 NH-39/STR/294 Curtain wall Bed Pcc Box Culvert 154+623 10 D/S 1/15/2022
1.3 0.1 0.13 Cum
279 NH-39/STR/295 Curtain wall 1st lift Box Culvert 154+222 14 D/S 1/15/2022
1.2 0.6 0.72 Cum
280 NH-39/STR/296 Foundation Bed PCC MNB for Service road section MNB 156+156 LHS 1/15/2022
Cum
281 NH-39/STR/297 Curtain wall2nd lift Box Culvert 154+031 10 D/S 1/15/2022
0.825 1 0.825 Cum
282 NH-39/STR/298 1/15/2022
283 NH-39/STR/299 Reinforcement Checking for Service road portion MNB 155+800 LHS 1/15/2022
284 NH-39/STR/300 Shuttering Checcking & Concrete pourring for Raft Service road portion MNB 155+800 LHS 1/15/2022
287 NH-39/STR/303 Toe Wall Wall Casting 162+950 163+250 300 LHS 1/16/2022
0.45 1 0.45 Cum
288 NH-39/STR/304 Toe Wall Wall Casting 163+250 163+510 260 LHS 1/16/2022
0.45 1 0.45 Cum
289 NH-39/STR/305 Stone pitching 156+650 156+850 200 RHS 1/16/2022
2.5 0.3 0.75 Cum
290 NH-39/STR/306 Stone pitching 157+020 157+170 150 RHS 1/16/2022
2.5 0.3 0.75 Cum
291 NH-39/STR/307 Curtain wall 1st lift Box Culvert 154+031 10 U/S 1/16/2022
1.2 0.6 0.72 Cum
292 NH-39/STR/308 Curtain wall 1st lift Box Culvert 154+222 14 U/S 1/16/2022
1.2 0.6 0.72 Cum
293 NH-39/STR/309 Curtain wall 1st lift Box Culvert 154+623 10 U/S 1/16/2022
1.2 0.6 0.72 Cum
294 NH-39/STR/310 Excavation of MNB for Service road section MNB 156+156 RHS 1/16/2022
Cum
295 NH-39/STR/311 Curtain wall 1st lift Box Culvert 154+623 10 D/S 1/16/2022
1.2 0.6 0.72 Cum
296 NH-39/STR/312 Curtain wall2nd lift Box Culvert 154+222 14 D/S 1/16/2022
0.825 1 0.825 Cum
297 NH-39/STR/313 Curtain wall Bed Pcc Box Culvert 154+770 11 U/S 1/16/2022
1.3 0.1 0.13 Cum
298 NH-39/STR/314 Curtain wall Bed Pcc Box Culvert 155+277 11 U/S 1/16/2022
1.3 0.1 0.13 Cum
299 NH-39/STR/315 Toe Wall Raft 156+850 157+020 170 RHS 1/17/2022
1 0.4 68 Cum
300 NH-39/STR/316 Toe Wall Raft 157+170 157+280 110 RHS 1/17/2022
1 0.4 44 Cum
301 NH-39/STR/317 Curtain wall Bed Pcc Box Culvert 154+770 11 D/S 1/17/2022
1.3 0.1 0.13 Cum
302 NH-39/STR/318 Curtain wall Bed Pcc Box Culvert 155+277 11 D/S 1/17/2022
1.3 0.1 0.13 Cum
303 NH-39/STR/319 Curtain wall 1st lift Box Culvert 154+623 10 D/S 1/17/2022
1.2 0.6 0.72 Cum
304 NH-39/STR/320 Curtain wall2nd lift Box Culvert 154+222 14 D/S 1/17/2022
0.825 1 0.825 Cum
305 NH-39/STR/321 Curtain wall Bed Pcc Box Culvert 154+770 11 U/S 1/17/2022
1.3 0.1 0.13 Cum
306 NH-39/STR/322 Curtain wall Bed Pcc Box Culvert 155+277 11 U/S 1/17/2022
1.3 0.1 0.13 Cum
RFI SUMMARY (STRUCTURE)
S.No RFI NO. Item Description Chainage Length Side NOS Width Height Qty Unit Details of Inspection
From To Date Time
308 NH-39/STR/324 Reinforcement Checking for Service road portion MNB 155+800 LHS 1/17/2022
309 NH-39/STR/325 Shuttering Checcking & Concrete pourring for Raft Service road portion MNB 155+800 LHS 1/17/2022
310 NH-39/STR/326 Filter midia laying below Stone pitching 169+300 169+500 200 LHS 1/18/2022
2.5 0.15 0.375 Cum
311 NH-39/STR/327 Filter midia laying below Stone pitching 169+300 169+425 125 RHS 1/18/2022
2.5 0.15 0.375 Cum
312 NH-39/STR/328 Curtain wall Final Lift Box Culvert 154+031 10 D/S 1/18/2022
0.675 0.9 0.6075 Cum
313 NH-39/STR/329 Curtain wall 1st lift Box Culvert 154+770 11 D/S 1/18/2022
1.2 0.6 0.72 Cum
314 NH-39/STR/330 Curtain wall 1st lift Box Culvert 155+277 11 D/S 1/18/2022
1.2 0.6 0.72 Cum
315 NH-39/STR/331 Curtain wall2nd lift Box Culvert 154+623 10 D/S 1/18/2022
0.825 1 0.825 Cum
316 NH-39/STR/332 Toe Wall Raft 162+950 163+250 300 RHS 1/19/2022
1 0.4 120 Cum
317 NH-39/STR/333 Toe Wall Raft 163+250 163+510 260 RHS 1/19/2022
1 0.4 104 Cum
318 NH-39/STR/334 Toe Wall Raft 169+425 169+530 105 RHS 1/19/2022
1 0.4 42 Cum
319 NH-39/STR/335 Toe Wall Wall Casting 156+850 157+020 170 RHS 1/19/2022
0.45 1 0.45 Cum
320 NH-39/STR/336 Toe Wall Wall Casting 157+170 157+280 110 RHS 1/19/2022
0.45 1 0.45 Cum
321 NH-39/STR/337 Stone pitching 169+300 169+500 200 LHS 1/19/2022
2.5 0.3 0.75 Cum
322 NH-39/STR/338 Stone pitching 169+300 169+425 125 RHS 1/19/2022
2.5 0.3 0.75 Cum
323 NH-39/STR/339 Curtain wall 1st lift Box Culvert 154+770 11 D/S 1/19/2022
1.2 0.6 0.72 Cum
324 NH-39/STR/340 Curtain wall 1st lift Box Culvert 155+277 11 D/S 1/19/2022
1.2 0.6 0.72 Cum
325 NH-39/STR/341 Curtain wall2nd lift Box Culvert 154+623 10 D/S 1/19/2022
0.825 1 0.825 Cum
326 NH-39/STR/342 Curtain wall 1st lift Box Culvert 154+770 11 U/S 1/19/2022
1.2 0.6 0.72 Cum
327 NH-39/STR/343 Curtain wall 1st lift Box Culvert 155+277 11 U/S 1/19/2022
1.2 0.6 0.72 Cum
328 NH-39/STR/344 Curtain wall2nd lift Box Culvert 154+031 10 U/S 1/19/2022
0.825 1 0.825 Cum
329 NH-39/STR/345 Curtain wall2nd lift Box Culvert 154+222 14 U/S 1/19/2022
0.825 1 0.825 Cum
330 NH-39/STR/346 Curtain wall2nd lift Box Culvert 154+623 10 U/S 1/19/2022
0.825 1 0.825 Cum
331 NH-39/STR/347 Foundation Bed PCC MNB for Service road section MNB 156+156 RHS 1/19/2022
Cum
332 NH-39/STR/348 Reinforcement Checking for Service road portion MNB 156+156 LHS 1/19/2022
Cum
333 NH-39/STR/349 Shuttering Checcking & Concrete pourring for Raft Service road portion MNB 156+156 LHS 1/19/2022
Cum
334 NH-39/STR/350 1/19/2022
335 NH-39/STR/351 Toe Wall Wall Casting 163+250 163+510 260 RHS 1/19/2022
0.45 1 0.45 Cum
336 NH-39/STR/352 Toe Wall Wall Casting 169+425 169+530 105 RHS 1/19/2022
0.45 1 0.45 Cum
337 NH-39/STR/353 1/19/2022
339 NH-39/STR/355 Curtain wall Final Lift Box Culvert 154+222 14 D/S 1/20/2022
0.675 0.9 0.6075 Cum
340 NH-39/STR/356 Protection Work for Stone pitching HPC 156+744 RHS 1/20/2022
Cum
341 NH-39/STR/357 1/20/2022
342 NH-39/STR/358 Curtain wall2nd lift Box Culvert 154+770 11 D/S 1/20/2022
0.825 1 0.825 Cum
343 NH-39/STR/359 Curtain wall2nd lift Box Culvert 155+277 11 D/S 1/20/2022
0.825 1 0.825 Cum
RFI SUMMARY (STRUCTURE)
S.No RFI NO. Item Description Chainage Length Side NOS Width Height Qty Unit Details of Inspection
From To Date Time
346 NH-39/STR/362 Toe Wall Wall Casting 162+950 163+250 300 RHS 1/21/2022
0.45 1 0.45 Cum
347 NH-39/STR/363 Toe Wall Wall Casting 163+250 163+510 260 RHS 1/21/2022
0.45 1 0.45 Cum
348 NH-39/STR/364 Toe Wall Wall Casting 169+425 169+530 105 RHS 1/21/2022
0.45 1 0.45 Cum
349 NH-39/STR/365 Filter midia laying below Stone pitching 156+650 156+940 290 LHS 1/21/2022
2.5 0.15 0.375 Cum
350 NH-39/STR/366 Filter midia laying below Stone pitching 156+940 157+280 340 LHS 1/21/2022
2.5 0.15 0.375 Cum
351 NH-39/STR/367 Curtain wall2nd lift Box Culvert 154+770 11 D/S 1/21/2022
0.825 1 0.825 Cum
352 NH-39/STR/368 Curtain wall2nd lift Box Culvert 155+277 11 D/S 1/21/2022
0.825 1 0.825 Cum
353 NH-39/STR/369 Curtain wall Final Lift Box Culvert 154+031 10 U/S 1/21/2022
0.675 0.4 0.4 Cum
354 NH-39/STR/370 Curtain wall Final Lift Box Culvert 154+222 14 U/S 1/21/2022
0.675 0.4 0.825 Cum
355 NH-39/STR/371 Curtain wall Final Lift Box Culvert 154+623 10 U/S 1/21/2022
0.675 0.4 0.72 Cum
356 NH-39/STR/372 Protection Work for Stone pitching HPC 157+096 RHS 1/21/2022
Cum
357 NH-39/STR/373 Protection Work for Stone pitching HPC 159+101 RHS 1/21/2022
Cum
358 NH-39/STR/374 Protection Work for Stone pitching HPC 160+969 RHS 1/21/2022
Cum
359 NH-39/STR/375 Curtain wall Final Lift Box Culvert 154+623 10 D/S 1/21/2022
0.675 0.9 0.6075 Cum
360 NH-39/STR/376 Curtain wall2nd lift Box Culvert 154+770 11 U/S 1/21/2022
0.825 1 0.825 Cum
361 NH-39/STR/377 Curtain wall2nd lift Box Culvert 155+277 11 U/S 1/21/2022
0.825 1 0.825 Cum
362 NH-39/STR/378 1/21/2022
372 NH-39/STR/388 Reinforcement Checking for Service road portion MNB 155+800 LHS 1/22/2022
373 NH-39/STR/389 Shuttering Checcking & Concrete pourring for Raft Service road portion MNB 155+800 LHS 1/22/2022
375 NH-39/STR/391 Filter midia laying below Stone pitching 162+950 163+250 300 LHS 1/23/2022
2.5 0.15 0.375 Cum
376 NH-39/STR/392 Protection Work for Stone pitching HPC 164+724 RHS 1/23/2022
Cum
377 NH-39/STR/393 Protection Work for Stone pitching HPC 165+308 RHS 1/23/2022
Cum
378 NH-39/STR/394 Protection Work for Stone pitching HPC 156+744 LHS 1/23/2022
Cum
379 NH-39/STR/395 Reinforcement Checking for Service road portion MNB 156+156 RHS 1/23/2022
Cum
380 NH-39/STR/396 Shuttering Checcking & Concrete pourring for Raft Service road portion MNB 156+156 RHS 1/23/2022
Cum
RFI SUMMARY (STRUCTURE)
S.No RFI NO. Item Description Chainage Length Side NOS Width Height Qty Unit Details of Inspection
From To Date Time
381 NH-39/STR/397 Shuttering Checcking & Concrete pourring for Service road portion MNB 156+156 LHS 1/23/2022
Cum
382 NH-39/STR/398 Curtain wall Final Lift Box Culvert 155+277 11 U/S 1/23/2022
0.675 0.4 0.27 Cum
383 NH-39/STR/399 Curtain wall Final Lift Box Culvert 155+277 11 D/S 1/23/2022
0.675 0.9 0.6075 Cum
384 NH-39/STR/400 Curtain wall Final Lift Box Culvert 154+770 11 U/S 1/23/2022
0.675 0.4 0.27 Cum
385 NH-39/STR/401 1/23/2022
400 NH-39/STR/416 Protection Work for Stone pitching Box Culvert 154+031 RHS 1/25/2022
Cum
401 NH-39/STR/417 Protection Work for Stone pitching Box Culvert 154+222 RHS 1/25/2022
Cum
402 NH-39/STR/418 Protection Work for Stone pitching Box Culvert 154+623 RHS 1/25/2022
Cum
403 NH-39/STR/419 Protection Work for Stone pitching HPC 161+792 LHS 1/25/2022
Cum
404 NH-39/STR/420 Protection Work for Stone pitching HPC 163+657 LHS 1/25/2022
Cum
405 NH-39/STR/421 Protection Work for Stone pitching HPC 164+227 LHS 1/25/2022
Cum
406 NH-39/STR/422 Shuttering Checcking & Concrete pourring for Service road portion MNB 156+156 RHS 1/25/2022
Cum
407 NH-39/STR/423 checking of Toe wall PCC HPC 170+977 6.8 RHS 29-1-22
1 0.5 0.1 0.05 Cum
408 NH-39/STR/424 checking of Toe wall casting HPC 170+977 6.8 RHS 30-1-22
1 0.3 0.3 0.09 Cum
409 NH-39/STR/425 checking of Toe wall PCC HPC 170+977 6.8 LHS 29-1-22
1 0.5 0.1 0.05 Cum
410 NH-39/STR/426 checking of Toe wall casting HPC 170+977 6.8 LHS 30-1-22
1 0.3 0.3 0.09 Cum
411 NH-39/STR/427 Checking of Curtain wall Bed PCC 185+062 12 LHS 1/25/2022
1 1.4 0.1 0.14 cum
412 NH-39/STR/428 Shuttering Checking &Pouring M15 for Curtain wall 185+062 12 LHS 1/25/2022
1 0.9 2.5 2.25 Cum
413 NH-39/STR/429 Protection Work for Stone pitching Box Culvert 155+277 RHS 1/27/2022
Cum
414 NH-39/STR/430 Protection Work for Stone pitching HPC 164+724 LHS 1/27/2022
Cum
415 NH-39/STR/431 Protection Work for Stone pitching HPC 165+308 LHS 1/27/2022
Cum
416 NH-39/STR/432 Shuttering Checcking & Concrete pourring for Service road portion MNB 156+156 RHS 1/27/2022
Cum
417 NH-39/STR/433 Protection Work for Stone pitching Box Culvert 154+770 RHS 1/27/2022
Cum
RFI SUMMARY (STRUCTURE)
S.No RFI NO. Item Description Chainage Length Side NOS Width Height Qty Unit Details of Inspection
From To Date Time
418 NH-39/STR/434 Protection Work for Stone pitching Box Culvert 154+031 LHS 1/27/2022
Cum
419 NH-39/STR/435 Protection Work for Stone pitching Box Culvert 154+222 LHS 1/27/2022
Cum
420 NH-39/STR/436 Protection Work for Stone pitching Box Culvert 154+623 LHS 1/27/2022
Cum
421 NH-39/STR/437 Reinforcement Checking for Service road portion MNB 156+156 LHS 1/27/2022
Cum
422 NH-39/STR/438 Shuttering Checcking & Concrete pourring for Service road portion MNB 156+156 LHS 1/27/2022
Cum
423 NH-39/STR/439 Checking of Curtain wall Bed PCC 181+252 12 RHS 1/27/2022
1 1.4 0.1 0.14 cum
424 NH-39/STR/440 Shuttering Checking &Pouring M15 for Curtain wall 181+252 12 RHS 1/27/2022
1 0.9 2.5 2.25 Cum
425 NH-39/STR/441 Checking of Curtain wall Bed PCC 181+252 12 LHS 1/27/2022
1 1.4 0.1 0.14 cum
426 NH-39/STR/442 Shuttering Checking &Pouring M15 for Curtain wall 181+252 12 LHS 1/27/2022
1 0.9 2.5 2.25 Cum
427 NH-39/STR/443 Checking of Curtain wall Bed PCC 185+062 12 RHS 1/27/2022
1 1.4 0.1 0.14 cum
428 NH-39/STR/444 Shuttering Checking &Pouring M15 for Curtain wall 185+062 12 RHS 1/27/2022
1 0.9 2.5 2.25 Cum
429 NH-39/STR/445 1/27/2022
430 NH-39/STR/446 Protection Work for Stone pitching Box Culvert 155+277 LHS 1/27/2022
Cum
431 NH-39/STR/447 Reinforcement Checking for Service road portion MNB 156+156 RHS 1/27/2022
Cum
432 NH-39/STR/448 Shuttering Checcking & Concrete pourring for Service road portion MNB 156+156 RHS 1/27/2022
Cum
433 NH-39/STR/449 Protection Work for Stone pitching Box Culvert 154+770 LHS 1/27/2022
Cum
434 NH-39/STR/450 checking of Toe wall PCC HPC 170+252 6.8 LHS 1/27/2022
1 0.5 0.1 0.05 Cum
435 NH-39/STR/451 checking of Toe wall casting HPC 170+252 6.8 LHS 1/27/2022
1 0.3 0.3 0.09 Cum
436 NH-39/STR/452 checking of Toe wall PCC HPC 171+160 6.8 RHS 1/27/2022
1 0.5 0.1 0.05 Cum
437 NH-39/STR/453 checking of Toe wall casting HPC 171+160 6.8 RHS 1/27/2022
1 0.3 0.3 0.09 Cum
438 NH-39/STR/454 checking of Toe wall PCC HPC 171+160 6.8 LHS 1/27/2022
1 0.5 0.1 0.05 Cum
439 NH-39/STR/455 checking of Toe wall casting HPC 171+160 6.8 LHS 1/27/2022
1 0.3 0.3 0.09 Cum
440 NH-39/STR/456 checking of Toe wall PCC HPC 171+676 6.8 RHS 1/27/2022
1 0.5 0.1 0.05 Cum
441 NH-39/STR/457 checking of Toe wall casting HPC 171+676 6.8 RHS 1/27/2022
1 0.3 0.3 0.09 Cum
442 NH-39/STR/458 checking of Toe wall PCC HPC 171+676 6.8 LHS 1/27/2022
1 0.5 0.1 0.05 Cum
443 NH-39/STR/459 checking of Toe wall casting HPC 171+676 6.8 LHS 1/27/2022
1 0.3 0.3 0.09 Cum
444 NH-39/STR/460
445 NH-39/STR/461
446 NH-39/STR/462
447 NH-39/STR/463
448 NH-39/STR/464
449 NH-39/STR/465
450 NH-39/STR/466
451 NH-39/STR/467
452 NH-39/STR/468
453 NH-39/STR/469
454 NH-39/STR/470 Reinforcement & Shuttering Checking for 2nd lift (Singrauli End) VUP 169+006 LHS 2/9/2022
RFI SUMMARY (STRUCTURE)
S.No RFI NO. Item Description Chainage Length Side NOS Width Height Qty Unit Details of Inspection
From To Date Time
455 NH-39/STR/471 Checking Pouring of Concrete M35 2nd lift (Singrauli End) VUP 169+006 LHS 2/9/2022
456 NH-39/STR/472 checking of Toe wall PCC HPC 93+020 6.8 RHS 26-1-22
1 0.5 0.1 0.05 Cum
457 NH-39/STR/473 checking of Toe wall casting HPC 93+020 6.8 RHS 27-1-22
1 0.3 0.3 0.09 Cum
458 NH-39/STR/474 checking of Toe wall PCC HPC 89+194 4.5 LHS 29-1-22
1 0.5 0.1 0.05 Cum
459 NH-39/STR/475 checking of Toe wall casting HPC 89+194 4.5 LHS 30-1-22
1 0.3 0.3 0.09 Cum
460 NH-39/STR/476
461 NH-39/STR/477
462 NH-39/STR/478 checking of Toe wall PCC HPC 90+513 6.8 RHS 29-1-22
1 0.5 0.1 0.05 Cum
463 NH-39/STR/479 checking of Toe wall casting HPC 90+513 6.8 RHS 30-1-22
1 0.3 0.3 0.09 Cum
464 NH-39/STR/480 checking of Toe wall PCC HPC 89+194 4.5 RHS 29-1-22
1 0.5 0.1 0.05 Cum
465 NH-39/STR/481 checking of Toe wall casting HPC 89+194 4.5 RHS 30-1-22
1 0.3 0.3 0.09 Cum
466 NH-39/STR/482 Reinforcement & shuttering Checking Pouring of Concrete M35 VUP 1st lift (MCW) VUP 169+006 12 LHS 29-1-22
2 0.825 1.2 23.76 Cum
467 NH-39/STR/483 Reinforcement & shuttering Checking Pouring of Concrete M35 VUP 2nd lift (MCW) VUP 169+006 12 LHS 30-1-22
2 0.825 1.2 23.76 Cum
468 NH-39/STR/484 Reinforcement & shuttering Checking Pouring of Concrete M35 VUP 3rd lift (MCW) VUP 169+006 12 LHS 31-1-22
2 0.825 1.2 23.76 Cum
469 NH-39/STR/485 Reinforcement & Shuttering Checking for VUP 3rd lift (MCW) VUP 169+006 LHS 2/20/2022
470 NH-39/STR/486 Reinforcement & shuttering Checking Pouring of Concrete M35 VUP final lift (MCW) VUP 169+006 12 LHS 1/2/2022
2 0.825 1.2 23.76 Cum
471 NH-39/STR/487 Reinforcement & Shuttering Checking for MNB 1st lift (SR) MNB 156+156 RHS 2/20/2022
472 NH-39/STR/488 checking of Appron & Stone Pitching work HPC 90+513 20 RHS 1/2/2022
1 3 0.3 0.9 Cum
473 NH-39/STR/489 checking of Appron & Stone Pitching work HPC 93+020 20 RHS 1/2/2022
1 3 0.3 0.9 Cum
474 NH-39/STR/490 Checking Pouring of Concrete M35 MNB 1st lift (SR) MNB 156+156 RHS 2/20/2022
475 NH-39/STR/491
NH-39/STR/492
NH-39/STR/493 Reinforcement & Shuttering Checking Pouring of M35 for outer & inner wall 1st lift (MNB) MNB 156+156 19.925 RHS 31-1-22
2 0.799 1.425 45.37221375 cum
19.925 31-1-22
3 0.486 1.425 41.39717625 cum
478 NH-39/STR/494 Reinforcement & Shuttering Checking Pouring of M35 for outer & inner wall Final lift (MN MNB 156+156 19.925 RHS 1/2/2022
2 0.799 1.425 45.37221375 cum
479 NH-39/STR/495 19.925 1/2/2022
3 0.486 1.425 41.39717625 cum
480 NH-39/STR/496 Checking Pouring of Concrete M35 VUP 3rd lift (MCW) VUP 169+006 LHS
481 NH-39/STR/497 Checking Pouring of Concrete M35 MNB 1st lift (SR) MNB 156+156 RHS 2/21/2022
483 NH-39/STR/499
484 NH-39/STR/500
485 NH-39/STR/501
486 NH-39/STR/502
487 NH-39/STR/503
488 NH-39/STR/504
NH-39/STR/505
RFI SUMMARY (STRUCTURE)
S.No RFI NO. Item Description Chainage Length Side NOS Width Height Qty Unit Details of Inspection
From To Date Time
NH-39/STR/506 Reinforcement & Shuttering Checking for 4th lift wall A2 Side VUP VUP 169+006 LHS 2/24/2022
NH-39/STR/507 Shuttering checking pouring of M15 grade concrete for toe wall 153+700 153+850 150 LHS 31-01-22
1.15 0.15 25.875 cum
492 NH-39/STR/508 Shuttering checking pouring of M15 grade concrete for toe wall 153+700 153+850 150 LHS 1/2/2022
1 0.4 60 cum
493 NH-39/STR/509 Shuttering checking pouring of M15 grade concrete for toe wall 153+700 153+850 150 LHS 2/2/2022
0.45 1 67.5 cum
494 NH-39/STR/510 checking of Toe wall PCC HPC 90+513 6.8 LHS 2/2/2022
1 0.5 0.1 0.05 Cum
495 NH-39/STR/511 checking of Toe wall casting HPC 90+513 6.8 LHS 3/2/2022
1 0.3 0.3 0.09 Cum
496 NH-39/STR/512 checking of Toe wall PCC HPC 90+020 6.8 LHS 2/2/2022
1 0.5 0.1 0.05 Cum
497 NH-39/STR/513 checking of Toe wall casting HPC 90+020 6.8 LHS 3/2/2022
1 0.3 0.3 0.09 Cum
498 NH-39/STR/514 Reinforcement & Shuttering Checking for 1st lift Outer wall Service Road (MNB) MNB 156+156 RHS 2/25/2022
499 NH-39/STR/515 Checking Pouring of Concrete M35 1st lift Outer wall Service Road (MNB) MNB 156+156 RHS 2/25/2022
500 NH-39/STR/516
501 NH-39/STR/517 checking of Appron & Stone Pitching work HPC 90+513 20 LHS 4/2/2022
1 3 0.3 0.9 Cum
502 NH-39/STR/518 checking of Appron & Stone Pitching work HPC 90+020 20 LHS 4/2/2022
1 3 0.3 0.9 Cum
503 NH-39/STR/519
504 NH-39/STR/520
505 NH-39/STR/521 Reinforcement & Shuttering Checking for 1st lift wall (Box Culvert) Box Culvert 158+855 LHS 2/26/2022
506 NH-39/STR/522 Checking Pouring of Concrete M35 1st lift wall (Box Culvert) Box Culvert 158+855 LHS 2/26/2022
507 NH-39/STR/523 checking of Toe wall PCC HPC 96+104 6.8 LHS 2/2/2022
1 0.5 0.1 0.05 Cum
508 NH-39/STR/524 checking of Toe wall casting HPC 96+104 6.8 LHS 3/2/2022
1 0.3 0.3 0.09 Cum
509 NH-39/STR/525
510 NH-39/STR/526 Checking Pouring of concrete M-35 4th lift wall A2 Side VUP VUP 169+006 LHS 2/27/2022
511 NH-39/STR/527
NH-39/STR/528
NH-39/STR/529 Reinforcement & Shuttering Checking Pouring of M35 for outer & inner wall 1st lift (MNB) MNB 156+156 19.925 LHS 2/4/2022
2 0.799 1.425 45.37221375 cum
19.925 2/4/2022
3 0.486 1.425 41.39717625 cum
Reinforcement & Shuttering Checking Pouring of M35 for outer & inner wall Final lift (MN MNB 156+156 19.925 LHS 2/5/2022
2 0.799 1.425 45.37221375 cum
NH-39/STR/530 19.925 2/5/2022
3 0.486 1.425 41.39717625 cum
NH-39/STR/531 Reinforcement & Shuttering Checking for 3rd lift wall A1 Side VUP VUP 169+006 LHS 3/2/2022
9.00AM
516 NH-39/STR/532
517 NH-39/STR/533
518 NH-39/STR/534 Checking Pouring of concrete M-35 3rd lift wall A1 Side VUP VUP 169+006 LHS 3/2/2022
9.30AM
519 NH-39/STR/535 Reinforcement & Shuttering Checking for Dirtwall A2 Side (MNB) MNB 146+938 LHS 3/2/2022
10.30AM
520 NH-39/STR/536 Checking Pouring of Concrete M35 Dirtwall A2 Side (MNB) MNB 146+938 LHS 3/2/2022
11.00AM
521 NH-39/STR/537 Reinforcement & Shuttering Checking for Dirtwall A2 Side (MJB) MJB 114+443 LHS 3/2/2022
12.30PM
522 NH-39/STR/538 checking of Toe wall PCC HPC 93+219 6.8 RHS 2/2/2022
1 0.5 0.1 0.05 Cum
RFI SUMMARY (STRUCTURE)
S.No RFI NO. Item Description Chainage Length Side NOS Width Height Qty Unit Details of Inspection
From To Date Time
523 NH-39/STR/539 checking of Toe wall casting HPC 93+219 6.8 RHS 3/2/2022
1 0.3 0.3 0.09 Cum
524 NH-39/STR/540 checking of Toe wall PCC HPC 95+318 6.8 RHS 4/2/2022
1 0.5 0.1 0.05 Cum
525 NH-39/STR/541 checking of Toe wall casting HPC 95+318 6.8 RHS 5/2/2022
1 0.3 0.3 0.09 Cum
526 NH-39/STR/542 checking of Toe wall PCC HPC 95+318 6.8 LHS 6/2/2022
1 0.5 0.1 0.05 Cum
527 NH-39/STR/543 checking of Toe wall casting HPC 95+318 6.8 LHS 7/2/2022
1 0.3 0.3 0.09 Cum
528 NH-39/STR/544 Checking Pouring of Concrete M35 Dirtwall A2 Side (MJB) MJB 114+443 LHS 3/3/2022
10.00AM
529 NH-39/STR/545 checking of Appron & Stone Pitching work HPC 93+219 20 RHS 7/2/2022
1 3 0.3 0.9 Cum
530 NH-39/STR/546 checking of Appron & Stone Pitching work HPC 95+318 20 RHS 8/2/2022
1 3 0.3 0.9 Cum
531 NH-39/STR/547 checking of Appron & Stone Pitching work HPC 96+104 20 RHS 8/2/2022
1 3 0.3 0.9 Cum
532 NH-39/STR/548 Reinforcement & Shuttering Checking for 1st lift wall Singrauli end (Box Culvert) Box Culvert 158+855 LHS 3/3/2022
10.30am
533 NH-39/STR/549 Checking Pouring of Concrete M35 1st lift wall Singrauli end (Box Culvert) Box Culvert 158+855 LHS 3/3/2022
11.00am
534 NH-39/STR/550
535 NH-39/STR/551
536 NH-39/STR/552
537 NH-39/STR/553
538 NH-39/STR/554
NH-39/STR/555 checking of Toe wall PCC HPC 97+056 6.8 RHS 8/2/2022
1 0.5 0.1 0.05 Cum
NH-39/STR/556 checking of Toe wall casting HPC 97+056 6.8 RHS 9/2/2022
1 0.3 0.3 0.09 Cum
541 NH-39/STR/557 Reinforcement & Shuttering Checking for slab P2-A2 Span (ROB-2) ROB-2 169+221 LHS 3/4/2022
10.00AM
542 NH-39/STR/558 checking of Toe wall PCC HPC 96+750 6.8 LHS 8/2/2022
1 0.5 0.1 0.05 Cum
543 NH-39/STR/559 checking of Toe wall casting HPC 96+750 6.8 LHS 9/2/2022
1 0.3 0.3 0.09 Cum
NH-39/STR/560 Shuttering checking pouring of PCC M15 grade concrete for toe wall 153+190 153+450 260 RHS 7/2/2022
1.15 0.15 44.85 cum
NH-39/STR/561 Shuttering checking pouring of Raft M15 grade concrete for toe wall 153+190 153+450 260 RHS 8/2/2022
1 0.4 104 cum
NH-39/STR/562
NH-39/STR/563 Reinforcement & Shuttering Checking for slab P2-A2 Span (ROB-2) ROB-2 169+221 LHS 3/5/2022
1030 am
NH-39/STR/564 Shuttering checking pouring of wall M15 grade concrete for toe wall 153+190 153+450 260 RHS 9/2/2022
0.45 1 117 cum
Shuttering checking pouring of M15 for Bed PCC (MNB) 155+800 21.221 RHS 2/7/2022
1 16.65 0.1 35.332965 cum
549 NH-39/STR/565 Reinforcement & Shuttering checking pouring of M35 for Raft (MNB) 155+800 21.221 RHS 2/8/2022
1 16.65 0.5 176.664825 cum
550 NH-39/STR/566 Reinforcement & Shuttering checking pouring of M35 for outer & inner wall 1st lift (MNB 155+800 21.221 RHS 2/9/2022
2 0.475 1.65 33.2639175 cum
551 155+800 21.221 RHS 2/9/2022
2 0.35 1.65 24.510255 cum
NH-39/STR/567 checking of Appron & Stone Pitching work HPC 96+750 20 LHS 10/2/2022
1 3 0.3 0.9 Cum
552 NH-39/STR/568 checking of Appron & Stone Pitching work HPC 97+056 20 RHS 10/2/2022
1 3 0.3 0.9 Cum
NH-39/STR/569 Reinforcement & Shuttering checking pouring of M35 for outer & inner wall Final lift (MN 155+800 21.221 RHS 2/10/2022
2 0.475 1.65 33.2639175 cum
553 NH-39/STR/569 155+800 21.221 RHS 2/10/2022
2 0.35 1.65 24.510255 cum
RFI SUMMARY (STRUCTURE)
S.No RFI NO. Item Description Chainage Length Side NOS Width Height Qty Unit Details of Inspection
From To Date Time
554 NH-39/STR/570 Reinforcement & Shuttering Checking for slab P2-A2 Span (ROB-2) ROB-2 169+221 LHS
44625
555 NH-39/STR/571
556 NH-39/STR/572
557 NH-39/STR/573
558 NH-39/STR/574 Reinforcement & shuttering Checking Pouring of Concrete M35 VUP 1st lift (MCW) VUP 169+006 12 RHS 8/2/2022
2 0.825 1.2 23.76 Cum
559 NH-39/STR/575 Reinforcement & shuttering Checking Pouring of Concrete M35 VUP 2nd lift (MCW) VUP 169+006 12 RHS 9/2/2022
2 0.825 1.2 23.76 Cum
560 NH-39/STR/576 Reinforcement & shuttering Checking Pouring of Concrete M35 VUP 3rd lift (MCW) VUP 169+006 12 RHS 10/2/2022
2 0.825 1.2 23.76 Cum
561 NH-39/STR/577 Reinforcement & Shuttering Checking for slab P2-A2 Span (ROB-2) ROB-2 169+221 LHS
44627
562 NH-39/STR/578 Reinforcement & shuttering Checking Pouring of Concrete M35 VUP final lift (MCW) VUP 169+006 12 RHS 11/2/2022
2 0.825 1.2 23.76 Cum
563 NH-39/STR/579
564 NH-39/STR/580
565 NH-39/STR/581
566 NH-39/STR/582
567 NH-39/STR/583
568 NH-39/STR/584 Reinforcement & Shuttering Checking for Dirtwall A2 side (ROB-2) ROB-2 169+221 LHS
44628
569 NH-39/STR/585 Checking Pouring of Concrete M-35 Dirtwall A2 Side (ROB-2) ROB-2 169+221 LHS
44628
570 NH-39/STR/586 checking of Toe wall PCC HPC 93+219 6.8 LHS 8/2/2022
1 0.5 0.1 0.05 Cum
571 NH-39/STR/587 checking of Toe wall casting HPC 93+219 6.8 LHS 9/2/2022
1 0.3 0.3 0.09 Cum
572 NH-39/STR/588 checking of Appron & Stone Pitching work HPC 93+219 20 LHS 13-2-22
1 3 0.3 0.9 Cum
573 NH-39/STR/589 checking of Appron & Stone Pitching work HPC 95+318 20 RHS 13-2-22
1 3 0.3 0.9 Cum
574 NH-39/STR/590 checking of Appron & Stone Pitching work HPC 96+104 20 LHS 13-2-22
1 3 0.3 0.9 Cum
575 NH-39/STR/591 checking of Toe wall PCC HPC 97+056 6.8 LHS 8/2/2022
0.5 0.1 0.05 Cum
576 NH-39/STR/592 checking of Toe wall casting HPC 97+056 6.8 LHS 9/2/2022
0.3 0.3 0.09 Cum
577 NH-39/STR/593 checking of Toe wall PCC HPC 170+252 6.8 RHS 8/2/2022
1 0.5 0.1 0.05 Cum
578 NH-39/STR/594 checking of Toe wall casting HPC 170+252 6.8 RHS 9/2/2022
1 0.3 0.3 0.09 Cum
579 NH-39/STR/595 checking of Toe wall PCC HPC 96+750 6.8 RHS 8/2/2022
1 0.5 0.1 0.05 Cum
580 NH-39/STR/596 checking of Toe wall casting HPC 96+750 6.8 RHS 9/2/2022
1 0.3 0.3 0.09 Cum
581 NH-39/STR/597 Reinforcement & Shuttering Checking for Dirtwall A1 Side (MNB) MNB 146+938 LHS
44629
582 NH-39/STR/598 checking of Appron & Stone Pitching work HPC 96+750 20 RHS 14-2-22
1 3 0.3 0.9 Cum
583 NH-39/STR/599 checking of Appron & Stone Pitching work HPC 97+056 20 LHS 14-2-22
3 0.3 0.9 Cum
584 NH-39/STR/600 Checking Pouring of Concrete M35 Dirtwall A1 Side (MNB) MNB 146+938 LHS
44629
585 NH-39/STR/601 Reinforcement & Shuttering Checking for 2nd lift wall Sidhi end (Box Culvert) Box Culvert 158+855 LHS
44629
586 NH-39/STR/602 Checking Pouring of Concrete M30 2nd lift wall Sidhi end (Box Culvert) Box Culvert 158+855 LHS
44629
587 NH-39/STR/603 Reinforcement & Shuttering Checking for Slab P2-A2 side span (ROB-2) ROB-2 169+221 LHS
44629
588 NH-39/STR/604 Checking Pouring of Concrete M-45 Slab P2-A2 side span (ROB-2) ROB-2 169+221 LHS
44629
589 NH-39/STR/605 checking of Toe wall PCC HPC 169+804 6.8 LHS 8/2/2022
1 0.5 0.1 0.05 Cum
590 NH-39/STR/606 checking of Toe wall casting HPC 169+804 6.8 LHS 9/2/2022
1 0.3 0.3 0.09 Cum
RFI SUMMARY (STRUCTURE)
S.No RFI NO. Item Description Chainage Length Side NOS Width Height Qty Unit Details of Inspection
From To Date Time
591 NH-39/STR/607 Checking of Curtain wall Bed PCC 184+438 12 LHS 8/2/2022
1 1.4 0.1 0.14 cum
592 NH-39/STR/608 Shuttering Checking &Pouring M15 for Curtain wall 184+438 12 LHS 9/2/2022
1 0.9 2.5 2.25 Cum
593 NH-39/STR/609
594 NH-39/STR/610 checking of Appron & Stone Pitching work HPC 169+804 20 LHS 16-2-22
1 3 0.3 0.9 Cum
595 NH-39/STR/611 checking of Appron & Stone Pitching work HPC 170+252 20 RHS 16-2-22
1 3 0.3 0.9 Cum
596 NH-39/STR/612 checking of Appron & Stone Pitching work HPC 171+160 20 LHS 16-2-22
1 3 0.3 0.9 Cum
597 NH-39/STR/613 checking of Appron & Stone Pitching work HPC 171+676 20 RHS 16-2-22
1 3 0.3 0.9 Cum
598 NH-39/STR/614 Shuttering checking pouring of PCC M15 grade concrete for toe wall 162+950 163+250 300 RHS 12/2/2022
1.15 0.15 51.75 cum
599 NH-39/STR/615 Shuttering checking pouring of Raft M15 grade concrete for toe wall 162+950 163+250 300 RHS 13-2-22
1 0.4 120 cum
600 NH-39/STR/616 Shuttering checking pouring of wall M15 grade concrete for toe wall 162+950 163+250 300 RHS 14-2-22
0.45 1 135 cum
601 NH-39/STR/617 Checking Pouring of Concrete M-45 Slab P2-A2 side span (ROB-2) ROB-2 169+221 LHS
602 NH-39/STR/618 checking of Toe wall PCC HPC 169+324 6.8 RHS 8/2/2022
1 0.5 0.1 0.05 Cum
603 NH-39/STR/619 checking of Toe wall casting HPC 169+324 6.8 RHS 9/2/2022
1 0.3 0.3 0.09 Cum
604
605 NH-39/STR/620
606
607 NH-39/STR/621 Checking of Curtain wall Bed PCC 183+660 12 LHS 8/2/2022
1 1.4 0.1 0.14 cum
608 NH-39/STR/622 Shuttering Checking &Pouring M15 for Curtain wall 183+660 12 LHS 9/2/2022
1 0.9 2.5 2.25 Cum
609 NH-39/STR/623 Checking of Curtain wall Bed PCC 184+438 12 RHS 8/2/2022
1 1.4 0.1 0.14 cum
610 NH-39/STR/624 Shuttering Checking &Pouring M15 for Curtain wall 184+438 12 RHS 9/2/2022
1 0.9 2.5 2.25 Cum
611 NH-39/STR/625 Shuttering checking pouring of M15 for Bed PCC (MNB) 155+800 21.221 LHS 14-2-22
1 16.65 0.1 35.332965 cum
612 NH-39/STR/626 Reinforcement & Shuttering checking pouring of M35 for Raft (MNB) 155+800 21.221 LHS 15-2-22
1 16.65 0.5 176.664825 cum
613 NH-39/STR/627 Reinforcement & Shuttering checking pouring of M35 for outer & inner wall 1st lift (MNB 155+800 21.221 LHS 16-2-22
2 0.475 1.65 33.2639175 cum
614 155+800 21.221 LHS 16-2-22
2 0.35 1.65 24.510255 cum
615 NH-39/STR/628 checking of Appron & Stone Pitching work HPC 169+324 20 RHS 14-2-22
1 3 0.3 0.9 Cum
616 NH-39/STR/629 Reinforcement & Shuttering checking pouring of M35 for outer & inner wall Final lift (MN 155+800 21.221 LHS 17-2-22
2 0.475 1.65 33.2639175 cum
617 NH-39/STR/630 155+800 21.221 LHS 17-2-22
2 0.35 1.65 24.510255 cum
618
619 NH-39/STR/631 checking of Toe wall PCC HPC 169+804 6.8 RHS 8/2/2022
1 0.5 0.1 0.05 Cum
620 NH-39/STR/632 checking of Toe wall casting HPC 169+804 6.8 RHS 9/2/2022
1 0.3 0.3 0.09 Cum
621 NH-39/STR/633
622 NH-39/STR/634
623 NH-39/STR/635
624 NH-39/STR/636
625 NH-39/STR/637
626 NH-39/STR/638
627 NH-39/STR/639
RFI SUMMARY (STRUCTURE)
S.No RFI NO. Item Description Chainage Length Side NOS Width Height Qty Unit Details of Inspection
From To Date Time
628 NH-39/STR/640
629 NH-39/STR/641
630 NH-39/STR/642
631 NH-39/STR/643
632 NH-39/STR/644
633 NH-39/STR/645
634 NH-39/STR/646
635 NH-39/STR/647
636 NH-39/STR/648
637 NH-39/STR/649 checking of Appron & Stone Pitching work HPC 169+804 20 RHS 20-2-22
1 3 0.3 0.9 Cum
638 NH-39/STR/650 checking of Appron & Stone Pitching work HPC 170+252 20 LHS 21/02/2022
1 3 0.3 0.9 Cum
639 NH-39/STR/651 checking of Appron & Stone Pitching work HPC 171+160 20 RHS 21/02/2022
1 3 0.3 0.9 Cum
640 NH-39/STR/652 checking of Appron & Stone Pitching work HPC 171+676 20 LHS 21/02/2022
1 3 0.3 0.9 Cum
641 NH-39/STR/653 Checking of Curtain wall Bed PCC 184+438 12 LHS 21/02/2022
1 1.4 0.1 0.14 cum
642 NH-39/STR/654 Shuttering Checking &Pouring M15 for Curtain wall 184+438 12 LHS 21/02/2022
1 0.9 2.5 2.25 Cum
643 NH-39/STR/655 Checking of Curtain wall Bed PCC 185+062 12 RHS 21/02/2022
1 1.4 0.1 0.14 cum
644 NH-39/STR/656 Shuttering Checking &Pouring M15 for Curtain wall 185+062 12 RHS 21/02/2022
1 0.9 2.5 2.25 Cum
645 NH-39/STR/657 Checking of Curtain wall Bed PCC 185+062 12 LHS 21/02/2022
1 1.4 0.1 0.14 cum
646 NH-39/STR/658 Shuttering Checking &Pouring M15 for Curtain wall 185+062 12 LHS 21/02/2022
1 0.9 2.5 2.25 Cum
647 NH-39/STR/659 Checking of Curtain wall Bed PCC Box culvrt 89+079 12 RHS 23-2-22
1 1.4 0.1 0.14 cum
648 NH-39/STR/660 Shuttering Checking &Pouring M15 for Curtain wall Box culvrt 89+079 12 RHS 24-2-22
1 0.9 2.5 2.25 Cum
649 NH-39/STR/661 Checking of Curtain wall Bed PCC Box culvrt 89+079 12 LHS 23-2-22
1 1.4 0.1 0.14 cum
650 NH-39/STR/662 Shuttering Checking &Pouring M15 for Curtain wall Box culvrt 89+079 12 LHS 24-2-22
1 0.9 2.5 2.25 Cum
651 NH-39/STR/663
652 NH-39/STR/664
653 NH-39/STR/665
654 NH-39/STR/666
655 NH-39/STR/667
656 NH-39/STR/668
657 NH-39/STR/669
658 NH-39/STR/670
659 NH-39/STR/671
660 NH-39/STR/672
661 NH-39/STR/673
662 NH-39/STR/674
663 NH-39/STR/675
664 NH-39/STR/676
RFI SUMMARY (STRUCTURE)
S.No RFI NO. Item Description Chainage Length Side NOS Width Height Qty Unit Details of Inspection
From To Date Time
665 NH-39/STR/677
666 NH-39/STR/678
667 NH-39/STR/679
668 NH-39/STR/680
669 NH-39/STR/681
670 NH-39/STR/682
671 NH-39/STR/683
672 NH-39/STR/684
673 NH-39/STR/685
674 NH-39/STR/686 Checking of Curtain wall Bed PCC 183+660 12 RHS 23-2-22
1 1.4 0.1 0.14 cum
675 NH-39/STR/687 Shuttering Checking &Pouring M15 for Curtain wall 183+660 12 RHS 24-2-22
1 0.9 2.5 2.25 Cum
676 NH-39/STR/688 checking of Appron & Stone Pitching work 183+660 14 RHS 25-2-22
1 5 0.3 1.5 Cum
677 NH-39/STR/689 Shuttering checking pouring of PCC M15 grade concrete for toe wall 153+480 153+750 270 RHS 22-2-22
1.15 0.15 46.575 cum
678 NH-39/STR/690 Shuttering checking pouring of Raft M15 grade concrete for toe wall 153+750 #VALUE! RHS 23-2-22
1 0.4 #VALUE! cum
679 NH-39/STR/691 Shuttering checking pouring of wall M15 grade concrete for toe wall 153+480 153+750 270 RHS 24-2-22
0.45 1 121.5 cum
680 NH-39/STR/692 checking of Toe wall PCC HPC 169+324 6.8 LHS 8/2/2022
1 0.5 0.1 0.05 Cum
681 NH-39/STR/693 checking of Toe wall casting HPC 169+324 6.8 LHS 9/2/2022
1 0.3 0.3 0.09 Cum
682 NH-39/STR/694 checking of Toe wall PCC HPC 89+344 4.5 RHS 8/2/2022
1 0.5 0.1 0.05 Cum
683 NH-39/STR/695 checking of Toe wall casting HPC 89+344 4.5 RHS 9/2/2022
1 0.3 0.3 0.09 Cum
684 NH-39/STR/696 checking of Toe wall PCC HPC 89+344 4.5 LHS 8/2/2022
1 0.5 0.1 0.05 Cum
685 NH-39/STR/697 checking of Toe wall casting HPC 89+344 4.5 LHS 9/2/2022
1 0.3 0.3 0.09 Cum
686 NH-39/STR/698
687 NH-39/STR/699
688 NH-39/STR/700
689 NH-39/STR/701 checking of Toe wall PCC HPC 90+019 4.5 LHS 24-2-22
1 0.5 0.1 0.05 Cum
690 NH-39/STR/702 checking of Toe wall casting HPC 90+019 4.5 LHS 25-2-22
1 0.3 0.3 0.09 Cum
691 NH-39/STR/703 checking of Toe wall PCC HPC 90+019 4.5 RHS 24-2-22
1 0.5 0.1 0.05 Cum
692 NH-39/STR/704 checking of Toe wall casting HPC 90+019 4.5 RHS 25-2-22
1 0.3 0.3 0.09 Cum
693 NH-39/STR/705 Shuttering checking pouring of PCC M15 grade concrete for toe wall 154+125 154+240 115 LHS 24-2-22
1.15 0.15 19.8375 cum
694 NH-39/STR/706 Shuttering checking pouring of Raft M15 grade concrete for toe wall 154+125 154+240 115 LHS 25-2-22
1 0.4 46 cum
695 NH-39/STR/707 Shuttering checking pouring of wall M15 grade concrete for toe wall 154+125 154+240 115 LHS 26-2-22
0.45 1 51.75 cum
696 NH-39/STR/708 checking of Appron & Stone Pitching work HPC 169+324 20 LHS 28-2-22
1 3 0.3 0.9 Cum
697 NH-39/STR/709 Checking of Curtain wall Bed PCC Box culvrt 89+775 12 LHS 23-2-22
1 1.4 0.1 0.14 cum
698 NH-39/STR/710 Shuttering Checking &Pouring M15 for Curtain wall Box culvrt 89+775 12 LHS 24-2-22
1 0.9 2.5 2.25 Cum
699 NH-39/STR/711 checking of Appron & Stone Pitching work HPC 20 16-2-22
1 3 0.3 0.9 Cum
700 NH-39/STR/712 Shuttering checking pouring of PCC M15 grade concrete for toe wall 154+630 154+780 150 LHS 25-2-22
1.15 0.15 25.875 cum
701 NH-39/STR/713 Shuttering checking pouring of Raft M15 grade concrete for toe wall 154+630 154+780 150 LHS 26-2-22
1 0.4 60 cum
RFI SUMMARY (STRUCTURE)
S.No RFI NO. Item Description Chainage Length Side NOS Width Height Qty Unit Details of Inspection
From To Date Time
702 NH-39/STR/714 Shuttering checking pouring of wall M15 grade concrete for toe wall 154+630 154+780 150 LHS 27-2-22
0.45 1 67.5 cum
703 NH-39/STR/715 Checking of Curtain wall Bed PCC Box culvrt 89+079 12 RHS 23-2-22
1 1.4 0.1 0.14 cum
704 NH-39/STR/716 Shuttering Checking &Pouring M15 for Curtain wall Box culvrt 89+079 12 RHS 24-2-22
1 0.9 2.5 2.25 Cum
705 NH-39/STR/717 Checking of Curtain wall Bed PCC Box culvrt 89+079 12 LHS 23-2-22
1 1.4 0.1 0.14 cum
706 NH-39/STR/718 Shuttering Checking &Pouring M15 for Curtain wall Box culvrt 89+079 12 LHS 24-2-22
1 0.9 2.5 2.25 Cum
707 NH-39/STR/719 Checking of Curtain wall Bed PCC Box culvrt 89+775 12 RHS 23-2-22
1 1.4 0.1 0.14 cum
708 NH-39/STR/720 Shuttering Checking &Pouring M15 for Curtain wall Box culvrt 89+775 12 RHS 24-2-22
1 0.9 2.5 2.25 Cum
709 NH-39/STR/721
710 NH-39/STR/722 Reinforcement & Shuttering checking pouring of M35 for SLAB (MNB) 156+156 19.925 LHS 1/3/2022
1 23.056 0.55 252.66494 cum
711 NH-39/STR/723
712 NH-39/STR/724
713 NH-39/STR/725 checking of Appron & Stone Pitching work HPC 170+706 20 RHS 2/3/2022
1 3 0.3 0.9 Cum
714 NH-39/STR/726 checking of Appron & Stone Pitching work HPC 170+977 20 RHS 2/3/2022
1 3 0.3 0.9 Cum
715 NH-39/STR/727
716 NH-39/STR/728
717 NH-39/STR/729
718 NH-39/STR/730
719 NH-39/STR/731
720 NH-39/STR/732
721 NH-39/STR/733
722 NH-39/STR/734
723 NH-39/STR/735
724 NH-39/STR/736
725 NH-39/STR/737
726 NH-39/STR/738
727 NH-39/STR/739
728 NH-39/STR/740
729 NH-39/STR/741
730 NH-39/STR/742
731 NH-39/STR/743
732 NH-39/STR/744
733 NH-39/STR/745
734 NH-39/STR/746
735 NH-39/STR/747
736 NH-39/STR/748
737 NH-39/STR/749
738 NH-39/STR/750
RFI SUMMARY (STRUCTURE)
S.No RFI NO. Item Description Chainage Length Side NOS Width Height Qty Unit Details of Inspection
From To Date Time
739 NH-39/STR/751
740 NH-39/STR/752
741 NH-39/STR/753 Reinforcement & Shuttering checking pouring of M35 for SLAB (MNB) 156+156 19.925 RHS 4/3/2022
1 23.056 0.55 252.66494 cum
742 NH-39/STR/754 checking of Appron & Stone Pitching work HPC 170+706 20 LHS 2/3/2022
1 3 0.3 0.9 Cum
743 NH-39/STR/755 checking of Appron & Stone Pitching work HPC 170+977 20 LHS 5/3/2022
1 3 0.3 0.9 Cum
744 NH-39/STR/756
745 NH-39/STR/757 Reinforcement & Shuttering checking pouring of M45 for SLAB SPAN P2-A2 (ROB-ii) 169+221 24.8 LHS 5/3/2022
1 12 0.25 3 cum
746 NH-39/STR/758
747 NH-39/STR/759
748 NH-39/STR/760
749 NH-39/STR/761
750 NH-39/STR/762
751 NH-39/STR/763
752 NH-39/STR/764
753 NH-39/STR/765
754 NH-39/STR/766
755 NH-39/STR/767
756 NH-39/STR/768
757 NH-39/STR/769
758 NH-39/STR/770
759 NH-39/STR/771
760 NH-39/STR/772
761 NH-39/STR/773
762 NH-39/STR/774
763 NH-39/STR/775
764 NH-39/STR/776
765 NH-39/STR/777
766 NH-39/STR/778 checking of Appron & Stone Pitching work Boxculvert 89+079 14 RHS 8/3/2022
1 5 0.3 1.5 Cum
767 NH-39/STR/779
768 NH-39/STR/780
769 NH-39/STR/781
770 NH-39/STR/782
771 NH-39/STR/783
772 NH-39/STR/784
773 NH-39/STR/785
774 NH-39/STR/786
775 NH-39/STR/787
RFI SUMMARY (STRUCTURE)
S.No RFI NO. Item Description Chainage Length Side NOS Width Height Qty Unit Details of Inspection
From To Date Time
776 NH-39/STR/788
777 NH-39/STR/789
778 NH-39/STR/790
779 NH-39/STR/791
780 NH-39/STR/792
781 NH-39/STR/793
782 NH-39/STR/794
783 NH-39/STR/795
784 NH-39/STR/796
785 NH-39/STR/797
786 NH-39/STR/798
787 NH-39/STR/799
788 NH-39/STR/800
789 NH-39/STR/801
790 NH-39/STR/802
791 NH-39/STR/803 checking of Appron & Stone Pitching work HPC 89+344 20 LHS 10/3/2022
1 3 0.3 0.9 Cum
792 NH-39/STR/804
793 NH-39/STR/805
794 NH-39/STR/806
795 NH-39/STR/807
796 NH-39/STR/808
797 NH-39/STR/809 checking of Appron & Stone Pitching work HPC 89+194 20 RHS 11/3/2022
1 3 0.3 0.9 Cum
798 NH-39/STR/810
799 NH-39/STR/811
800 NH-39/STR/812
801 NH-39/STR/813
802 NH-39/STR/814
803 NH-39/STR/815
804 NH-39/STR/816
805 NH-39/STR/817 checking of Appron & Stone Pitching work Boxculvert 89+079 14 LHS 12/3/2022
1 5 0.3 1.5 Cum
806 NH-39/STR/818
807 NH-39/STR/819
808 NH-39/STR/820
809 NH-39/STR/821
810 NH-39/STR/822
811 NH-39/STR/823
812 NH-39/STR/824
RFI SUMMARY (STRUCTURE)
S.No RFI NO. Item Description Chainage Length Side NOS Width Height Qty Unit Details of Inspection
From To Date Time
813 NH-39/STR/825
814 NH-39/STR/826
815 NH-39/STR/827
816 NH-39/STR/828
817 NH-39/STR/829
818 NH-39/STR/830
819 NH-39/STR/831
820 NH-39/STR/832
821 NH-39/STR/833
822 NH-39/STR/834
823 NH-39/STR/835 checking of Appron & Stone Pitching work HPC 89+194 20 LHS 14-3-22
1 3 0.3 0.9 Cum
824 NH-39/STR/836
825 NH-39/STR/837
826 NH-39/STR/838
827 NH-39/STR/839
828 NH-39/STR/840
829 NH-39/STR/841
830 NH-39/STR/842
831 NH-39/STR/843
832 NH-39/STR/844
833 NH-39/STR/845
834 NH-39/STR/846
835 NH-39/STR/847
836 NH-39/STR/848 checking of Appron & Stone Pitching work HPC 89+344 20 RHS 15-3-22
1 3 0.3 0.9 Cum
837 NH-39/STR/849
838 NH-39/STR/850
839 NH-39/STR/851
840 NH-39/STR/852
841 NH-39/STR/853
842 NH-39/STR/854
843 NH-39/STR/855
844 NH-39/STR/856
845 NH-39/STR/857
846 NH-39/STR/858
847 NH-39/STR/859
848 NH-39/STR/860
849 NH-39/STR/861
RFI SUMMARY (STRUCTURE)
S.No RFI NO. Item Description Chainage Length Side NOS Width Height Qty Unit Details of Inspection
From To Date Time
850 NH-39/STR/862
851 NH-39/STR/863
852 NH-39/STR/864
853 NH-39/STR/865
854 NH-39/STR/866
855 NH-39/STR/867
856 NH-39/STR/868
857 NH-39/STR/869 checking of Appron & Stone Pitching work Boxculvert 89+775 14 RHS 17-3-22
1 5 0.3 1.5 Cum
858 NH-39/STR/870
859 NH-39/STR/871
860 NH-39/STR/872
861 NH-39/STR/873
862 NH-39/STR/874
863 NH-39/STR/875
864 NH-39/STR/876
865 NH-39/STR/877
866 NH-39/STR/878
867 NH-39/STR/879
868 NH-39/STR/880
869 NH-39/STR/881
870 NH-39/STR/882
871 NH-39/STR/883
872 NH-39/STR/884
873 NH-39/STR/885
874 NH-39/STR/886
875 NH-39/STR/887
876 NH-39/STR/888
877 NH-39/STR/889
878 NH-39/STR/890
879 NH-39/STR/891
880 NH-39/STR/892
881 NH-39/STR/893
882 NH-39/STR/894
883 NH-39/STR/895
884 NH-39/STR/896
885 NH-39/STR/897
886 NH-39/STR/898 checking of Appron & Stone Pitching work Boxculvert 89+775 14 LHS 20-3-22
1 5 0.3 1.5 Cum
RFI SUMMARY (STRUCTURE)
S.No RFI NO. Item Description Chainage Length Side NOS Width Height Qty Unit Details of Inspection
From To Date Time
887 NH-39/STR/899
888 NH-39/STR/900
889 NH-39/STR/901
890 NH-39/STR/902
891 NH-39/STR/903
892 NH-39/STR/904
893 NH-39/STR/905
894 NH-39/STR/906
895 NH-39/STR/907
896 NH-39/STR/908
897 NH-39/STR/909
898 NH-39/STR/910
899 NH-39/STR/911
900 NH-39/STR/912
901 NH-39/STR/913
902 NH-39/STR/914
903 NH-39/STR/915
904 NH-39/STR/916
905 NH-39/STR/917 checking of Appron & Stone Pitching work HPC 90+019 20 RHS 22-3-22
1 3 0.3 0.9 Cum
906 NH-39/STR/918
907 NH-39/STR/919
908 NH-39/STR/920
909 NH-39/STR/921
910 NH-39/STR/922
911 NH-39/STR/923
912 NH-39/STR/924
913 NH-39/STR/925
914 NH-39/STR/926
915 NH-39/STR/927
916 NH-39/STR/928
917 NH-39/STR/929
918 NH-39/STR/930
919 NH-39/STR/931
920 NH-39/STR/932
921 NH-39/STR/933
922 NH-39/STR/934
923 NH-39/STR/935
RFI SUMMARY (STRUCTURE)
S.No RFI NO. Item Description Chainage Length Side NOS Width Height Qty Unit Details of Inspection
From To Date Time
924 NH-39/STR/936
925 NH-39/STR/937
926 NH-39/STR/938
927 NH-39/STR/939
928 NH-39/STR/940
929 NH-39/STR/941 checking of Appron & Stone Pitching work HPC 90+019 20 LHS 24-3-22
1 3 0.3 0.9 Cum
930 NH-39/STR/942
931 NH-39/STR/943
932 NH-39/STR/944
933 NH-39/STR/945
934 NH-39/STR/946
935 NH-39/STR/947
936 NH-39/STR/948
937 NH-39/STR/949
938 NH-39/STR/950
939 NH-39/STR/951
940 NH-39/STR/952
941 NH-39/STR/953
942 NH-39/STR/954
943 NH-39/STR/955
944 NH-39/STR/956
945 NH-39/STR/957
946 NH-39/STR/958 Reinforcement & Shuttering checking pouring of M45 for SLAB SPAN P2-A2 (ROB-ii) 169+221 24.8 LHS 26-3-22
1 12 0.25 3 cum
947 NH-39/STR/959
948 NH-39/STR/960
949 NH-39/STR/961
950 NH-39/STR/962
951 NH-39/STR/963
952 NH-39/STR/964 Filter media laying & stone pitching for protection work 154+630 154+780 150 LHS 4/1/2022
1 8 0.3 2.4 Cum
953 NH-39/STR/965 Layout,OGL Checking and excavation for foundation MNB 155+384 35 BHS 4/2/2022
1 29.5 1.5 44.25 Cum
954 NH-39/STR/966 Layout,OGL Checking and excavation for toe wall 153+190 153+290 100 LHS 4/3/2022
1 1.5 0.8 1.2 Cum
955 NH-39/STR/967 Checking of Foundation bed PCC for toe wall 153+190 153+290 100 LHS 4/4/2022
1 1.15 0.1 0.115 Cum
956 NH-39/STR/968 shuttering checking & Pouring of M20 Toe wall Raft casting 153+190 153+290 100 LHS 4/5/2022
1 1 0.4 0.4 Cum
957 NH-39/STR/969 shuttering checking & Pouring of M20 Toe wall WALL casting 153+190 153+240 50 LHS 4/6/2022
1 0.6 1 0.6 Cum
958 NH-39/STR/970 shuttering checking & Pouring of M20 Toe wall WALL casting 153+240 153+290 50 LHS 4/7/2022
1 0.6 1 0.6 Cum
959 NH-39/STR/971 Checking of Foundation bed PCC for MNB 155+384 32.95 LHS 4/4/2022
1 14.383 0.1 1.4383 Cum
960 NH-39/STR/972 Checking of Foundation bed PCC for MNB 155+384 32.95 RHS 4/5/2022
1 14.383 0.1 1.4383 Cum
RFI SUMMARY (STRUCTURE)
S.No RFI NO. Item Description Chainage Length Side NOS Width Height Qty Unit Details of Inspection
From To Date Time
962 NH-39/STR/974 Reinforcement shuttering checking & Pouring of M35 MNB Raft casting 155+384 32.95 LHS 4/7/2022
1 14.383 0.5 7.1915 Cum
963 NH-39/STR/975 Reinforcement shuttering checking & Pouring of M35 MNB Raft casting 155+384 32.95 RHS 4/8/2022
1 14.383 0.5 7.1915 Cum
964 NH-39/STR/976
965 NH-39/STR/977
966 NH-39/STR/978 Layout,OGL Checking and excavation for Retaining wall 154+035 154+140 105 LHS 4/11/2022
1 3 1.5 4.5 Cum
967 NH-39/STR/979 Checking of Foundation bed PCC for Retaining wall 154+035 154+140 105 LHS 4/12/2022
1 2.6 0.1 0.26 Cum
968 NH-39/STR/980 4/13/2022
970 NH-39/STR/982 Reinforcement shuttering checking & Pouring of M30 Retaining wall Raft casting 154+035 154+085 50 LHS 4/15/2022
1 2.4 0.4 0.96 Cum
971 NH-39/STR/983 Reinforcement & Shuttering checking pouring of M40 for SLAB SPAN P-14 P-15 (MJB) 114+413 LHS 4/8/2022
972 NH-39/STR/984 Reinforcement shuttering checking & Pouring of M30 Retaining wall Raft casting 154+085 154+140 55 LHS 4/16/2022
1 2.4 0.4 0.96 Cum
973 NH-39/STR/985
974 NH-39/STR/986 Reinforcement shuttering checking & Pouring of M30 Retaining wall for wall casting 154+035 154+085 50 LHS 4/17/2022
1 0.3 1.8 0.54 Cum
975 NH-39/STR/987 Reinforcement shuttering checking & Pouring of M30 Retaining wall for wall casting 154+085 154+140 55 LHS 4/18/2022
1 0.3 1.8 0.54 Cum
976 NH-39/STR/988 Layout,OGL Checking and excavation for foundation VUP 110+030 15.65 RHS 4/18/2022
1 14 4 56 Cum
977 NH-39/STR/989 4/19/2022
978 NH-39/STR/990 Checking of Foundation bed PCC for VUP 110+030 13.65 RHS 4/20/2022
1 12 0.1 1.2 Cum
979 NH-39/STR/991 Dismentling of exiting MNB 93+843 RHS 4/12/2022
981 NH-39/STR/993
982 NH-39/STR/994
983 NH-39/STR/995 Reinforcement shuttering checking & Pouring of M35 MNB wall 1st lift casting 155+384 14.383 LHS 4/9/2022
7 0.4 1.5 4.2 Cum 44661
984 NH-39/STR/996 Reinforcement shuttering checking & Pouring of M35 MNB wall 1st lift casting 155+384 14.383 RHS 4/10/2022
7 0.4 1.5 4.2 Cum
985 NH-39/STR/997 Reinforcement shuttering checking & Pouring of M35 MNB wall final lift casting 155+384 14.383 LHS 4/11/2022
7 0.4 1.5 4.2 Cum 44661
986 NH-39/STR/998 Reinforcement shuttering checking & Pouring of M35 MNB wall final lift casting 155+384 14.383 RHS 4/12/2022
7 0.4 1.5 4.2 Cum
987 NH-39/STR/999
988 NH-39/STR/1000
989 NH-39/STR/1001
990 NH-39/STR/1002
991 NH-39/STR/1003
992 NH-39/STR/1004
993 NH-39/STR/1005
994 NH-39/STR/1006
995 NH-39/STR/1007
996 NH-39/STR/1008
997 NH-39/STR/1009
RFI SUMMARY (STRUCTURE)
S.No RFI NO. Item Description Chainage Length Side NOS Width Height Qty Unit Details of Inspection
From To Date Time
998 NH-39/STR/1010
999 NH-39/STR/1011
1000 NH-39/STR/1012
1001 NH-39/STR/1013
1002 NH-39/STR/1014
1003 NH-39/STR/1015
1004 NH-39/STR/1016
1005 NH-39/STR/1017
1006 NH-39/STR/1018
1007 NH-39/STR/1019
1008 NH-39/STR/1020
1009 NH-39/STR/1021
1010 NH-39/STR/1022
1011 NH-39/STR/1023
1012 NH-39/STR/1024
1013 NH-39/STR/1025
1014 NH-39/STR/1026
1015 NH-39/STR/1027
1016 NH-39/STR/1028
1017 NH-39/STR/1029
1018 NH-39/STR/1030
1019 NH-39/STR/1031
1020 NH-39/STR/1032
1021 NH-39/STR/1033
1022 NH-39/STR/1034
1023 NH-39/STR/1035
1024 NH-39/STR/1036
1025 NH-39/STR/1037
1026 NH-39/STR/1038
1027 NH-39/STR/1039
1028 NH-39/STR/1040
1029 NH-39/STR/1041
1030 NH-39/STR/1042
1031 NH-39/STR/1043
1032 NH-39/STR/1044
1033 NH-39/STR/1045
1034 NH-39/STR/1046
RFI SUMMARY (STRUCTURE)
S.No RFI NO. Item Description Chainage Length Side NOS Width Height Qty Unit Details of Inspection
From To Date Time
1035 NH-39/STR/1047
1036 NH-39/STR/1048
1037 NH-39/STR/1049
1038 NH-39/STR/1050 Reinforcement shuttering checking & Pouring of M35 Raft casting VUP 110+030 13.65 RHS 4/25/2022
1 12 0.85 10.2 Cum
1039 NH-39/STR/1051 Reinforcement shuttering checking & Pouring of M35 MNB SLAB casting 155+384 32.95 LHS 4/25/2022
1 14.383 0.4 5.7532 Cum 44661
1040 NH-39/STR/1052 Reinforcement shuttering checking & Pouring of M35 MNB SLAB casting 155+384 32.95 RHS 4/26/2022
1 14.383 0.4 5.7532 Cum
1041 NH-39/STR/1053
1042 NH-39/STR/1054
1043 NH-39/STR/1055 Checking of Toe wall excavation 109+755 109+855 100 LHS 4/26/2022
1044 NH-39/STR/1056 Checking of Retaining wall excavation 154+035 154+224 189 LHS 4/26/2022
1045 NH-39/STR/1057 Checking of Toe wall PCC 109+755 109+855 100 LHS 4/26/2022
1046 NH-39/STR/1058 Checking of Retaining wall PCC 154+035 154+124 89 LHS 4/26/2022
1047 NH-39/STR/1059 Reinforcement shuttering checking & Pouring of M35 wall 1st lift casting VUP 110+030 12 RHS 4/27/2022
2 0.825 1.5 2.475 Cum
1048 NH-39/STR/1060
1049 NH-39/STR/1061
1050 NH-39/STR/1062
1051 NH-39/STR/1063
1052 NH-39/STR/1064
1053 NH-39/STR/1065 Reinforcement shuttering checking & Pouring of M35 wall 2nd lift casting VUP 110+030 12 RHS 4/28/2022
2 0.825 1.5 2.475 Cum
1054 NH-39/STR/1066
1055 NH-39/STR/1067
1056 NH-39/STR/1068 Reinforcement & Shuttering checking for Raft (VUP) 110+030 RHS 4/27/2022
1057 NH-39/STR/1069 Checking of Retaining wall PCC 154+124 154+224 100 LHS 4/27/2022
1058 NH-39/STR/1070 Checking Pouring of concrete M20 Toe wall RAFT 109+755 109+855 100 LHS 4/27/2022
1059 NH-39/STR/1071
1060 NH-39/STR/1072
1061 NH-39/STR/1073
1062 NH-39/STR/1074
1063 NH-39/STR/1075
1064 NH-39/STR/1076
1065 NH-39/STR/1077
1066 NH-39/STR/1078
1067 NH-39/STR/1079 checking pouring of concrete M35 Raft (VUP) 110+030 RHS 4/27/2022
1068 NH-39/STR/1080 Checking Pouring of concrete M20 Toe wall wall casting 109+755 109+855 100 LHS 4/27/2022
1069 NH-39/STR/1081
1070 NH-39/STR/1082
1071 NH-39/STR/1083
RFI SUMMARY (STRUCTURE)
S.No RFI NO. Item Description Chainage Length Side NOS Width Height Qty Unit Details of Inspection
From To Date Time
1072 NH-39/STR/1084
1073 NH-39/STR/1085
1074 NH-39/STR/1086
1075 NH-39/STR/1087 checking pouring of concrete M35 Raft (VUP) 110+030 RHS 4/29/2022
1076 NH-39/STR/1088 Reinforcement & Shuttering checking for slab (VUP) 169+006 RHS 4/29/2022
1077 NH-39/STR/1089 Reinforcement shuttering checking & Pouring of M35 wall final lift casting VUP 110+030 12 RHS 4/29/2022
2 0.825 1.5 2.475 Cum
1078 NH-39/STR/1090
1079 NH-39/STR/1091
1080 NH-39/STR/1092
1081 NH-39/STR/1093
1082 NH-39/STR/1094
1083 NH-39/STR/1095
1084 NH-39/STR/1096
1085 NH-39/STR/1097 Reinforcement & Shuttering checking for slab (VUP) 169+006 RHS 4/30/2022
1086 NH-39/STR/1098 Checking pouring of Concrete M-35 SLAB (VUP) 169+006 RHS 4/30/2022
1087 NH-39/STR/1099 Reinforcrmrnt & shuttering checking for SLAB (MNB) 155+800 RHS 4/30/2022
1088 NH-39/STR/1100 Checking pouring of Concrete M-35 SLAB (MNB) 155+800 RHS 4/30/2022
1089 NH-39/STR/1101
1090 NH-39/STR/1102
1091 NH-39/STR/1103
1092 NH-39/STR/1104
1093 NH-39/STR/1105
1094 NH-39/STR/1106
1095 NH-39/STR/1107
1096 NH-39/STR/1108
1097 NH-39/STR/1109
1098 NH-39/STR/1110
1099 NH-39/STR/1111 Reinforcement & Shuttering checking for slab (VUP) 169+006 RHS 5/1/2022
1100 NH-39/STR/1112 Reinforcement & Shuttering checking pouring of concrete M30 Raft (Retaining wall ) 154+124 154+184 60 LHS 5/1/2022
1101 NH-39/STR/1113 Checking of Toe wall excavation 109+855 109+955 100 LHS 5/1/2022
1102 NH-39/STR/1114
1103 NH-39/STR/1115
1104 NH-39/STR/1116
1105 NH-39/STR/1117
1106 NH-39/STR/1118
1107 NH-39/STR/1119
1108 NH-39/STR/1120
RFI SUMMARY (STRUCTURE)
S.No RFI NO. Item Description Chainage Length Side NOS Width Height Qty Unit Details of Inspection
From To Date Time
1109 NH-39/STR/1121
1110 NH-39/STR/1122
1111 NH-39/STR/1123
1112 NH-39/STR/1124
1113 NH-39/STR/1125
1114 NH-39/STR/1126
1115 NH-39/STR/1127
1116 NH-39/STR/1128
1117 NH-39/STR/1129
1118 NH-39/STR/1130 Reinforcement & Shuttering checking for slab (VUP) 169+006 RHS 5/2/2022
1119 NH-39/STR/1131 Reinforcement & Shuttering checking pouring of concrete M30 Raft (Retaining wall ) 154+184 154+224 40 LHS 5/2/2022
1120 NH-39/STR/1132 Checking of Toe wall PCC 109+855 109+955 100 LHS 5/2/2022
1121 NH-39/STR/1133 Layout ,OGL Checking and excavation for foundation P2 Pier (MNB) 167+454 LHS 5/2/2022
1122 NH-39/STR/1134
1123 NH-39/STR/1135
1124 NH-39/STR/1136
1125 NH-39/STR/1137
1126 NH-39/STR/1138
1127 NH-39/STR/1139
1128 NH-39/STR/1140
1129 NH-39/STR/1141
1130 NH-39/STR/1142
1131 NH-39/STR/1143
1132 NH-39/STR/1144
1133 NH-39/STR/1145
1134 NH-39/STR/1146
1135 NH-39/STR/1147
1136 NH-39/STR/1148
1137 NH-39/STR/1149
1138 NH-39/STR/1150
1139 NH-39/STR/1151
1140 NH-39/STR/1152
1141 NH-39/STR/1153
1142 NH-39/STR/1154 Reinforcement & Shuttering checking pouring of concrete M30 WALL (Retaining wall ) 154+124 154+184 60 LHS 5/3/2022
1143 NH-39/STR/1155 Checking of Toe wall Raft casting 109+855 109+955 100 LHS 5/3/2022
1144 NH-39/STR/1156 Layout ,OGL Checking and excavation of Abutment A2 foundation (MNB) 146+938 RHS 5/3/2022
1145 NH-39/STR/1157
RFI SUMMARY (STRUCTURE)
S.No RFI NO. Item Description Chainage Length Side NOS Width Height Qty Unit Details of Inspection
From To Date Time
1146 NH-39/STR/1158
1147 NH-39/STR/1159
1148 NH-39/STR/1160
1149 NH-39/STR/1161
1150 NH-39/STR/1162
1151 NH-39/STR/1163
1152 NH-39/STR/1164
1153 NH-39/STR/1165
1154 NH-39/STR/1166
1155 NH-39/STR/1167
1156 NH-39/STR/1168
1157 NH-39/STR/1169
1158 NH-39/STR/1170 Reinforcement & Shuttering checking pouring of concrete M30 WALL (Retaining wall ) 154+184 154+224 40 LHS 5/3/2022
1159 NH-39/STR/1171 Checking of Toe wall wall casting 109+855 109+905 50 LHS 5/3/2022
1160 NH-39/STR/1172 Shuttering checking of Pouring of P2 foundation Bed PCC (MNB) 167+454 LHS 5/3/2022
1161 NH-39/STR/1173
1162 NH-39/STR/1174
1163 NH-39/STR/1175
1164 NH-39/STR/1176
1165 NH-39/STR/1177
1166 NH-39/STR/1178
1167 NH-39/STR/1179
1168 NH-39/STR/1180
1169 NH-39/STR/1181
1170 NH-39/STR/1182
1171 NH-39/STR/1183
1172 NH-39/STR/1184
1173 NH-39/STR/1185
1174 NH-39/STR/1186
1175 NH-39/STR/1187
1176 NH-39/STR/1188
1177 NH-39/STR/1189
1178 NH-39/STR/1190 Checking of Retaining wall PCC 154+035 154+124 89 LHS 5/4/2022
1179 NH-39/STR/1191 Checking of Toe wall wall casting 109+905 109+955 50 LHS 5/4/2022
1180 NH-39/STR/1192
1181 NH-39/STR/1193
1182 NH-39/STR/1194
RFI SUMMARY (STRUCTURE)
S.No RFI NO. Item Description Chainage Length Side NOS Width Height Qty Unit Details of Inspection
From To Date Time
1183 NH-39/STR/1195
1184 NH-39/STR/1196
1185 NH-39/STR/1197
1186 NH-39/STR/1198
1187 NH-39/STR/1199
1188 NH-39/STR/1200
1189 NH-39/STR/1201
1190 NH-39/STR/1202
1191 NH-39/STR/1203
1192 NH-39/STR/1204
1193 NH-39/STR/1205
1194 NH-39/STR/1206 Checking of Retaining wall raft casting 154+035 154+124 89 LHS 5/6/2022
1195 NH-39/STR/1207 Checking of Toe wall Excavation 109+955 110+055 100 LHS 5/6/2022
1196 NH-39/STR/1208
1197 NH-39/STR/1209
1198 NH-39/STR/1210
1199 NH-39/STR/1211
1200 NH-39/STR/1212
1201 NH-39/STR/1213
1202 NH-39/STR/1214
1203 NH-39/STR/1215
1204 NH-39/STR/1216 Reinforcemet & shuttering Checking pouring of concrete M30 Retaining wall for wall casti 154+035 154+124 89 LHS 5/7/2022
1205 NH-39/STR/1217 Checking of Toe wall PCC 109+955 110+055 100 LHS 5/7/2022
1206 NH-39/STR/1218 shuttering Checking pouring of concrete M30 for SLAB (VUP) 169+006 RHS 5/7/2022
1207 NH-39/STR/1219
1208 NH-39/STR/1220
1209 NH-39/STR/1221
1210 NH-39/STR/1222
1211 NH-39/STR/1223
1212 NH-39/STR/1224
1213 NH-39/STR/1225
1214 NH-39/STR/1226
1215 NH-39/STR/1227
1216 NH-39/STR/1228
1217 NH-39/STR/1229
1218 NH-39/STR/1230
1219 NH-39/STR/1231
RFI SUMMARY (STRUCTURE)
S.No RFI NO. Item Description Chainage Length Side NOS Width Height Qty Unit Details of Inspection
From To Date Time
1220 NH-39/STR/1232
1221 NH-39/STR/1233
1222 NH-39/STR/1234
1223 NH-39/STR/1235
1224 NH-39/STR/1236
1225 NH-39/STR/1237
1226 NH-39/STR/1238
1227 NH-39/STR/1239
1228 NH-39/STR/1240
1229 NH-39/STR/1241
1230 NH-39/STR/1242
1231 NH-39/STR/1243
1232 NH-39/STR/1244
1233 NH-39/STR/1245
1234 NH-39/STR/1246
1235 NH-39/STR/1247 Layout ,OGL Checking and excavationfor Retaining wall 156+180 156+280 100 LHS 5/10/2022
1236 NH-39/STR/1248 Checking of Toe wall Raft 109+955 100 LHS 5/10/2022
1237 NH-39/STR/1249
1238 NH-39/STR/1250
1239 NH-39/STR/1251
1240 NH-39/STR/1252
1241 NH-39/STR/1253
1242 NH-39/STR/1254
1243 NH-39/STR/1255
1244 NH-39/STR/1256
1245 NH-39/STR/1257
1246 NH-39/STR/1258
1247 NH-39/STR/1259
1248 NH-39/STR/1260
1249 NH-39/STR/1261
1250 NH-39/STR/1262
1251 NH-39/STR/1263
1252 NH-39/STR/1264 Checking of PCC Retaining wall 156+180 156+280 100 LHS 5/11/2022
1253 NH-39/STR/1265 Checking of Toe wall WALL casting 109+955 110+005 50 LHS 5/11/2022
1254 NH-39/STR/1266 shuttering Checking pouring of concrete M35 for SLAB (VUP) 169+006 RHS 5/11/2022
1255 NH-39/STR/1267
1256 NH-39/STR/1268
RFI SUMMARY (STRUCTURE)
S.No RFI NO. Item Description Chainage Length Side NOS Width Height Qty Unit Details of Inspection
From To Date Time
1257 NH-39/STR/1269
1258 NH-39/STR/1270
1259 NH-39/STR/1271
1260 NH-39/STR/1272
1261 NH-39/STR/1273
1262 NH-39/STR/1274
1263 NH-39/STR/1275
1264 NH-39/STR/1276
1265 NH-39/STR/1277
1266 NH-39/STR/1278 Checking of Retaining wall raft casting 156+180 156+280 100 LHS 5/12/2022
1267 NH-39/STR/1279 Checking of Toe wall WALL casting 110+005 110+055 50 LHS 5/12/2022
1268 NH-39/STR/1280
1269 NH-39/STR/1281
1270 NH-39/STR/1282
1271 NH-39/STR/1283
1272 NH-39/STR/1284
1273 NH-39/STR/1285
1274 NH-39/STR/1286
1275 NH-39/STR/1287
1276 NH-39/STR/1288 Reinforcemet & shuttering Checking pouring of concrete M30 Retaining wall for wall casti 156+180 156+230 50 LHS 5/13/2022
1277 NH-39/STR/1289
1278 NH-39/STR/1290
1279 NH-39/STR/1291
1280 NH-39/STR/1292
1281 NH-39/STR/1293
1282 NH-39/STR/1294
1283 NH-39/STR/1295 Reinforcemet & shuttering Checking pouring of concrete M30 Retaining wall for wall casti 156+230 156+280 50 LHS 5/14/2022
1284 NH-39/STR/1296
1285 NH-39/STR/1297
1286 NH-39/STR/1298
1287 NH-39/STR/1299
1288 NH-39/STR/1300
1289 NH-39/STR/1301
1290 NH-39/STR/1302
1291 NH-39/STR/1303 Layout ,OGL Checking and excavationfor Retaining wall 155+710 155+810 100 RHS 5/15/2022
1292 NH-39/STR/1304
1293 NH-39/STR/1305
RFI SUMMARY (STRUCTURE)
S.No RFI NO. Item Description Chainage Length Side NOS Width Height Qty Unit Details of Inspection
From To Date Time
1294 NH-39/STR/1306
1295 NH-39/STR/1307
1296 NH-39/STR/1308
1297 NH-39/STR/1309
1298 NH-39/STR/1310
1299 NH-39/STR/1311 Checking of PCC Retaining wall 155+710 155+810 100 RHS 5/16/2022
1300 NH-39/STR/1312
1301 NH-39/STR/1313
1302 NH-39/STR/1314
1303 NH-39/STR/1315
1304 NH-39/STR/1316
1305 NH-39/STR/1317
1306 NH-39/STR/1318
1307 NH-39/STR/1319 Checking of Retaining wall raft casting 155+710 155+810 100 RHS 5/17/2022
1308 NH-39/STR/1320
1309 NH-39/STR/1321
1310 NH-39/STR/1322
1311 NH-39/STR/1323
1312 NH-39/STR/1324
1313 NH-39/STR/1325
1314 NH-39/STR/1326
1315 NH-39/STR/1327
1316 NH-39/STR/1328 Reinforcemet & shuttering Checking pouring of concrete M30 Retaining wall for wall casti 155+710 155+760 50 RHS 5/18/2022
1317 NH-39/STR/1329
1318 NH-39/STR/1330
1319 NH-39/STR/1331
1320 NH-39/STR/1332
1321 NH-39/STR/1333
1322 NH-39/STR/1334
1323 NH-39/STR/1335 Reinforcemet & shuttering Checking pouring of concrete M30 Retaining wall for wall casti 155+760 155+810 50 RHS 5/19/2022
1324 NH-39/STR/1336
1325 NH-39/STR/1337
1326 NH-39/STR/1338
1327 NH-39/STR/1339
1328 NH-39/STR/1340
1329 NH-39/STR/1341
1330 NH-39/STR/1342
RFI SUMMARY (STRUCTURE)
S.No RFI NO. Item Description Chainage Length Side NOS Width Height Qty Unit Details of Inspection
From To Date Time
1331 NH-39/STR/1343
1332 NH-39/STR/1344
1333 NH-39/STR/1345 Layout ,OGL Checking and excavationfor Toe wall 171+130 171+230 100 LHS 5/20/2022
1334 NH-39/STR/1346
1335 NH-39/STR/1347
1336 NH-39/STR/1348
1337 NH-39/STR/1349
1338 NH-39/STR/1350
1339 NH-39/STR/1351 Checking of Toe wall PCC 171+130 171+230 100 LHS 5/21/2022
1340 NH-39/STR/1352
1341 NH-39/STR/1353
1342 NH-39/STR/1354
1343 NH-39/STR/1355
1344 NH-39/STR/1356
1345 NH-39/STR/1357
1346 NH-39/STR/1358 Checking of Toe wall Raft 171+130 171+230 100 LHS 5/22/2022
1347 NH-39/STR/1359
1348 NH-39/STR/1360
1349 NH-39/STR/1361
1350 NH-39/STR/1362
1351 NH-39/STR/1363
1352 NH-39/STR/1364
1353 NH-39/STR/1365
1354 NH-39/STR/1366
1355 NH-39/STR/1367
1356 NH-39/STR/1368 Checking of Toe wall WALL casting 171+130 171+180 50 LHS 5/23/2022
1357 NH-39/STR/1369
1358 NH-39/STR/1370
1359 NH-39/STR/1371
1360 NH-39/STR/1372
1361 NH-39/STR/1373
1362 NH-39/STR/1374
1363 NH-39/STR/1375 Checking of Toe wall WALL casting 171+180 171+230 50 LHS 5/24/2022
1364 NH-39/STR/1376
1365 NH-39/STR/1377
1366 NH-39/STR/1378
1367 NH-39/STR/1379
RFI SUMMARY (STRUCTURE)
S.No RFI NO. Item Description Chainage Length Side NOS Width Height Qty Unit Details of Inspection
From To Date Time
1368 NH-39/STR/1380
1369 NH-39/STR/1381
1370 NH-39/STR/1382
1371 NH-39/STR/1383
1372 NH-39/STR/1384
1373 NH-39/STR/1385
1374 NH-39/STR/1386
1375 NH-39/STR/1387
1376 NH-39/STR/1388
1377 NH-39/STR/1389
1378 NH-39/STR/1390
1379 NH-39/STR/1391
1380 NH-39/STR/1392
1381 NH-39/STR/1393 Layout ,OGL Checking and excavationfor Toe wall 171+230 171+330 100 LHS 5/24/2022
1382 NH-39/STR/1394
1383 NH-39/STR/1395
1384 NH-39/STR/1396
1385 NH-39/STR/1397
1386 NH-39/STR/1398 Layout ,OGL Checking and excavation for Toe wall 171+230 171+330 100 LHS 5/27/2022
1387 NH-39/STR/1399
1388 NH-39/STR/1400
1389 NH-39/STR/1401
1390 NH-39/STR/1402
1391 NH-39/STR/1403
1392 NH-39/STR/1404
1393 NH-39/STR/1405 Checking of Toe wall PCC 171+230 171+330 100 LHS 5/28/2022
1394 NH-39/STR/1406
1395 NH-39/STR/1407
1396 NH-39/STR/1408
1397 NH-39/STR/1409
1398 NH-39/STR/1410
1399 NH-39/STR/1411 Checking of Toe wall Raft 171+230 171+330 100 LHS 5/29/2022
1400 NH-39/STR/1412
1401 NH-39/STR/1413
1402 NH-39/STR/1414
1403 NH-39/STR/1415
1404 NH-39/STR/1416
RFI SUMMARY (STRUCTURE)
S.No RFI NO. Item Description Chainage Length Side NOS Width Height Qty Unit Details of Inspection
From To Date Time
1405 NH-39/STR/1417
1406 NH-39/STR/1418
1407 NH-39/STR/1419
1408 NH-39/STR/1420
1409 NH-39/STR/1421 Checking of Toe wall M20 wall final lift casting 171+230 171+280 50 LHS 5/30/2022
1410 NH-39/STR/1422 checking of Pouring M15 A2 foundation PCC (MNB) 146+938 RHS 5/30/2022
1411 NH-39/STR/1423
1412 NH-39/STR/1424
1413 NH-39/STR/1425
1414 NH-39/STR/1426
1415 NH-39/STR/1427
1416 NH-39/STR/1428
1417 NH-39/STR/1429
1418 NH-39/STR/1430
1419 NH-39/STR/1431
1420 NH-39/STR/1432 Checking of Toe wall M20 wall final lift casting 171+280 171+330 50 LHS 5/31/2022
1421 NH-39/STR/1433
1422 NH-39/STR/1434
1423 NH-39/STR/1435
1424 NH-39/STR/1436
1425 NH-39/STR/1437
1426 NH-39/STR/1438 Checking of Toe wall Foundation PCC M15 171+330 171+430 100 LHS 6/1/2022
1427 NH-39/STR/1439 Reinforcemet & shuttering checking Pouring of A2 Abutment foundation 146+938 RHS 6/1/2022
1428 NH-39/STR/1440 Checking of Toe wall M20 wall final lift casting 171+580 171+610 30 LHS 6/1/2022
1429 NH-39/STR/1441 Layout ,OGL Checking and excavation for Retaining wall 171+130 171+200 70 RHS 6/1/2022
1430 NH-39/STR/1442 Checking of Toe wall M20 wall final lift casting 171+330 171+380 50 LHS 6/1/2022
1431 NH-39/STR/1443 Reinforcemet & shuttering Checking pouring of concrete M35 VUP Median portion Raft Fo 169+006 BHS 6/1/2022
1432 NH-39/STR/1444 Layout ,OGL Checking and excavation for Retaining wall 171+200 171+230 30 RHS 6/1/2022
1433 NH-39/STR/1445 Checking of Toe wall M20 Raft casting 171+330 171+430 100 LHS 6/2/2022
1434 NH-39/STR/1446 Checking of Toe wall M20 wall final lift casting 171+430 171+450 20 LHS 6/2/2022
1435 NH-39/STR/1447 Checking of Toe wall M20 wall final lift casting 171+550 171+580 30 LHS 6/2/2022
1436 NH-39/STR/1448 Reinforcemet & shuttering checking Pouring of A2 Abutment foundation 146+938 RHS 6/2/2022
1437 NH-39/STR/1449 Checking of Toe wall M20 wall final lift casting 171+580 171+610 30 LHS 6/2/2022
1438 NH-39/STR/1450 Layout ,OGL Checking and excavation for Retaining wall 171+130 171+230 100 RHS 6/2/2022
1439 NH-39/STR/1451 Checking of Toe wall M20 wall final lift casting 171+330 171+380 50 LHS 6/2/2022
1440 NH-39/STR/1452 Reinforcemet & shuttering Checking pouring of concrete M35 VUP Median portion Raft Fo 169+006 BHS 6/2/2022
1441 NH-39/STR/1453 Checking of Toe wall M20 wall final lift casting 171+330 171+380 50 LHS 6/3/2022
RFI SUMMARY (STRUCTURE)
S.No RFI NO. Item Description Chainage Length Side NOS Width Height Qty Unit Details of Inspection
From To Date Time
1442 NH-39/STR/1454 Reinforcemet & shuttering Checking of M35 VUP Median portion Raft Foundation 169+006 BHS 6/3/2022
1443 NH-39/STR/1455 Checking of Toe wall M20 wall final lift casting 171+380 171+430 50 LHS 6/3/2022
1444 NH-39/STR/1456 Checking pouring of concrete M35 VUP Median portion Raft Foundation 169+006 BHS 6/3/2022
1445 NH-39/STR/1457 Checking of Toe wall Foundation PCC M15 171+430 171+460 30 LHS 6/3/2022
1446 NH-39/STR/1458 Checking of Toe wall Foundation PCC M15 171+480 171+500 20 LHS 6/3/2022
1447 NH-39/STR/1459 Checking of Toe wall M20 wall final lift casting 171+380 171+430 50 LHS 6/4/2022
1448 NH-39/STR/1460 Reinforcemet & shuttering Checking pouring of concrete M35 VUP Median portion Raft Fo 169+006 BHS 6/4/2022
1449 NH-39/STR/1461 Layout ,OGL Checking and excavation for Toe wall 171+430 171+480 50 LHS 6/4/2022
1450 NH-39/STR/1462 Layout ,OGL Checking and excavation for Toe wall 171+480 171+530 50 LHS 6/4/2022
1451 NH-39/STR/1463 Reinforcemet & shuttering Checking pouring of concrete M35 VUP Median portion Raft Fo 169+006 BHS 6/5/2022
1452 NH-39/STR/1464 Checking of Toe wall M20 Raft casting 171+430 171+450 20 LHS 6/5/2022
1453 NH-39/STR/1465 Checking of Toe wall M20 Raft casting 171+480 171+510 30 LHS 6/5/2022
1454 NH-39/STR/1466 Checking of Toe wall M20 Raft casting 171+580 171+610 30 LHS 6/5/2022
1455 NH-39/STR/1467 Reinforcemet & shuttering Checking pouring of concrete M35 VUP Median portion Raft Fo 169+006 BHS 6/6/2022
1456 NH-39/STR/1468 Checking of Toe wall Foundation PCC M15 171+430 171+460 30 LHS 6/6/2022
1457 NH-39/STR/1469 Checking of Toe wall Foundation PCC M15 171+480 171+500 20 LHS 6/6/2022
1458 NH-39/STR/1470 Checking of Toe wall Foundation PCC M15 171+510 171+530 20 LHS 6/6/2022
1459 NH-39/STR/1471 Layout ,OGL Checking and excavation for Toe wall 171+430 171+530 100 LHS 6/7/2022
1460 NH-39/STR/1472 Checking of Toe wall Foundation PCC M15 171+430 171+530 100 LHS 6/7/2022
1461 NH-39/STR/1473 Checking of Toe wall M20 wall final lift casting 171+580 171+610 30 LHS 6/7/2022
1462 NH-39/STR/1474 Layout ,OGL Checking and excavation for Retaining wall 171+130 171+200 70 RHS 6/7/2022
1463 NH-39/STR/1475 Checking of Toe wall M20 Raft casting 171+430 171+510 80 LHS 6/7/2022
1464 NH-39/STR/1476 Checking of Toe wall M20 Raft casting 171+430 171+530 100 LHS 6/8/2022
1465 NH-39/STR/1477 Checking of Toe wall M20 wall final lift casting 171+430 171+450 20 LHS 6/8/2022
1466 NH-39/STR/1478 Checking of Toe wall M20 wall final lift casting 171+550 171+580 30 LHS 6/8/2022
1467 NH-39/STR/1479 Reinforcemet & shuttering checking Pouring of A2 Abutment foundation 146+938 RHS 6/8/2022
1468 NH-39/STR/1480 Checking of Toe wall M20 wall final lift casting 171+580 171+610 30 LHS 6/8/2022
1469 NH-39/STR/1481 Layout ,OGL Checking and excavation for Retaining wall 171+130 171+230 100 RHS 6/8/2022
1470 NH-39/STR/1482 Checking of Toe wall M20 Raft casting 171+430 171+530 100 LHS 6/8/2022
1471 NH-39/STR/1483 Checking of Toe wall M20 wall final lift casting 171+430 171+480 50 LHS 6/9/2022
1472 NH-39/STR/1484 Checking of Toe wall M20 wall final lift casting 171+550 171+580 30 LHS 6/9/2022
1473 NH-39/STR/1485 Reinforcemet & shuttering checking Pouring of A2 Abutment foundation 146+938 RHS 6/9/2022
1474 NH-39/STR/1486 Layout ,OGL Checking and excavation for Toe wall 171+530 171+630 100 LHS 6/9/2022
1475 NH-39/STR/1487 Reinforcemet & shuttering checking A2 Abutment foundation 146+938 RHS 6/9/2022
1476 NH-39/STR/1488 Checking of Toe wall M20 wall final lift casting 171+430 171+480 50 LHS 6/10/2022
1477 NH-39/STR/1489 Reinforcemet & shuttering checking A2 Abutment foundation 146+938 RHS 6/10/2022
1478 NH-39/STR/1490 Reinforcemet & shuttering checking A2 Abutment foundation 146+938 RHS 6/10/2022
RFI SUMMARY (STRUCTURE)
S.No RFI NO. Item Description Chainage Length Side NOS Width Height Qty Unit Details of Inspection
From To Date Time
1479 NH-39/STR/1491 Reinforcemet & shuttering checking A2 Abutment foundation 146+938 RHS 6/10/2022
1480 NH-39/STR/1492 Checking of Toe wall M20 wall final lift casting 171+530 171+550 20 LHS 6/10/2022
1481 NH-39/STR/1493 Layout ,OGL Checking and excavation for Retaining wall 171+130 171+230 100 RHS 6/10/2022
1482 NH-39/STR/1494 Checking of Toe wall M20 wall final lift casting 171+480 171+530 50 LHS 6/11/2022
1483 NH-39/STR/1495 Reinforcemet & shuttering checking A2 Abutment foundation 146+938 RHS 6/11/2022
1484 NH-39/STR/1496 Layout ,OGL Checking and excavation for Toe wall 171+530 171+630 100 LHS 6/12/2022
1485 NH-39/STR/1497 Reinforcemet & shuttering checking A2 Abutment foundation 146+938 RHS 6/12/2022
1486 NH-39/STR/1498 Reinforcemet & shuttering checking A2 Abutment foundation 146+938 RHS 6/13/2022
1487 NH-39/STR/1499 Checking of Toe wall M20 Raft casting 171+530 171+630 100 LHS 6/13/2022
1488 NH-39/STR/1500 Reinforcemet & shuttering checking and pouring 1st lift median portion wall VUP 169+006 RHS 6/13/2022
1489 NH-39/STR/1501 Reinforcemet & shuttering checking Pouring of A2 Abutment foundation 146+938 RHS 6/14/2022
1490 NH-39/STR/1502 Checking of Toe wall M20 wall final lift casting 171+530 171+550 20 LHS 6/14/2022
1491 NH-39/STR/1503 Layout ,OGL Checking and excavation for Retaining wall 171+130 171+230 100 RHS 6/14/2022
1492 NH-39/STR/1504 Reinforcemet & shuttering checking and pouring 1st lift median portion wall VUP 169+006 RHS 6/14/2022
1493 NH-39/STR/1505 Checking of Toe wall M20 wall final lift casting 171+550 171+580 30 LHS 6/14/2022
1494 NH-39/STR/1506 Reinforcemet & shuttering checking Pouring of A2 Abutment foundation 146+938 RHS 6/15/2022
1495 NH-39/STR/1507 Checking of Toe wall M20 wall final lift casting 171+580 171+610 30 LHS 6/15/2022
1496 NH-39/STR/1508 Layout ,OGL Checking and excavation for Retaining wall 171+130 171+230 100 RHS 6/15/2022
1497 NH-39/STR/1509 Reinforcemet & shuttering checking and pouring 1st lift median portion wall VUP 169+006 RHS 6/15/2022
1498 NH-39/STR/1510 Checking of Toe wall M20 wall final lift casting 171+610 171+630 20 LHS 6/15/2022
1499 NH-39/STR/1511 Reinforcemet & shuttering checking Pouring of A2 Abutment foundation 146+938 RHS 6/16/2022
1500 NH-39/STR/1512 Checking of Toe wall M20 wall final lift casting 171+580 171+610 30 LHS 6/16/2022
1501 NH-39/STR/1513 Layout ,OGL Checking and excavation for Retaining wall 171+130 171+230 100 RHS 6/16/2022
1502 NH-39/STR/1514 Reinforcemet & shuttering checking and pouring 1st lift median portion wall VUP 169+006 RHS 6/16/2022
1503 NH-39/STR/1515 Checking of Toe wall M20 wall final lift casting 171+610 171+630 20 LHS 6/16/2022
1504 NH-39/STR/1516 Checking of Toe wall M20 Raft casting 171+530 171+630 100 LHS 6/17/2022
100 44729
1505 NH-39/STR/1517 Reinforcemet & shuttering checking Pouring M35 of A2 Abutment foundation 146+938 RHS 6/17/2022
44729
1506 NH-39/STR/1518 Reinforcemet & shuttering checking and pouring M35 1st lift median portion wall VUP 169+006 RHS 6/17/2022
44729
1507 NH-39/STR/1519 checking Pouring Concrete M35 of A2 Abutment foundation 146+938 RHS 6/17/2022
44729
1508 NH-39/STR/1520 Reinforcemet & shuttering checking of 1st lift median portion wall VUP 169+006 RHS 6/18/2022
44730
1509 NH-39/STR/1521 Checking pouring of Concrete M35 1st lift median portion wall VUP 169+006 RHS 6/18/2022
44730
1510 NH-39/STR/1522 Reinforcemet & shuttering checking of 2nd lift median portion wall VUP 169+006 BHS 6/19/2022
44731
1511 NH-39/STR/1523 Checking pouring of Concrete M35 2nd lift median portion wall VUP 169+006 BHS 6/19/2022
44731
1512 NH-39/STR/1524 Checking of Toe wall M20 Raft casting 171+530 171+630 100 LHS 6/20/2022
44732
1513 NH-39/STR/1525 Reinforcemet & shuttering checking of SLAB P6 &P7 (MJB) 114+443 LHS 6/20/2022
1514 NH-39/STR/1526 Checking of Toe wall M20 wall final lift casting 171+530 171+580 50 LHS 6/21/2022
1515 NH-39/STR/1527 Checking of Toe wall M20 wall final lift casting 171+580 171+630 50 LHS 6/22/2022
RFI SUMMARY (STRUCTURE)
S.No RFI NO. Item Description Chainage Length Side NOS Width Height Qty Unit Details of Inspection
From To Date Time
1516 NH-39/STR/1528 Joint verification of Structures for actual status of stretch as per schedule 'B' 82+400 187+993 105593 BHS 6/23/2022
1517 NH-39/STR/1529 Reinforcemet & shuttering checking of SLAB P6 &P7 (MJB) 114+443 LHS 6/24/2022
1518 NH-39/STR/1530 Checking Pouring of Concrete M35 Median wall 1st lift (VUP) 169+006 BHS 6/24/2022
1519 NH-39/STR/1531 Joint verification of Structures for actual status of stretch as per schedule 'B' 82+400 137+000 54600 BHS 6/24/2022
1520 NH-39/STR/1532 checking Pouring of Concrete M40 SLAB P6 &P7 (MJB) 114+443 LHS 6/24/2022
1521 NH-39/STR/1533 Reinforcemet & shuttering checking of 2nd lift wall (VUP) 169+006 BHS 6/25/2022
1522 NH-39/STR/1534 Reinforcemet & shuttering checking of SLAB P6 &P7 (MJB) 114+443 LHS 6/25/2022
1523 NH-39/STR/1535 Reinforcemet & shuttering checking of wall final lift & SLAB (Box culvert) 158+755 LHS 6/25/2022
1524 NH-39/STR/1536 checking Pouring of Concrete M40 SLAB P6 &P7 (MJB) 114+443 LHS 6/25/2022
1525 NH-39/STR/1537 Reinforcemet & shuttering checking of SLAB P6 &P7 (MJB) 114+443 LHS 6/26/2022
1526 NH-39/STR/1538 checking Pouring of Concrete M40 SLAB P6 &P7 (MJB) 114+443 LHS 6/26/2022
1527 NH-39/STR/1539 Reinforcemet & shuttering checking of P2 Raft (MNB) 167+454 LHS 6/29/2022
1528 NH-39/STR/1540 Reinforcemet & shuttering checking of P2 Raft (MNB) 167+454 LHS 7/1/2022
1529 NH-39/STR/1541 checking Pouring of concrete M35 P2 Raft (MNB) 167+454 LHS 7/1/2022
1530 NH-39/STR/1542 Checking of Toe wall M20 wall final lift casting 171+616 171+641 25 LHS 7/1/2022
1531 NH-39/STR/1543 Checking of Toe wall M20 wall final lift casting 171+616 171+641 25 LHS 7/2/2022
1532 NH-39/STR/1544 Checking of Toe wall M20 wall final lift casting 171+641 171+661 20 LHS 7/3/2022
1533 NH-39/STR/1545 Checking of Toe wall M20 wall final lift casting 171+641 171+661 20 LHS 7/4/2022
1534 NH-39/STR/1546 checking Pouring of concrete M35 2nd lift wall (VUP) 169+006 BHS 7/4/2022
1535 NH-39/STR/1547 Checking of Toe wall M20 wall final lift casting 171+641 171+666 25 LHS 7/5/2022
1536 NH-39/STR/1548 Reinforcemet & shuttering checking of Pier P2 1st lift (MNB) 167+454 LHS 7/5/2022
1537 NH-39/STR/1549 checking Pouring of concrete M35 Pier P2 1st lift (MNB) 167+454 LHS 7/5/2022
1538 NH-39/STR/1550 checking Pouring of concrete M35 Pier P2 1st lift (MNB) 167+454 LHS 7/6/2022
1539 NH-39/STR/1551 Checking of Toe wall M20 wall final lift casting 171+666 171+686 20 LHS 7/7/2022
1540 NH-39/STR/1552 Checking of Toe wall M20 wall final lift casting 171+766 171+796 30 LHS 7/8/2022
1541 NH-39/STR/1553 Reinforcemet checking of Retaining wall Raft 163+345 163+360 15 RHS 7/21/2022
1542 NH-39/STR/1554 Shuttering checking & Pouring of concrete M30 Retaining wall Raft casting 163+345 163+360 15 RHS 7/21/2022
1543 NH-39/STR/1555 Reinforcemet checking of Retaining wall 1st lift 163+345 163+360 15 RHS 7/22/2022
1544 NH-39/STR/1556 Shuttering checking & Pouring of concrete M30 Retaining wall 1st lift casting 163+345 163+360 15 RHS 7/22/2022
1545 NH-39/STR/1557 Reinforcemet checking of Retaining wall Raft 163+330 163+345 15 RHS 7/23/2022
1546 NH-39/STR/1558 Shuttering checking & Pouring of concrete M30 Retaining wall Raft casting 163+330 163+345 15 RHS 7/23/2022
1547 NH-39/STR/1559 Reinforcemet checking of Retaining wall Raft 163+330 163+345 15 RHS 7/24/2022
1548 NH-39/STR/1560 Shuttering checking & Pouring of concrete M30 Retaining wall Raft casting 163+330 163+345 15 RHS 7/24/2022
1549 NH-39/STR/1561 Reinforcemet checking of Retaining wall Raft 163+357 163+372 15 RHS 7/27/2022
1550 NH-39/STR/1562 Shuttering checking & Pouring of concrete M30 Retaining wall 1st lift casting 163+357 163+372 15 RHS 7/27/2022
1551 NH-39/STR/1563 Shuttering checking & Pouring of concrete M30 Retaining wall 1st lift casting 163+357 163+372 15 RHS 7/28/2022
1552 NH-39/STR/1564 Shuttering checking & Pouring of concrete M30 Retaining wall 1st lift casting 163+357 163+372 15 RHS 7/29/2022
RFI SUMMARY (STRUCTURE)
S.No RFI NO. Item Description Chainage Length Side NOS Width Height Qty Unit Details of Inspection
From To Date Time
1553 NH-39/STR/1565 Shuttering checking & Pouring of concrete M30 Retaining wall 1st lift casting 163+357 163+372 15 RHS 7/29/2022
1554 NH-39/STR/1566 Reinforcemet checking of Retaining wall Raft 163+372 163+387 15 RHS 8/1/2022
1555 NH-39/STR/1567 Shuttering checking & Pouring of concrete M30 Retaining wall Raft lift casting 163+372 163+387 15 RHS 8/1/2022
1556 NH-39/STR/1568 Checking of A2 foundation level and bed pcc M15 grade concrete. 137+640 RHS 8/3/2022
1557 NH-39/STR/1569 Reinforcemet checking of Retaining wall 1st lift 163+330 163+345 15 RHS 8/4/2022
1558 NH-39/STR/1570 Shuttering checking & Pouring of concrete M30 Retaining wall 1st lift casting 163+330 163+345 15 RHS 8/4/2022
1559 NH-39/STR/1571 Layout & Excavation For Retaining wall 154+140 154+185 45 LHS 8/4/2022
1560 NH-39/STR/1572 Checking of Filter media laying For HPC 102+871 BHS 8/4/2022
1561 NH-39/STR/1573 Checking of Filter media laying For HPC 102+751 BHS 8/4/2022
1562 NH-39/STR/1574 Checking of Filter media laying For HPC 102+330 BHS 8/4/2022
1563 NH-39/STR/1575 Checking of Filter media laying For HPC 102+272 BHS 8/4/2022
1564 NH-39/STR/1576 Checking of Filter media laying For HPC 102+094 BHS 8/4/2022
1565 NH-39/STR/1577 Checking of Filter media laying For HPC 102+015 BHS 8/4/2022
1566 NH-39/STR/1578 Checking of Filter media laying For HPC 101+298 BHS 8/4/2022
1567 NH-39/STR/1579 Checking of Filter media laying For HPC 101+125 BHS 8/4/2022
1568 NH-39/STR/1580 Layout OGL checkng & Excavation for RCC Drain 103+170 103+375 205 RHS 8/4/2022
1569 NH-39/STR/1581 Layout OGL checkng & Excavation for RCC Drain 116+050 116+250 200 RHS 8/4/2022
1570 NH-39/STR/1582 Checking of stone pitching for HPC 102+330 LHS 8/4/2022
1571 NH-39/STR/1583 Checking of stone pitching for HPC 102+272 LHS 8/4/2022
1572 NH-39/STR/1584 Line Level Checking & PCC Laying For Retaining wall 154+140 154+185 45 LHS 8/4/2022
1573 NH-39/STR/1585 Checking of stone pitching for HPC 102+871 LHS 8/5/2022
1574 NH-39/STR/1586 Checking of stone pitching for HPC 102+751 LHS 8/5/2022
1575 NH-39/STR/1587 Checking of stone pitching for HPC 101+298 LHS 8/5/2022
1576 NH-39/STR/1588 Checking of stone pitching for HPC 102+330 RHS 8/5/2022
1577 NH-39/STR/1589 Checking of stone pitching for HPC 102+272 RHS 8/5/2022
1578 NH-39/STR/1590 Checking of stone pitching for HPC 102+871 RHS 8/5/2022
1579 NH-39/STR/1591 Reinforcemet checking of Retaining wall top Lift 163+345 163+360 15 RHS 8/5/2022
1580 NH-39/STR/1592 Checking of stone pitching for HPC 101+125 LHS 8/5/2022
1581 NH-39/STR/1593 Foundation PCC for RCC Drain 103+170 103+375 205 RHS 8/5/2022
1582 NH-39/STR/1594 Foundation PCC for RCC Drain 116+050 116+250 200 RHS 8/5/2022
1583 NH-39/STR/1595 Reinforcemet checking of Retaining wall top Lift 163+345 163+360 15 RHS 8/5/2022
1584 NH-39/STR/1596 Shuttering checking & Pouring of concrete M30 Retaining wall top casting 163+345 163+360 15 RHS 8/5/2022
1585 NH-39/STR/1597 Checking of stone pitching for HPC 101+298 LHS 8/6/2022
1586 NH-39/STR/1598 Checking of Filter media laying For HPC 102+015 BHS 8/6/2022
1587 NH-39/STR/1599 Checking of Filter media laying For HPC 101+298 BHS 8/6/2022
1588 NH-39/STR/1600 Checking of Filter media laying For HPC 101+125 BHS 8/6/2022
1589 NH-39/STR/1601 Checking of Filter media laying For HPC 101+040 BHS 8/6/2022
RFI SUMMARY (STRUCTURE)
S.No RFI NO. Item Description Chainage Length Side NOS Width Height Qty Unit Details of Inspection
From To Date Time
1590 NH-39/STR/1602 Checking of Filter media laying For HPC 97+400 BHS 8/6/2022
1591 NH-39/STR/1603 Reinforcement shuttering checking & pouring M20 grade RCC Drain Raft 103+170 103+375 205 RHS 8/6/2022
1592 NH-39/STR/1604 Reinforcement shuttering checking & pouring M20 grade RCC Drain Raft 116+050 116+250 200 RHS 8/6/2022
1593 NH-39/STR/1605 Layout & Excavation For Retaining wall 156+200 156+247 47 LHS 8/6/2022
1594 NH-39/STR/1606 Checking of stone pitching for HPC 97+400 LHS 8/6/2022
1595 NH-39/STR/1607 Checking of stone pitching for HPC 90+730 LHS 8/6/2022
1596 NH-39/STR/1608 Checking of Filter media laying For HPC 90+730 BHS 8/7/2022
1597 NH-39/STR/1609 Checking of Filter media laying For HPC 96+405 BHS 8/7/2022
1598 NH-39/STR/1610 Checking of Filter media laying For HPC 91+243 BHS 8/7/2022
1599 NH-39/STR/1611 Checking of Filter media laying For HPC 92+105 BHS 8/7/2022
1600 NH-39/STR/1612 Checking of stone pitching for HPC 102+015 LHS 8/7/2022
1601 NH-39/STR/1613 Checking of stone pitching for HPC 101+298 LHS 8/7/2022
1602 NH-39/STR/1614 Reinforcement shuttering checking & pouring M20 grade RCC Drain Wall 103+170 103+275 105 RHS 8/7/2022
1603 NH-39/STR/1615 Reinforcement shuttering checking & pouring M20 grade RCC Drain Wall 116+050 116+150 100 RHS 8/7/2022
1605 NH-39/STR/1617 Reinforcemet checking of Retaining wall Raft 154+140 154+185 45 LHS 8/7/2022
1606 NH-39/STR/1618 Shuttering checking & Pouring of concrete M30 Retaining wall Raft casting 154+140 154+185 45 LHS 8/7/2022
1607 NH-39/STR/1619 Checking of stone pitching for HPC 101+125 LHS 8/8/2022
1608 NH-39/STR/1620 Checking of stone pitching for HPC 101+040 LHS 8/8/2022
1609 NH-39/STR/1621 Reinforcemet checking of Retaining wall top Lift 163+330 163+345 15 RHS 8/8/2022
1610 NH-39/STR/1622 Checking of stone pitching for HPC 101+125 RHS 8/8/2022
1611 NH-39/STR/1623 Checking of stone pitching for HPC 101+298 RHS 8/8/2022
1612 NH-39/STR/1624 Checking of stone pitching for HPC 97+400 RHS 8/8/2022
1613 NH-39/STR/1625 Checking of stone pitching for HPC 92+105 LHS 8/8/2022
1614 NH-39/STR/1626 Checking of Filter media laying For HPC 92+357 BHS 8/8/2022
1615 NH-39/STR/1627 Checking of Filter media laying For HPC 92+667 BHS 8/8/2022
1616 NH-39/STR/1628 Reinforcemet checking of Retaining wall top Lift 163+330 163+345 15 RHS 8/8/2022
1617 NH-39/STR/1629 Shuttering checking & Pouring of concrete M30 Retaining wall top casting 163+330 163+345 15 RHS 8/8/2022
1618 NH-39/STR/1630 Line Level Checking & PCC Laying For Retaining wall 156+200 156+247 47 LHS 8/8/2022
1619 NH-39/STR/1631 Reinforcement shuttering checking & pouring M20 grade RCC Drain Wall 103+275 103+375 100 RHS 8/9/2022
1620 NH-39/STR/1632 Reinforcement shuttering checking & pouring M20 grade RCC Drain Wall 116+150 116+250 100 RHS 8/9/2022
1621 NH-39/STR/1633 Checking of Filter media laying For HPC 94+540 BHS 8/9/2022
1622 NH-39/STR/1634 Checking of Filter media laying For HPC 152+685 BHS 8/9/2022
1623 NH-39/STR/1635 Checking of Filter media laying For HPC 153+206 BHS 8/9/2022
1624 NH-39/STR/1636 Checking of Filter media laying For HPC 153+525 BHS 8/9/2022
1625 NH-39/STR/1637 Reinforcemet checking of Retaining wall 1st lift 163+372 163+387 15 RHS 8/9/2022
1626 NH-39/STR/1638 Shuttering checking & Pouring of concrete M30 Retaining wall 1st lift casting 163+372 163+387 15 RHS 8/9/2022
RFI SUMMARY (STRUCTURE)
S.No RFI NO. Item Description Chainage Length Side NOS Width Height Qty Unit Details of Inspection
From To Date Time
1627 NH-39/STR/1639 Layout & Excavation For Retaining wall 156+247 156+277 30 LHS 8/9/2022
1628 NH-39/STR/1640 Layout ,OGL Checking and excavation for Toe wall 109+855 109+945 90 LHS 8/10/2022
1629 NH-39/STR/1641 Layout ,OGL Checking and excavation for Toe wall 112+015 112+120 105 RHS 8/10/2022
1630 NH-39/STR/1642 Layout ,OGL Checking and excavation for Toe wall 112+250 112+400 150 RHS 8/10/2022
1631 NH-39/STR/1643 Checking of stone pitching for HPC 92+357 LHS 8/10/2022
1632 NH-39/STR/1644 Checking of stone pitching for HPC 92+667 LHS 8/10/2022
1633 NH-39/STR/1645 Checking of stone pitching for HPC 94+540 LHS 8/10/2022
1634 NH-39/STR/1646 Reinforcemet checking of Retaining wall top Lift 163+357 163+372 15 RHS 8/10/2022
1635 NH-39/STR/1647 Shuttering checking & Pouring of concrete M30 Retaining wall top casting 163+357 163+372 15 RHS 8/10/2022
1636 NH-39/STR/1648 Line Level Checking & PCC Laying For Retaining wall 156+247 156+277 30 LHS 8/10/2022
1637 NH-39/STR/1649 Checking of stone pitching for HPC 152+685 LHS 8/11/2022
1638 NH-39/STR/1650 Checking of stone pitching for HPC 90+730 RHS 8/11/2022
1639 NH-39/STR/1651 Checking of stone pitching for HPC 102+015 RHS 8/11/2022
1640 NH-39/STR/1652 Checking of Toe wall Foundation PCC M15 109+855 109+945 90 LHS 8/11/2022
1641 NH-39/STR/1653 Checking of Toe wall Foundation PCC M15 112+015 112+120 105 RHS 8/11/2022
1642 NH-39/STR/1654 Checking of Toe wall Foundation PCC M15 112+250 112+400 150 RHS 8/11/2022
1643 NH-39/STR/1655 Checking of Filter media laying For HPC 88+745 BHS 8/11/2022
1644 NH-39/STR/1656 Reinforcemet checking of Retaining wall Raft 156+247 156+277 30 LHS 8/11/2022
1645 NH-39/STR/1657 Shuttering checking & Pouring of concrete M30 Retaining wall Raft casting 156+247 156+277 30 LHS 8/11/2022
1646 NH-39/STR/1658 Checking of Toe wall M20 Raft casting 109+855 109+945 90 LHS 8/12/2022
1647 NH-39/STR/1659 Checking of Toe wall M20 Raft casting 112+015 112+120 105 RHS 8/12/2022
1648 NH-39/STR/1660 Checking of Toe wall M20 Raft casting 112+250 112+400 150 RHS 8/12/2022
1649 NH-39/STR/1661 Reinforcemet checking of Retaining wall top lift 163+372 163+387 15 RHS 8/12/2022
1650 NH-39/STR/1662 Shuttering checking & Pouring of concrete M30 Retaining wall top lift casting 163+372 163+387 15 RHS 8/12/2022
1651 NH-39/STR/1663 Checking of stone pitching for HPC 101+298 RHS 8/12/2022
1652 NH-39/STR/1664 Checking of Toe wall M20 wall final lift casting 109+855 109+945 90 LHS 8/13/2022
1653 NH-39/STR/1665 Reinforcemet checking of Retaining wall 1st lift 154+140 154+185 45 LHS 8/13/2022
1654 NH-39/STR/1666 Shuttering checking & Pouring of concrete M30 Retaining wall 1st lift casting 154+140 154+185 45 LHS 8/13/2022
1655 NH-39/STR/1667 Checking of Filter media laying For HPC 88+905 BHS 8/13/2022
1656 NH-39/STR/1668 Reinforcemet checking of Retaining wall 1st lift 156+247 156+277 30 LHS 8/13/2022
1657 NH-39/STR/1669 Shuttering checking & Pouring of concrete M30 Retaining wall 1st lift casting 156+247 156+277 30 LHS 8/13/2022
1658 NH-39/STR/1670 Layout OGL checkng & Excavation for RCC Drain 166+485 166+705 220 LHS 8/13/2022
1659 NH-39/STR/1671 Checking of Filter media laying For HPC 87+526 BHS 8/14/2022
1660 NH-39/STR/1672 Checking of Toe wall M20 wall final lift casting 112+015 112+120 105 RHS 8/14/2022
1661 NH-39/STR/1673 Reinforcemet checking of Retaining wall Raft 156+200 156+247 47 LHS 8/14/2022
1662 NH-39/STR/1674 Shuttering checking & Pouring of concrete M30 Retaining wall Raft casting 156+200 156+247 47 LHS 8/14/2022
S.No RFI NO. Item Description Chainage Length Side NOS Width Height Qty Unit Details of Inspection
From To Date Time
1665 NH-39/STR/1677 Line level checking & PCC Laying for RCC Drian 166+485 166+669 184 LHS 8/16/2022
1666 NH-39/STR/1678 Checking of stone pitching for HPC 153+206 LHS 8/16/2022
1667 NH-39/STR/1679 Checking of stone pitching for HPC 153+525 LHS 8/16/2022
1668 NH-39/STR/1680 Reinforcemet checking of Retaining wall 1st lift 156+200 156+247 47 LHS 8/16/2022
1669 NH-39/STR/1681 Shuttering checking & Pouring of concrete M30 Retaining wall 1st lift casting 156+200 156+247 47 LHS 8/16/2022
1670 NH-39/STR/1682 Checking of Filter media laying For HPC 87+774 BHS 8/17/2022
1671 NH-39/STR/1683 Reinforcement checking For RCC Drain Raft 166+485 166+669 184 LHS 8/17/2022
1672 NH-39/STR/1684 Shuttering checking & pouring M20 grade RCC Drain Raft 166+485 166+669 184 LHS 8/17/2022
1673 NH-39/STR/1685 Checking of Filter media laying For HPC 87+108 BHS 8/17/2022
1674 NH-39/STR/1686 Reinforcemet checking of Retaining wall top lift 156+247 156+277 30 LHS 8/17/2022
1675 NH-39/STR/1687 Shuttering checking & Pouring of concrete M30 Retaining wall top lift casting 156+247 156+277 30 LHS 8/17/2022
1676 NH-39/STR/1688 Reinforcement checking For RCC Drain Wall 166+485 166+580 95 LHS 8/18/2022
1677 NH-39/STR/1689 shuttering checking & pouring M20 grade RCC Drain Wall 166+485 166+580 95 LHS 8/18/2022
1678 NH-39/STR/1690 Checking of Toe wall M20 wall final lift casting 112+250 112+340 90 RHS 8/18/2022
1679 NH-39/STR/1691 Reinforcemet checking of Retaining wall top lift 154+140 154+185 45 LHS 8/18/2022
1680 NH-39/STR/1692 Shuttering checking & Pouring of concrete M30 Retaining wall top lift casting 154+140 154+185 45 LHS 8/18/2022
1683 NH-39/STR/1695 Checking of Toe wall M20 wall final lift casting 112+340 112+400 60 RHS 8/19/2022
1684 NH-39/STR/1696 Reinforcement checking For RCC Drain Raft 166+580 166+669 89 LHS 8/19/2022
1685 NH-39/STR/1697 shuttering checking & pouring M20 grade RCC Drain Wall 166+580 166+669 89 LHS 8/19/2022
1686 NH-39/STR/1698 Reinforcemet checking of Retaining wall top lift 156+200 156+247 47 LHS 8/19/2022
1687 NH-39/STR/1699 Shuttering checking & Pouring of concrete M30 Retaining wall top lift casting 156+200 156+247 47 LHS 8/19/2022
1688 NH-39/STR/1700 Checking of stone pitching for HPC 96+405 LHS 8/19/2022
1689 NH-39/STR/1701 Checking of stone pitching for HPC 91+243 LHS 8/19/2022
1690 NH-39/STR/1702 Checking of stone pitching for HPC 92+667 RHS 8/20/2022
1691 NH-39/STR/1703 Checking of stone pitching for HPC 94+540 RHS 8/20/2022
1692 NH-39/STR/1704 Checking of stone pitching for HPC 102+094 LHS 8/20/2022
1693 NH-39/STR/1705 Checking of stone pitching for HPC 102+015 LHS 8/20/2022
1694 NH-39/STR/1706 Checking of Filter media laying For HPC 86+694 BHS 8/20/2022
1695 NH-39/STR/1707 Checking of Filter media laying For HPC 99+635 BHS 8/20/2022
1696 NH-39/STR/1708 Checking of stone pitching for HPC 88+745 LHS 8/20/2022
1697 NH-39/STR/1709 Checking of stone pitching for HPC 152+685 RHS 8/21/2022
1698 NH-39/STR/1710 Checking of stone pitching for HPC 153+206 RHS 8/21/2022
1699 NH-39/STR/1711 Checking of stone pitching for HPC 153+525 RHS 8/21/2022
1700 NH-39/STR/1712 Checking of stone pitching for HPC 88+905 LHS 8/21/2022
RFI SUMMARY (STRUCTURE)
S.No RFI NO. Item Description Chainage Length Side NOS Width Height Qty Unit Details of Inspection
From To Date Time
1701 NH-39/STR/1713 Checking of stone pitching for HPC 87+526 LHS 8/21/2022
1702 NH-39/STR/1714 Checking of stone pitching for HPC 96+405 RHS 8/22/2022
1703 NH-39/STR/1715 Checking of stone pitching for HPC 91+243 RHS 8/22/2022
1704 NH-39/STR/1716 Checking of stone pitching for HPC 102+094 RHS 8/22/2022
1705 NH-39/STR/1717 Checking of stone pitching for HPC 102+015 RHS 8/22/2022
1706 NH-39/STR/1718 Checking of stone pitching for HPC 88+745 RHS 8/22/2022
1707 NH-39/STR/1719 Checking of stone pitching for HPC 88+905 RHS 8/22/2022
1708 NH-39/STR/1720 Checking of stone pitching for HPC 87+526 RHS 8/22/2022
1709 NH-39/STR/1721 Checking of stone pitching for HPC 87+774 LHS 8/22/2022
1710 NH-39/STR/1722 Checking of stone pitching for HPC 87+108 LHS 8/22/2022
1711 NH-39/STR/1723 Checking of stone pitching for HPC 87+774 RHS 8/23/2022
1712 NH-39/STR/1724 Checking of stone pitching for HPC 87+108 RHS 8/23/2022
1713 NH-39/STR/1725 Layout,OGL Checking and excavation for Retaining wall 163+100 163+200 100 RHS 8/23/2022
1714 NH-39/STR/1726 Layout,OGL checking and excavation For drain 166+220 166+520 300 RHS 8/24/2022
1715 NH-39/STR/1727 Layout,OGL checking and excavation For Toe wall 169+040 169+170 130 RHS 8/24/2022
1716 NH-39/STR/1728 Layout,OGL Checking and excavation for Retaining wall 163+100 163+200 100 RHS 8/24/2022
1717 NH-39/STR/1729 Checking of stone pitching for HPC 86+694 LHS 8/24/2022
1718 NH-39/STR/1730 Checking of stone pitching for HPC 99+635 LHS 8/24/2022
1719 NH-39/STR/1731 Checking of stone pitching for HPC 86+694 RHS 8/24/2022
1720 NH-39/STR/1732 Checking of stone pitching for HPC 99+635 RHS 8/24/2022
1721 NH-39/STR/1733 Checking of Protection work stone picting 166+220 166+520 300 RHS 8/25/2022
1722 NH-39/STR/1734 Layout,OGL checking and excavation For Toe wall 169+040 169+170 130 RHS 8/25/2022
1723 NH-39/STR/1735 Layout,OGL Checking and excavation for Retaining wall 163+100 163+200 100 RHS 8/25/2022
1724 NH-39/STR/1736 Layout,OGL checking and excavation For drain 166+220 166+520 300 RHS 8/26/2022
1725 NH-39/STR/1737 Layout,OGL checking and excavation For Toe wall 169+040 169+170 130 RHS 8/26/2022
1726 NH-39/STR/1738 Layout,OGL Checking and excavation for Retaining wall 163+100 163+200 100 RHS 8/26/2022
8/26/2022
1727 NH-39/STR/1739 Layout,OGL checking and excavation For Toe wall 169+015 169+205 190 LHS 8/27/2022
1732 NH-39/STR/1744 Checking of Toe wall PCC 169+015 169+115 100 LHS 8/29/2022
1733 NH-39/STR/1745 Reinforcemet checking of Retaining wall RAFT Lift 163+327 163+342 15 RHS 8/29/2022
1734 NH-39/STR/1746 shuttering checking & pouring M20 grade RCC Drain Wall RAFT 166+485 166+521 36 LHS 8/29/2022
1735 NH-39/STR/1747 Checking of Toe wall M20 Raft casting 169+015 169+045 30 LHS 8/30/2022
1736 NH-39/STR/1748 Checking of Toe wall M20 Raft casting 169+045 169+085 40 LHS 8/31/2022
RFI SUMMARY (STRUCTURE)
S.No RFI NO. Item Description Chainage Length Side NOS Width Height Qty Unit Details of Inspection
From To Date Time
1737 NH-39/STR/1749
1738 NH-39/STR/1750 Checking of Toe wall PCC 169+115 169+205 90 LHS 8/31/2022 8/31/2022
1739 NH-39/STR/1751 Reinforcemet & shuttering checking of Retaining wall RAFT 163+327 163+342 15 RHS 8/31/2022 8/31/2022
1740 NH-39/STR/1752 Checking pouring of M30 Retaining wall RAFT casting 163+327 163+342 15 RHS 8/31/2022 8/31/2022
1741 NH-39/STR/1753 Reinforcement & Checking pouring M20 grade RCC Drain Wall RAFT casting 166+485 166+521 36 LHS 8/31/2022 8/31/2022
1742 NH-39/STR/1754 Reinforcemet & shuttering checking of Retaining wall RAFT 163+342 163+357 15 RHS 8/31/2022 8/31/2022
1743 NH-39/STR/1755 Checking pouring of M30 Retaining wall RAFT casting 163+342 163+357 15 RHS 8/31/2022 8/31/2022
1744 NH-39/STR/1756 Checking of Filter media laying For HPC 146+329 RHS 8/31/2022 8/31/2022
1745 NH-39/STR/1757 Checking of Filter media laying For HPC 146+235 BHS 8/31/2022 8/31/2022
1746 NH-39/STR/1758 Reinforcement & Checking pouring M20 grade RCC Drain Wall RAFT casting 166+545 166+569 24 LHS 8/31/2022 8/31/2022
1747 NH-39/STR/1759 Checking of Filter media laying For HPC 146+329 RHS 8/31/2022 8/31/2022
1748 NH-39/STR/1760 Checking of Filter media laying For HPC 146+235 BHS 8/31/2022 8/31/2022
1749 NH-39/STR/1761 Reinforcement & Checking pouring M20 grade RCC Drain Wall RAFT casting 166+569 166+593 24 LHS 9/1/2022 9/1/2022
1750 NH-39/STR/1762 Reinforcemet & shuttering checking of Retaining wall 1st lift 163+342 163+357 15 RHS 9/1/2022 9/1/2022
1751 NH-39/STR/1763 Checking pouring of M30 Retaining wall 1st lift casting 163+342 163+357 15 RHS 9/1/2022 9/1/2022
1752 NH-39/STR/1764 Reinforcemet & shuttering checking of Retaining wall 1st lift 163+342 163+357 15 RHS 9/2/2022 9/2/2022
1753 NH-39/STR/1765 Checking pouring of M30 Retaining wall 1st lift casting 163+342 163+357 15 RHS 9/2/2022 9/2/2022
1754 NH-39/STR/1766 Reinforcement & Checking pouring M20 grade RCC Drain RAFT casting 166+593 166+605 12 LHS 9/2/2022 9/2/2022
1755 NH-39/STR/1767 Layout OGL checkng & Excavation for RCC Drain 166+669 166+807 138 LHS 9/7/2022 9/3/2022
1756 NH-39/STR/1768 Line level checking & PCC Laying for RCC Drian 166+669 166+807 138 LHS 9/7/2022 9/3/2022
1757 NH-39/STR/1769 Reinforcement & Checking pouring M20 grade RCC Drain RAFT casting 166+669 166+807 138 LHS 9/8/2022 9/4/2022
1758 NH-39/STR/1770 Reinforcemet & shuttering checking of Retaining wall 1st lift 163+327 163+342 15 RHS 9/8/2022 9/4/2022
1759 NH-39/STR/1771 Checking pouring of M30 Retaining wall 1st lift casting 163+327 163+342 15 RHS 9/8/2022 9/4/2022
1760 NH-39/STR/1772 Layout OGL checkng & Excavation for RCC Drain 179+980 180+180 200 LHS 9/9/2022 9/5/2022
1761 NH-39/STR/1773 Checking of Toe wall M20 Raft casting 169+085 169+115 30 LHS 9/9/2022 9/5/2022
1762 NH-39/STR/1774 Line level checking & PCC Laying for RCC Drain 179+980 180+180 200 LHS 9/9/2022 9/5/2022
1763 NH-39/STR/1775 Checking of Toe wall M20 Raft casting 169+115 169+145 30 LHS 9/9/2022 9/5/2022
1764 NH-39/STR/1776 Checking of PCC Retaining wall 163+311 163+321 10 RHS 9/9/2022 9/5/2022
1765 NH-39/STR/1777 Line level checking & PCC Laying for RCC Drain 179+980 180+180 200 LHS 9/10/2022 9/6/2022
1766 NH-39/STR/1778 Checking of Toe wall M20 Raft casting 169+145 169+175 30 LHS 9/10/2022 9/6/2022
1767 NH-39/STR/1779 Checking of PCC Retaining wall 163+307 163+321 14 RHS 9/10/2022 9/6/2022
1768 NH-39/STR/1780 Checking of Toe wall M20 Raft casting 169+175 169+205 30 LHS 9/11/2022 9/7/2022
1769 NH-39/STR/1781 Line level checking & PCC Laying for RCC Drain 179+980 180+180 200 LHS 9/11/2022 9/7/2022
1770 NH-39/STR/1782 Checking of PCC Retaining wall 163+311 163+321 10 RHS 9/11/2022 9/7/2022
1771 NH-39/STR/1783 Reinforcemet & shuttering checking of Retaining wall RAFT 163+307 163+327 20 RHS 9/12/2022 9/8/2022
1772 NH-39/STR/1784 Checking pouring of M30 Retaining wall RAFT casting 163+307 163+327 20 RHS 9/12/2022 9/8/2022
1773 NH-39/STR/1785 Checking of Toe wall M20 final lift casting 169+015 169+045 30 LHS 9/12/2022 9/8/2022
RFI SUMMARY (STRUCTURE)
S.No RFI NO. Item Description Chainage Length Side NOS Width Height Qty Unit Details of Inspection
From To Date Time
1774 NH-39/STR/1786 Reinforcemet & shuttering checking of Retaining wall RAFT 163+307 163+327 20 RHS 9/13/2022 9/9/2022
1775 NH-39/STR/1787 Checking pouring of M30 Retaining wall RAFT casting 163+307 163+327 20 RHS 9/13/2022 9/9/2022
1776 NH-39/STR/1788 Checking of Toe wall M20 final lift casting 169+045 169+075 30 LHS 9/13/2022 9/9/2022
1777 NH-39/STR/1789 Checking of Toe wall Excavation 112+018 112+079 61 RHS 15-09-22 9/11/2022
1778 NH-39/STR/1790 Checking of Toe wall Excavation 112+357 112+465 108 RHS 15-09-22 9/11/2022
1779 NH-39/STR/1791 Checking of Toe wall Excavation 109+881 109+965 84 RHS 15-09-22 9/11/2022
1780 NH-39/STR/1792 Checking of PCC Drain Excavation 116+154 116+221 67 RHS 1 0.9 0.7 42.21 Cum 15-09-22 9/11/2022
1781 NH-39/STR/1793 Checking of PCC Drain Excavation 103+330 103+360 30 RHS 1 0.9 0.7 18.9 Cum 15-09-22 9/11/2022
1782 NH-39/STR/1794 Checking of PCC Drain Excavation 103+500 103+570 70 RHS 1 0.9 0.7 44.1 Cum 15-09-22 9/11/2022
1783 NH-39/STR/1795 Level Checking and PCC pile cap bottom Abutment A1 137+640 RHS 15-09-22 9/11/2022
1784 NH-39/STR/1796 Line level cheking of Toe wall PCC 112+018 112+079 61 RHS 15-09-22 9/11/2022
1785 NH-39/STR/1797 Line level cheking of Toe wall PCC 112+357 112+465 108 RHS 15-09-22 9/11/2022
1786 NH-39/STR/1798 Line level cheking of Toe wall PCC 109+881 109+965 84 RHS 15-09-22 9/11/2022
1787 NH-39/STR/1799 Checking of PCC Drain for PCC 116+154 116+221 67 RHS 1 0.9 0.1 6.03 Cum 15-09-22 9/11/2022
NH-39/STR/1800 Checking of PCC Drain for PCC 103+330 103+360 30 RHS 1 0.9 0.1 2.7 Cum 15-09-22 9/11/2022
NH-39/STR/1801 Checking of PCC Drain for PCC 103+500 103+570 70 RHS 1 0.9 0.1 6.3 Cum 15-09-22 9/11/2022
NH-39/STR/1802 Checking of Toe wall Excavation 109+801 109+855 54 LHS 16-09-22 9/12/2022
NH-39/STR/1803 Checking of PCC Drain Excavation 103+608 103+715 107 RHS 1 0.9 0.7 67.41 Cum 16-09-22 9/12/2022
NH-39/STR/1804 Shuttering cheking & Concrete pourring of Toe wall Raft 112+018 112+079 61 RHS 16-09-22 9/12/2022
NH-39/STR/1805 Shuttering cheking & Concrete pourring of Toe wall Raft 112+357 112+465 108 RHS 16-09-22 9/12/2022
NH-39/STR/1806 Shuttering cheking & Concrete pourring of Toe wall Raft 109+881 109+965 84 RHS 16-09-22 9/12/2022
NH-39/STR/1807 Line level cheking of Toe wall PCC 109+801 109+855 54 LHS 16-09-22 9/12/2022
NH-39/STR/1808 Checking of PCC Drain for PCC 103+608 103+715 107 RHS 1 0.9 0.1 9.63 Cum 16-09-22 9/12/2022
NH-39/STR/1809 Reinforcement & Shuttering Checking MNB for Slab MCW 155+800 RHS 16-09-22 9/12/2022
NH-39/STR/1810 Reinforcement & Shuttering Checking Retaining wall Raft 153+307 153+327 20 RHS 16-09-22 9/12/2022
NH-39/STR/1811 Concrete Pouring Retaining wall Raft 153+307 153+327 20 RHS 16-09-22 9/12/2022
NH-39/STR/1812 Level Checking and PCC pile cap bottom Abutment A1 137+640 RHS 16-09-22 9/12/2022
NH-39/STR/1813 Level Checking and PCC for Toe Wall Toe Wall 112+296 112+357 RHS 17-09-22 9/13/2022
NH-39/STR/1814 Shuttering cheking & Concrete pourring of Toe wall Raft Toe Wall 112+296 112+357 RHS 18-09-22 9/14/2022
NH-39/STR/1815 Layout,OGL Checking and excavation for Toe wall 171+300 171+405 105 LHS 18-09-22 9/14/2022
NH-39/STR/1816 Shuttering cheking & Concrete pourring of Toe wall Final Lift 112+018 112+079 61 RHS 18-09-22 9/14/2022
NH-39/STR/1817 Shuttering cheking & Concrete pourring of Toe wall Final Lift 112+357 112+490 133 RHS 18-09-22 9/14/2022
NH-39/STR/1818 Shuttering cheking & Concrete pourring of Toe wall Final Lift 109+881 109+965 84 RHS 18-09-22 9/14/2022
NH-39/STR/1819 Shuttering cheking & Concrete pourring of Toe wall Raft 109+801 109+855 54 LHS 18-09-22 9/14/2022
NH-39/STR/1820 Checking of PCC Drain Wall Casting 116+154 116+221 67 RHS 2 0.1 0.6 8.04 Cum 18-09-22 9/14/2022
NH-39/STR/1821 Checking of PCC Drain Wall Casting 103+330 103+360 30 RHS 2 0.1 0.6 3.6 Cum 18-09-22 9/14/2022
NH-39/STR/1822 Checking of PCC Drain Wall Casting 103+500 103+570 70 RHS 2 0.1 0.6 8.4 Cum 18-09-22 9/14/2022
RFI SUMMARY (STRUCTURE)
S.No RFI NO. Item Description Chainage Length Side NOS Width Height Qty Unit Details of Inspection
From To Date Time
NH-39/STR/1823 Checking of Concrete pourring MNB Slab MCW 155+800 RHS 18-09-22 9/14/2022
NH-39/STR/1824 Line Level Checking and PCC Laying for toe wall 171+300 171+405 105 LHS 18-09-22 9/14/2022
NH-39/STR/1825 Reinforcemet & shuttering checking of Retaining wall 1st lift 163+307 163+327 20 RHS 18-09-22 9/14/2022
NH-39/STR/1826 Checking pouring of M30 Retaining wall 1st lift 163+307 163+327 20 RHS 18-09-22 9/14/2022
NH-39/STR/1827 12/26/1899
NH-39/STR/1828 Excavation of PCC Drain 116+904 117+069 165 LHS 19-09-22 9/15/2022
NH-39/STR/1829 Shuttering cheking & Concrete pourring of Toe wall Final Lift 109+801 109+855 54 LHS 19-09-22 9/15/2022
NH-39/STR/1830 Shuttering cheking & Concrete pourring of Toe wall Raft 171+300 171+405 105 LHS 19-09-22 9/15/2022
NH-39/STR/1831 Checking of PCC Drain for PCC 116+904 117+069 165 LHS 1 0.9 0.1 14.85 Cum 19-09-22 9/15/2022
NH-39/STR/1832 12/26/1899
NH-39/STR/1833 Checking of PCC Drain Wall Casting 116+904 117+069 165 LHS 2 0.1 0.6 19.8 Cum 20-09-22 9/16/2022
NH-39/STR/1834 Shuttering cheking & Concrete pourring of Toe wall 171+370 171+405 35 LHS 20-09-22 9/16/2022
NH-39/STR/1835 Checking of PCC Drain Excavation 116+572 116+690 118 LHS 1 0.9 0.7 74.34 Cum 20-09-22 9/16/2022
NH-39/STR/1836 Checking of PCC Drain Wall Casting 103+608 103+715 107 RHS 2 0.1 0.6 12.84 Cum 20-09-22 9/16/2022
NH-39/STR/1840 Shuttering & Reinorcement Checking for Slab MNB 155+800 RHS 21-09-22 9/17/2022
NH-39/STR/1841 Checking of PCC Drain for PCC 116+572 116+690 118 LHS 1 0.9 0.1 10.62 Cum 22-09-22 9/18/2022
NH-39/STR/1843 Shuttering cheking & Concrete pourring of Toe wall Toe Wall 112+296 112+357 RHS 22-09-22 9/18/2022
NH-39/STR/1844 Checking of PCC Drain Wall Casting 116+572 116+690 118 LHS Cum 23-09-22 9/19/2022
NH-39/STR/1845 Base PCC Laying for Girder Casting (MJB) 120+740 25 RHS 1 1.5 0.1 3.75 Cum 23-09-22 9/19/2022
NH-39/STR/1846 Base PCC Laying for Girder Casting (MJB) 114+443 25 RHS 1 1.5 0.1 3.75 Cum 23-09-22 9/19/2022
NH-39/STR/1847 Concrete pourring for Slab MNB( M35 Grade ) 155+800 RHS 23-09-22 9/19/2022
NH-39/STR/1848 Base PCC Laying for Girder Casting (MJB) 114+443 25 RHS 1 1.5 0.1 3.75 Cum 24-09-22 9/20/2022
NH-39/STR/1849 Checking of PCC Drain Wall Casting 116+572 116+630 58 LHS 2 0.1 0.6 6.96 Cum 24-09-22 9/20/2022
NH-39/STR/1850 Sahuttering & Reinforcement Checking for VUP Slab 110+030 RHS 24-09-22 9/20/2022
NH-39/STR/1853 Shuttering & Reinforcement Checking RCC Drain Wall 166+485 166+521 36 LHS 25-09-22 9/21/2022
NH-39/STR/1854 Shuttering & Reinforcement Checking RCC Drain Wall 166+669 166+730 61 LHS 25-09-22 9/21/2022
NH-39/STR/1855 Concrete pouring M20 grade RCC Drain Wall casting 166+669 166+730 61 LHS 25-09-22 9/21/2022
NH-39/STR/1856 Shuttering & Reinforcement Checking Of Cross Girder P1-P2 120+740 RHS 25-09-22 9/21/2022
NH-39/STR/1857 Shuttering & Reinforcement Checking RCC Drain Raft 179+980 180+030 50 LHS 25-09-22 9/21/2022
NH-39/STR/1858 Concrete pouring for RCC Drain Raft casting 179+980 180+030 50 LHS 25-09-22 9/21/2022
NH-39/STR/1859 Checking of PCC Drain Wall Casting 116+630 116+690 60 LHS 2 0.1 0.6 7.2 Cum 25-09-22 9/21/2022
RFI SUMMARY (STRUCTURE)
S.No RFI NO. Item Description Chainage Length Side NOS Width Height Qty Unit Details of Inspection
From To Date Time
NH-39/STR/1860 Concrete pouring M20 grade RCC Drain Wall casting 166+485 166+521 36 LHS 25-09-22 9/21/2022
NH-39/STR/1861 Checking of Concrete pouring for Cross Girder P1-P2 120+740 RHS 25-09-22 9/21/2022
NH-39/STR/1864 Shuttering & Reinforcement Checking RCC Drain Raft 180+030 180+180 150 LHS 26-09-22 9/22/2022
NH-39/STR/1865 Concrete pouring for RCC Drain Raft casting 180+030 180+180 150 LHS 26-09-22 9/22/2022
NH-39/STR/1866 Checking of Concrete pouring for VUP Slab 110+030 RHS 26-09-22 9/22/2022
NH-39/STR/1867 Layout & Excavation for PCC Drain 116+830 116+904 74 LHS 26-09-22 9/22/2022
NH-39/STR/1868 Line & Level Checking of PCC for PCC Drain 116+830 116+904 74 LHS 26-09-22 9/22/2022
NH-39/STR/1869 Shuttering & Reinforcement Checking RCC Drain Wall 179+980 180+030 50 LHS 26-09-22 9/22/2022
RFI SUMMARY (STRUCTURE)
S.No RFI NO. Item Description Chainage Length Side NOS Width Height Qty Unit Details of Inspection
From To Date Time
NH-39/STR/1870 Concrete pouring for RCC Drain Wall casting 179+980 180+030 50 LHS 26-09-22 9/22/2022
NH-39/STR/1871 Checking of PCC Drain Excavation 116+230 116+330 100 RHS 1 0.9 0.7 63 Cum 26-09-22 9/22/2022
NH-39/STR/1872 Checking of PCC Drain for PCC 116+230 116+330 100 RHS 1 0.9 0.1 9 Cum 26-09-22 9/22/2022
NH-39/STR/1873 Layout & Excavation for MNB Abutment A1 146+938 RHS 26-09-22 9/22/2022
NH-39/STR/1874 Shuttering & Reinforcement Checking for MNB Abutment A1 Raft 137+640 RHS 26-09-22 9/22/2022
NH-39/STR/1875 Layout & Excavation for MNB Abutment A12 167+454 LHS 26-09-22 9/22/2022
NH-39/STR/1876 Checking of PCC Drain Wall Casting 116+830 116+904 74 LHS 2 0.1 0.6 8.88 Cum 26-09-22 9/22/2022
NH-39/STR/1877 Concrete pouring for RCC Drain Wall casting 166+730 166+780 50 LHS 26-09-22 9/22/2022
NH-39/STR/1878 Shuttering & Reinforcement Checking RCC Drain Raft 166+521 166+669 148 LHS 26-09-22 9/22/2022
NH-39/STR/1879 Concrete pouring for RCC Drain Raft casting 166+521 166+669 148 LHS 26-09-22 9/22/2022
NH-39/STR/1880 Shuttering cheking & Concrete pourring of Toe wall 171+330 171+370 40 LHS 26-09-22 9/22/2022
NH-39/STR/1881 Layout & Excavation for RCC Drain 165+550 165+650 100 RHS 26-09-22 9/22/2022
NH-39/STR/1882 Line & Level Checking of PCC for RCC Drain 165+550 165+600 50 RHS 26-09-22 9/22/2022
NH-39/STR/1884 Concrete pourring for Slab MNB( M35 Grade ) 155+800 RHS 27-09-22 9/23/2022
NH-39/STR/1885 Checking of PCC Drain Wall Casting 116+230 116+330 100 RHS 2 0.1 0.6 12 Cum 27-09-22 9/23/2022
NH-39/STR/1886 Shuttering & Reinforcement Checking Pile Cap A1 for MNB 137+500 RHS 27-09-22 9/23/2022
NH-39/STR/1887 Shuttering & Reinforcement Checking Girder for MJB 114+400 RHS 27-09-22 9/23/2022
NH-39/STR/1888 Shuttering Checking Concrete pouring of PCC Drain Wall 116+830 116+904 74 LHS 27-09-22 9/23/2022
NH-39/STR/1889 Checking of Concrete pouring of Pile Cap A1 for MNB 137+500 27-09-22 9/23/2022
NH-39/STR/1890 Shuttering & Reinforcement Checking RCC Drain Wall 180+030 180+180 150 LHS 27-09-22 9/23/2022
NH-39/STR/1891 Concrete pouring for RCC Drain Wall casting 180+030 180+180 150 LHS 27-09-22 9/23/2022
NH-39/STR/1892 Shuttering & Reinforcement Checking RCC Drain Wall 166+521 166+669 148 LHS 27-09-22 9/23/2022
NH-39/STR/1893 Concrete pouring for RCC Drain Wall casting 166+521 166+669 148 LHS 27-09-22 9/23/2022
NH-39/STR/1894 Shuttering & Reinforcement Checking RCC Drain Raft 165+550 165+600 50 RHS 27-09-22 9/23/2022
NH-39/STR/1895 Concrete pouring for RCC Drain Raft casting 165+550 165+600 50 RHS 27-09-22 9/23/2022
NH-39/STR/1897 Shuttering cheking & Concrete pourring of Toe wall Toe Wall 112+310 112+396 LHS 27-09-22 9/23/2022
NH-39/STR/1899 Checking of Concrete pouring for VUP Slab 110+030 RHS 28-09-22 9/24/2022
NH-39/STR/1900
NH-39/STR/1901
NH-39/STR/1902
NH-39/STR/1904 Concrete pouring for MNB abutment A1 pile cap 137+640 RHS 29-09-22 9/30/2022
S.No RFI NO. Item Description Chainage Length Side NOS Width Height Qty Unit Details of Inspection
From To Date Time
NH-39/STR/1907 29-09-22 9/30/2022
29-09-22 9/30/2022
M.P. Road Development Corporation Ltd.
Balance work for Rehabilitation and up-gradation of Sidhi-Singrouli from km 82.400 to km 187.993 section of new NH-39 (Old NH-75E)(Design Length 105.593 km to four lane with paved shoulders
on through Engineering, Procurement & Construction (EPC) mode under NH (O) in the state of Madhya Pradesh.
1 NH-39/STR/1904 Concrete pouring for MNB abutment A1 pile cap 137+640 RHS 29-09-22 30-09-22 10.50AM
Highway RFI
1 NH-39/HW/4237 Tree Plantation Work 99205 101+000 1795 BHS 29-09-22 30-09-22 8.30AM
2 NH-39/HW/4238 FDD & Level Checking for GSB Layer 179350 179+600 250 LHS 29-09-22 30-09-22 9.30AM
3 NH-39/HW/4239 Application of Tack Coat for DBM Laying 97660 98+200 540 LHS 29-09-22 30-09-22 9.30AM
4 NH-39/HW/4240 Checking of DBM laying 97660 98+200 540 LHS 29-09-22 30-09-22 10.50AM
5 NH-39/HW/4241 Application of Tack Coat for DBM Laying 134350 134+700 350 RHS 29-09-22 30-09-22 2.30PM
6 NH-39/HW/4242 Checking of DBM laying 134350 134+700 350 RHS 29-09-22 30-09-22 3.30PM
7 NH-39/HW/4243 Tree Plantation Work 159900 161+500 1600 BHS 29-09-22 30-09-22 5.30PM
S.No RFI NO. Item Description Chainage Length Side Details of Inspection Status Remarks
1 NH-39/HW/741 Checking of Emb.3th layer FDD test 167800 168200 400 RHS 12/12/2021 3.45PM Not done
2 NH-39/HW/742 Checking of Emb.3rd layer FDD test 168250 168420 170 RHS 12/12/2021 4.00PM Not done
3 NH-39/HW/753 Checking of Emb.1st layer FDD test 167800 168200 400 LHS 12/12/2021 5.00PM Not done
4 NH-39/HW/761 Checking of Emb.5th layer FDD test 168250 168420 170 LHS 13/12/2021 08.30AM Not done
5 NH-39/HW/771 Checking of Emb.18th layer FDD test 171200 171270 70 LHS 13/12/2021 2.30PM Not done
6 NH-39/HW/772 Checking of Emb.18th layer FDD test 171200 171270 70 RHS 13/12/2021 3.00PM Not done
7 NH-39/HW/776 Checking of Emb.3rd layer FDD test 168250 168420 170 RHS 13/12/2021 4.00PM Not done
8 NH-39/HW/787 Checking of Emb.2nd layer FDD test 167800 168200 400 LHS 13/12/2021 5.00PM Not done
9 NH-39/HW/796 Checking of Emb.5th layer FDD test 168250 168420 170 LHS 14/12/2021 08.30AM Not done
10 NH-39/HW/818 Checking of Emb.2nd layer FDD test 167800 168200 400 LHS 14/12/2021 5.00PM Not done
11 NH-39/HW/829 Checking of Emb.5th layer FDD test 168250 168420 170 LHS 15/12/2021 8.30am Not done
12 NH-39/HW/877 Checking of Emb.5th layer FDD test 167800 168200 400 RHS 16/12/2021 11.45am Not done
13 NH-39/HW/878 Checking of Emb.4th layer FDD test 168250 168420 170 RHS 16/12/2021 12.10pm Not done
14 NH-39/HW/887 Checking of OGL Level Checking & FDD test 170960 171100 140 BHS 16/12/2021 3.55pm Not done
15 NH-39/HW/888 Checking of Emb.3rd layer FDD test 167800 168200 400 LHS 16/12/2021 4.20pm Not done
16 NH-39/HW/909 Level & FDD Checking for SG Top layer 156660 156920 260 RHS 17/12/2021 10.15am Not done
17 NH-39/HW/910 Checking of Emb.20th layer FDD test 171200 171270 70 LHS 17/12/2021 10.30am Not done
18 NH-39/HW/911 Checking of Emb.20th layer FDD test 171200 171270 70 RHS 17/12/2021 10.45am Not done
19 NH-39/HW/912 Checking of Emb.21st layer FDD test 171200 171270 70 LHS 17/12/2021 11.10am Not done
20 NH-39/HW/913 Checking of Emb.21st layer FDD test 171200 171270 70 RHS 17/12/2021 11.30am Not done
21 NH-39/HW/927 Checking of EMB.2nd Truck Lay Bye FDD test 157790 158030 240 RHS 17/12/2021 4.50pm Not done
22 NH-39/HW/930 Checking of Emb.4th layer FDD test 169050 169180 130 LHS 17/12/2021 5.50pm Not done
23 NH-39/HW/991 Checking of EMB.4th Truck Lay Bye FDD test 157860 158100 240 LHS 19/12/2021 11.00am Not done
24 NH-39/HW/1054 Checking of Emb.8th layer FDD test 171421 171450 29 LHS 21/12/2021 9.30am Not done
25 NH-39/HW/1055 Level & FDD Checking for SG Top layer 156660 156900 240 LHS 21/12/2021 9.55am Not done
26 NH-39/HW/1072 Checking of Emb.27th layer FDD test 171200 171270 70 RHS 21/12/2021 4.25pm Not done
27 NH-39/HW/1077 Checking of Emb.6th layer FDD test 167800 168200 400 RHS 21/12/2021 5.10pm Not done
28 NH-39/HW/1093 Level & FDD Checking for SG Top layer 156660 156900 240 LHS 22/12/2021 9.55am Not done
29 NH-39/HW/1179 Level & FDD Checking for SG Top layer 162970 163220 250 RHS 24/12/2021 2.15pm Not done
30 NH-39/HW/1183 FDD Checking of SG 2nd layer 170960 171100 140 RHS 24/12/2021 3.05pm Not done
31 NH-39/HW/1674 Level & FDD Checking for WMM Top layer 162760 162880 120 LHS 23/01/2022 12.40 PM Not Done
32 NH-39/HW/1675 Level & FDD Checking for WMM Top layer 155700 156061 361 RHS 23/01/2022 12.55PM Not Done
33 NH-39/HW/1676 Level & FDD Checking for WMM Top layer 156073 156460 387 RHS 23/01/2022 2.00PM Not Done
34 NH-39/HW/1699 Level & FDD Checking for WMM Top layer 157540 157600 60 LHS 23/01/2022 6.35 PM Not Done
35 NH-39/HW/1700 Level & FDD Checking for WMM Top layer 157615 157660 45 LHS 23/01/2022 6.45 PM Not Done
36 NH-39/HW/1701 Level & FDD Checking for WMM Top layer 158740 158900 160 LHS 23/01/2022 6.45 PM Not Done
Balance work for Rehabilitation and up-gradation of Sidhi-Singrouli from km 82.400 to km 187.993 section of new NH-39 (Old NH-75E)(Design Length 105.593 km to
Name of Project
four lane with paved shoulders on through Engineering, Procurement & Construction (EPC) mode under NH (O) in the state of Madhya Pradesh.
Employer Ministry of Road Transport & Highway
Client M.P. Road Development Corporation Ltd.
Authority Engineer
EPC Contractor Tirupati Build-con Pvt. Ltd.
RFI SUMMARY (STRUCTURE)
S.No RFI NO. Item Description Chainage Details of Inspection
Side Length Width Height Qty Unit
From To Date Time
1 NH-39/STR/67 Toe Wall Wall Casting 156770 156870 LHS 100 0.45 1 45 Cum 12/13/2021
2 NH-39/STR/79 Toe Wall Wall Casting 169300 169481 LHS 181 0.45 1 81.45 Cum 12/14/2021
3 NH-39/STR/80 Toe Wall Wall Casting 169300 169500 RHS 200 0.45 1 90 Cum 12/14/2021
4 NH-39/STR/185 Curtain Wall Bed Pcc 153+829 U/S 13 1.3 0.1 1.69 Cum 12/23/2021
5 NH-39/STR/186 Curtain Wall Bed Pcc 153+829 D/S 13 1.3 0.1 1.69 Cum 12/23/2021
6 NH-39/STR/195 Curtain Wall First Lift 153+829 U/S 13 1.2 0.6 9.36 Cum 12/24/2021
7 NH-39/STR/196 Curtain Wall First Lift 153+829 D/S 13 1.2 0.6 9.36 Cum 12/24/2021
8 NH-39/STR/205 Curtain Wall 2nd Lift 153+829 U/S 13 0.825 1 10.725 Cum 12/25/2021
9 NH-39/STR/206 Curtain Wall 2nd Lift 153+829 D/S 13 0.825 1 10.725 Cum 12/25/2021
10 NH-39/STR/311 Curtain wall 1st lift Box Culvert 154623 D/S 10 1.2 0.6 7.2 Cum 1/16/2022
11 NH-39/STR/312 Curtain wall2nd lift Box Culvert 154222 D/S 14 0.825 1 11.55 Cum 1/16/2022
12 NH-39/STR/313 Curtain wall Bed Pcc Box Culvert 154770 U/S 11 1.3 0.1 1.43 Cum 1/16/2022
13 NH-39/STR/314 Curtain wall Bed Pcc Box Culvert 155277 U/S 11 1.3 0.1 1.43 Cum 1/16/2022
14 NH-39/STR/329 Curtain wall 1st lift Box Culvert 154770 D/S 11 1.2 0.6 7.92 Cum 1/18/2022
15 NH-39/STR/330 Curtain wall 1st lift Box Culvert 155277 D/S 11 1.2 0.6 7.92 Cum 1/18/2022
16 NH-39/STR/331 Curtain wall2nd lift Box Culvert 154623 D/S 10 0.825 1 8.25 Cum 1/18/2022
17 NH-39/STR/351 Toe Wall Wall Casting 163250 163510 RHS 260 0.45 1 117 Cum 1/19/2022
18 NH-39/STR/352 Toe Wall Wall Casting 169425 169530 RHS 105 0.45 1 47.25 Cum 1/19/2022
19 NH-39/STR/358 Curtain wall2nd lift Box Culvert 154770 D/S 11 0.825 1 9.075 Cum 1/20/2022
20 NH-39/STR/359 Curtain wall2nd lift Box Culvert 155277 D/S 11 0.825 1 9.075 Cum 1/20/2022
21 NH-39/STR/375 Curtain wall Final Lift Box Culvert 154623 D/S 10 0.675 0.9 6.075 Cum 1/21/2022
22 NH-39/STR/376 Curtain wall2nd lift Box Culvert 154770 U/S 11 0.825 1 9.075 Cum 1/21/2022
23 NH-39/STR/377 Curtain wall2nd lift Box Culvert 155277 U/S 11 0.825 1 9.075 Cum 1/21/2022
24 NH-39/STR/398 Curtain wall Final Lift Box Culvert 155277 U/S 11 0.675 0.4 2.7 Cum 1/23/2022
25 NH-39/STR/399 Curtain wall Final Lift Box Culvert 155277 D/S 11 0.675 0.9 6.6825 Cum 1/23/2022
26 NH-39/STR/400 Curtain wall Final Lift Box Culvert 154770 U/S 11 0.675 0.4 2.7 Cum 1/23/2022
05.593 km to
sh.
Status
Not done
Not done
Not done
Not done
Not done
Not done
Not done
Not done
Not done
Not done
Not done
Not done
Not done
Not done
Not done
Not done
Not done
Not done
Not done
Not done
Not done
Not done
Not done
Not done
Not done
Not done
Name of Project
Balance work for Rehabilitation and up-gradation of Sidhi-Singrouli from km 82.400 to km 187.993 section of new NH-39 (Old NH-75E)(Design Length 105.593 km to four
Engineering, Procurement & Construction (EPC) mode under NH (O) in the state of Madhya Pradesh.
Authority Engineer
EPC Contractor Tirupati Build-con Pvt. Ltd.
RFI SUMMARY (STRUCTURE)
1 NH-39/STR/01 Curtain Wall Filter midia laying & Stone pitching 162+367 LHS
2 NH-39/STR/02 Curtain Wall Filter midia laying & Stone pitching 162+367 RHS
3 NH-39/STR/03 Curtain Wall Filter midia laying & Stone pitching 165+794 LHS
4 NH-39/STR/04 Curtain Wall Filter midia laying & Stone pitching 165+794 RHS
5 NH-39/STR/05 Curtain Wall Filter midia laying & Stone pitching 154+222 U/S
6 NH-39/STR/06 Curtain Wall Filter midia laying & Stone pitching 154+222 D/S
7 NH-39/STR/07 Curtain Wall Filter midia laying & Stone pitching 155+064 LHS
8 NH-39/STR/08 Curtain Wall Filter midia laying & Stone pitching 155+064 RHS
9 NH-39/STR/09 Curtain Wall Filter midia laying & Stone pitching 162+800 LHS
10 NH-39/STR/10 Curtain Wall Filter midia laying & Stone pitching 162+800 RHS
11 NH-39/STR/11 Curtain Wall Filter midia laying & Stone pitching 158+822 LHS
12 NH-39/STR/12 Curtain Wall Filter midia laying & Stone pitching 158+822 RHS
13 NH-39/STR/13 Curtain Wall Filter midia laying & Stone pitching 159+322 LHS
14 NH-39/STR/14 Curtain Wall Filter midia laying & Stone pitching 159+322 RHS
15 NH-39/STR/15 Curtain Wall Filter midia laying & Stone pitching 159+854 LHS
16 NH-39/STR/16 Curtain Wall Filter midia laying & Stone pitching 159+854 RHS
17 NH-39/STR/17 Curtain Wall Filter midia laying & Stone pitching 162+826 LHS
18 NH-39/STR/18 Curtain Wall Filter midia laying & Stone pitching 162+826 RHS
19 NH-39/STR/19 Curtain Wall Filter midia laying & Stone pitching 161+577 LHS
20 NH-39/STR/20 Curtain Wall Filter midia laying & Stone pitching 161+577 RHS
21 NH-39/STR/21 Curtain Wall Filter midia laying & Stone pitching 157+453 LHS
22 NH-39/STR/22 Curtain Wall Filter midia laying & Stone pitching 157+453 RHS
23 NH-39/STR/23 Curtain Wall Filter midia laying & Stone pitching 158+855 LHS
24 NH-39/STR/24 Curtain Wall Filter midia laying & Stone pitching 158+855 RHS
25 NH-39/STR/25 Curtain Wall Filter midia laying & Stone pitching 158+145 LHS
26 NH-39/STR/26 Curtain Wall Filter midia laying & Stone pitching 158+145 RHS
27 NH-39/STR/27 Curtain Wall Filter midia laying & Stone pitching 158+340 LHS
28 NH-39/STR/28 Curtain Wall Filter midia laying & Stone pitching 158+340 RHS
29 NH-39/STR/45 Toe Wall Layout & excavation 156+650 156+850 RHS
30 NH-39/STR/46 Toe Wall Layout & excavation 156+770 156+870 LHS
31 NH-39/STR/47 Toe Wall Layout & excavation 157+020 157+170 RHS
32 NH-39/STR/48 Toe Wall Bed PCC 156+650 156+850 RHS 200 1.150
33 NH-39/STR/49 Toe Wall Bed PCC 156+770 156+870 LHS 100 1.150
34 NH-39/STR/50 Toe Wall Bed PCC 157+020 157+170 RHS 150 1.150
35 NH-39/STR/51 Toe Wall Layout & excavation 169+300 169+481 LHS
36 NH-39/STR/52 Toe Wall Layout & excavation 169+300 169+418 RHS
37 NH-39/STR/53 Toe Wall Raft 156+650 156+850 RHS 200 1.000
51 NH-39/STR/67 Toe Wall Wall Casting 156+770 156+870 LHS 100 0.450
52 NH-39/STR/68 Toe Wall Wall Casting 157+020 157+170 RHS 150 0.450
53 NH-39/STR/69 Toe Wall Raft 169+300 169+500 LHS 200 1.000
54 NH-39/STR/70 Toe Wall Raft 169+300 169+425 RHS 125 1.000
55 NH-39/STR/71 Curtain wall Bed Pcc 158+855 D/S 14.0 1.300
56 NH-39/STR/72 Curtain wall Bed Pcc 158+855 U/S 14.0 1.300
57 NH-39/STR/73 Curtain wall Bed Pcc 158+145 D/S 10.0 1.300
58 NH-39/STR/74 Curtain wall Bed Pcc 158+145 U/S 10.0 1.300
59 NH-39/STR/75 Curtain wall Bed Pcc 159+322 D/S 11.0 1.300
60 NH-39/STR/76 Curtain wall Bed Pcc 159+322 U/S 11.0 1.300
61 NH-39/STR/77 Curtain wall Bed Pcc 159+854 D/S 11.0 1.300
62 NH-39/STR/78 Curtain wall Bed Pcc 159+854 U/S 11.0 1.300
RFI SUMMARY (STRUCTURE)
63 NH-39/STR/79 Toe Wall Wall Casting 169+300 169+481 LHS 181 0.450
64 NH-39/STR/80 Toe Wall Wall Casting 169+300 169+500 RHS 200 0.450
169 NH-39/STR/185 Curtain Wall Bed Pcc 153+829 U/S 13.0 1.300
170 NH-39/STR/186 Curtain Wall Bed Pcc 153+829 D/S 13.0 1.300
171 NH-39/STR/187 Curtain Wall First Lift 160+826 U/S 11.0 1.200
172 NH-39/STR/188 Curtain Wall First Lift 160+826 D/S 11.0 1.200
173 NH-39/STR/189 Curtain Wall First Lift 161+577 U/S 14.0 1.200
174 NH-39/STR/190 Curtain Wall First Lift 161+577 D/S 14.0 1.200
175 NH-39/STR/191 Curtain Wall First Lift 165+794 U/S 14.0 1.200
176 NH-39/STR/192 Curtain Wall First Lift 165+794 D/S 14.0 1.200
177 NH-39/STR/193 Curtain Wall First Lift 155+064 U/S 13.0 1.200
178 NH-39/STR/194 Curtain Wall First Lift 155+064 D/S 13.0 1.200
179 NH-39/STR/195 Curtain Wall First Lift 153+829 U/S 13.0 1.200
180 NH-39/STR/196 Curtain Wall First Lift 153+829 D/S 13.0 1.200
181 NH-39/STR/197 Curtain Wall 2nd Lift 160+826 U/S 11.0 0.825
182 NH-39/STR/198 Curtain Wall 2nd Lift 160+826 D/S 11.0 0.825
183 NH-39/STR/199 Curtain Wall 2nd Lift 161+577 U/S 14.0 0.825
184 NH-39/STR/200 Curtain Wall 2nd Lift 161+577 D/S 14.0 0.825
185 NH-39/STR/201 Curtain Wall 2nd Lift 165+794 U/S 14.0 0.825
186 NH-39/STR/202 Curtain Wall 2nd Lift 165+794 D/S 14.0 0.825
187 NH-39/STR/203 Curtain Wall 2nd Lift 155+064 U/S 13.0 0.825
188 NH-39/STR/204 Curtain Wall 2nd Lift 155+064 D/S 13.0 0.825
189 NH-39/STR/205 Curtain Wall 2nd Lift 153+829 U/S 13.0 0.825
190 NH-39/STR/206 Curtain Wall 2nd Lift 153+829 D/S 13.0 0.825
191 NH-39/STR/207 Curtain Wall Final Lift 160+826 U/S 11.0 0.675
192 NH-39/STR/208 Curtain Wall Final Lift 160+826 D/S 11.0 0.675
193 NH-39/STR/209 Curtain Wall Final Lift 161+577 U/S 14.0 0.675
194 NH-39/STR/210 Curtain Wall Final Lift 161+577 D/S 14.0 0.675
195 NH-39/STR/211 Curtain Wall Final Lift 165+794 U/S 14.0 0.675
196 NH-39/STR/212 Curtain Wall Final Lift 165+794 D/S 14.0 0.675
197 NH-39/STR/213 Curtain Wall Final Lift 155+064 U/S 13.0 0.675
RFI SUMMARY (STRUCTURE)
295 NH-39/STR/311 Curtain wall 1st lift Box Culvert 154+623 D/S 10.0 1.200
296 NH-39/STR/312 Curtain wall2nd lift Box Culvert 154+222 D/S 14.0 0.825
297 NH-39/STR/313 Curtain wall Bed Pcc Box Culvert 154+770 U/S 11.0 1.300
298 NH-39/STR/314 Curtain wall Bed Pcc Box Culvert 155+277 U/S 11.0 1.300
299 NH-39/STR/315 Toe Wall Raft 156+850 157+020 RHS 170.0 1.000
300 NH-39/STR/316 Toe Wall Raft 157+170 157+280 RHS 110.0 1.000
301 NH-39/STR/317 Curtain wall Bed Pcc Box Culvert 154+770 D/S 11.0 1.300
302 NH-39/STR/318 Curtain wall Bed Pcc Box Culvert 155+277 D/S 11.0 1.300
303 NH-39/STR/319 Curtain wall 1st lift Box Culvert 154+623 D/S 10.0 1.200
304 NH-39/STR/320 Curtain wall2nd lift Box Culvert 154+222 D/S 14.0 0.825
305 NH-39/STR/321 Curtain wall Bed Pcc Box Culvert 154+770 U/S 11.0 1.300
306 NH-39/STR/322 Curtain wall Bed Pcc Box Culvert 155+277 U/S 11.0 1.300
307 NH-39/STR/323
308 NH-39/STR/324 Reinforcement Checking for Service road portion MNB 155+800 LHS
309 NH-39/STR/325 Shuttering Checcking & Concrete pourring for Raft Service road portion MNB 155+800 LHS
310 NH-39/STR/326 Filter midia laying below Stone pitching 169+300 169+500 LHS 200.0 2.500
311 NH-39/STR/327 Filter midia laying below Stone pitching 169+300 169+425 RHS 125.0 2.500
312 NH-39/STR/328 Curtain wall Final Lift Box Culvert 154+031 D/S 10.0 0.675
313 NH-39/STR/329 Curtain wall 1st lift Box Culvert 154+770 D/S 11.0 1.200
314 NH-39/STR/330 Curtain wall 1st lift Box Culvert 155+277 D/S 11.0 1.200
315 NH-39/STR/331 Curtain wall2nd lift Box Culvert 154+623 D/S 10.0 0.825
316 NH-39/STR/332 Toe Wall Raft 162+950 163+250 RHS 300.0 1.000
317 NH-39/STR/333 Toe Wall Raft 163+250 163+510 RHS 260.0 1.000
318 NH-39/STR/334 Toe Wall Raft 169+425 169+530 RHS 105.0 1.000
319 NH-39/STR/335 Toe Wall Wall Casting 156+850 157+020 RHS 170.0 0.450
320 NH-39/STR/336 Toe Wall Wall Casting 157+170 157+280 RHS 110.0 0.450
321 NH-39/STR/337 Stone pitching 169+300 169+500 LHS 200.0 2.500
322 NH-39/STR/338 Stone pitching 169+300 169+425 RHS 125.0 2.500
323 NH-39/STR/339 Curtain wall 1st lift Box Culvert 154+770 D/S 11.0 1.200
324 NH-39/STR/340 Curtain wall 1st lift Box Culvert 155+277 D/S 11.0 1.200
325 NH-39/STR/341 Curtain wall2nd lift Box Culvert 154+623 D/S 10.0 0.825
326 NH-39/STR/342 Curtain wall 1st lift Box Culvert 154+770 U/S 11.0 1.200
327 NH-39/STR/343 Curtain wall 1st lift Box Culvert 155+277 U/S 11.0 1.200
328 NH-39/STR/344 Curtain wall2nd lift Box Culvert 154+031 U/S 10.0 0.825
329 NH-39/STR/345 Curtain wall2nd lift Box Culvert 154+222 U/S 14.0 0.825
330 NH-39/STR/346 Curtain wall2nd lift Box Culvert 154+623 U/S 10.0 0.825
331 NH-39/STR/347 Foundation Bed PCC MNB for Service road section MNB 156+156 RHS
332 NH-39/STR/348 Reinforcement Checking for Service road portion MNB 156+156 LHS
333 NH-39/STR/349 Shuttering Checcking & Concrete pourring for Raft Service road portion MNB 156+156 LHS
334 NH-39/STR/350
RFI SUMMARY (STRUCTURE)
335 NH-39/STR/351 Toe Wall Wall Casting 163+250 163+510 RHS 260.0 0.450
336 NH-39/STR/352 Toe Wall Wall Casting 169+425 169+530 RHS 105.0 0.450
337 NH-39/STR/353
338 NH-39/STR/354
339 NH-39/STR/355 Curtain wall Final Lift Box Culvert 154+222 D/S 14.0 0.675
340 NH-39/STR/356 Protection Work for Stone pitching HPC 156+744 RHS
341 NH-39/STR/357
342 NH-39/STR/358 Curtain wall2nd lift Box Culvert 154+770 D/S 11.0 0.825
343 NH-39/STR/359 Curtain wall2nd lift Box Culvert 155+277 D/S 11.0 0.825
344 NH-39/STR/360
345 NH-39/STR/361
346 NH-39/STR/362 Toe Wall Wall Casting 162+950 163+250 RHS 300.0 0.450
347 NH-39/STR/363 Toe Wall Wall Casting 163+250 163+510 RHS 260.0 0.450
348 NH-39/STR/364 Toe Wall Wall Casting 169+425 169+530 RHS 105.0 0.450
349 NH-39/STR/365 Filter midia laying below Stone pitching 156+650 156+940 LHS 290.0 2.500
350 NH-39/STR/366 Filter midia laying below Stone pitching 156+940 157+280 LHS 340.0 2.500
351 NH-39/STR/367 Curtain wall2nd lift Box Culvert 154+770 D/S 11.0 0.825
352 NH-39/STR/368 Curtain wall2nd lift Box Culvert 155+277 D/S 11.0 0.825
353 NH-39/STR/369 Curtain wall Final Lift Box Culvert 154+031 U/S 10.0 0.675
354 NH-39/STR/370 Curtain wall Final Lift Box Culvert 154+222 U/S 14.0 0.675
355 NH-39/STR/371 Curtain wall Final Lift Box Culvert 154+623 U/S 10.0 0.675
356 NH-39/STR/372 Protection Work for Stone pitching HPC 157+096 RHS
357 NH-39/STR/373 Protection Work for Stone pitching HPC 159+101 RHS
358 NH-39/STR/374 Protection Work for Stone pitching HPC 160+969 RHS
359 NH-39/STR/375 Curtain wall Final Lift Box Culvert 154+623 D/S 10.0 0.675
360 NH-39/STR/376 Curtain wall2nd lift Box Culvert 154+770 U/S 11.0 0.825
361 NH-39/STR/377 Curtain wall2nd lift Box Culvert 155+277 U/S 11.0 0.825
362 NH-39/STR/378
363 NH-39/STR/379 Stone pitching 156+650 156+940 LHS 290.0 2.500
364 NH-39/STR/380 Stone pitching 156+940 157+280 LHS 340.0 2.500
365 NH-39/STR/381 Curtain wall Final Lift Box Culvert 154+623 D/S 10.0 0.675
366 NH-39/STR/382 Curtain wall2nd lift Box Culvert 154+770 U/S 11.0 0.825
367 NH-39/STR/383 Curtain wall2nd lift Box Culvert 155+277 U/S 11.0 0.825
368 NH-39/STR/384 Protection Work for Stone pitching HPC 161+792 RHS
369 NH-39/STR/385 Protection Work for Stone pitching HPC 163+657 RHS
370 NH-39/STR/386 Protection Work for Stone pitching HPC 164+227 RHS
371 NH-39/STR/387
372 NH-39/STR/388 Reinforcement Checking for Service road portion MNB 155+800 LHS
373 NH-39/STR/389 Shuttering Checcking & Concrete pourring for Raft Service road portion MNB 155+800 LHS
374 NH-39/STR/390
375 NH-39/STR/391 Filter midia laying below Stone pitching 162+950 163+250 LHS 300.0 2.500
376 NH-39/STR/392 Protection Work for Stone pitching HPC 164+724 RHS
377 NH-39/STR/393 Protection Work for Stone pitching HPC 165+308 RHS
378 NH-39/STR/394 Protection Work for Stone pitching HPC 156+744 LHS
379 NH-39/STR/395 Reinforcement Checking for Service road portion MNB 156+156 RHS
380 NH-39/STR/396 Shuttering Checcking & Concrete pourring for Raft Service road portion MNB 156+156 RHS
381 NH-39/STR/397 Shuttering Checcking & Concrete pourring for Service road portion MNB 156+156 LHS
382 NH-39/STR/398 Curtain wall Final Lift Box Culvert 155+277 U/S 11.0 0.675
383 NH-39/STR/399 Curtain wall Final Lift Box Culvert 155+277 D/S 11.0 0.675
384 NH-39/STR/400 Curtain wall Final Lift Box Culvert 154+770 U/S 11.0 0.675
385 NH-39/STR/401
386 NH-39/STR/402 Stone pitching 162+950 163+250 LHS 300.0 2.500
387 NH-39/STR/403 Curtain wall Final Lift Box Culvert 154+770 D/S 11.0 0.675
388 NH-39/STR/404 Curtain wall Final Lift Box Culvert 155+277 D/S 11.0 0.675
389 NH-39/STR/405 Curtain wall Final Lift Box Culvert 154+770 U/S 11.0 0.675
390 NH-39/STR/406 Curtain wall Final Lift Box Culvert 155+277 U/S 11.0 0.675
RFI SUMMARY (STRUCTURE)
NH-39/STR/528 Reinforcement & Shuttering Checking Pouring of M35 for outer & inner wall 1st lift (MNB) MNB 156+156 LHS 2 19.93 0.80
NH-39/STR/528 3 19.93 0.49
NH-39/STR/529 Reinforcement & Shuttering Checking Pouring of M35 for outer & inner wall Final lift (MNB) MNB 156+156 LHS 2 19.93 0.80
NH-39/STR/529 3 19.93 0.49
NH-39/STR/531 Reinforcement & Shuttering Checking for 3rd lift wall A1 Side VUP VUP 169+006 LHS
516 NH-39/STR/532
517 NH-39/STR/533
518 NH-39/STR/534 Checking Pouring of concrete M-35 3rd lift wall A1 Side VUP VUP 169+006 LHS
519 NH-39/STR/535 Reinforcement & Shuttering Checking for Dirtwall A2 Side (MNB) MNB 146+938 LHS
520 NH-39/STR/536 Checking Pouring of Concrete M35 Dirtwall A2 Side (MNB) MNB 146+938 LHS
521 NH-39/STR/537 Reinforcement & Shuttering Checking for Dirtwall A2 Side (MJB) MJB 114+443 LHS
NH-39/STR/538 checking of Toe wall PCC HPC 93+219 RHS 2 4.5 0.5
NH-39/STR/539 checking of Toe wall casting HPC 93+219 RHS 2 4.5 0.3
NH-39/STR/540 checking of Toe wall PCC HPC 95+318 RHS 2 4.5 0.5
NH-39/STR/541 checking of Toe wall casting HPC 95+318 RHS 2 4.5 0.3
NH-39/STR/542 checking of Toe wall PCC HPC 95+318 LHS 2 4.5 0.5
NH-39/STR/543 checking of Toe wall casting HPC 95+318 LHS 2 4.5 0.3
528 NH-39/STR/544 Checking Pouring of Concrete M35 Dirtwall A2 Side (MJB) MJB 114+443 LHS
529 NH-39/STR/545 checking of Appron & Stone Pitching work HPC 93+219 RHS 1 20 3
530 NH-39/STR/546 checking of Appron & Stone Pitching work HPC 95+318 RHS 1 20 3
531 NH-39/STR/547 checking of Appron & Stone Pitching work HPC 96+104 RHS 1 20 3
532 NH-39/STR/548 Reinforcement & Shuttering Checking for 1st lift wall Singrauli end (Box Culvert) Box Culvert 158+855 LHS
533 NH-39/STR/549 Checking Pouring of Concrete M35 1st lift wall Singrauli end (Box Culvert) Box Culvert 158+855 LHS
534 NH-39/STR/550 Reinforcement & shuttering Checking Pouring of Concrete M35 VUP 1st lift (MCW) VUP 169+006 RHS 2 12.00 0.83
535 NH-39/STR/551 Reinforcement & shuttering Checking Pouring of Concrete M35 VUP 2nd lift (MCW) VUP 169+006 RHS 2 12.00 0.83
536 NH-39/STR/552 Reinforcement & shuttering Checking Pouring of Concrete M35 VUP 3rd lift (MCW) VUP 169+006 RHS 2 12.00 0.83
537 NH-39/STR/553 Reinforcement & Shuttering checking pouring of M35 for outer & inner wall 1st lift (MNB) 155+800 RHS 2 21.22 0.48
538 NH-39/STR/553 155+800 RHS 2 21.22 0.35
NH-39/STR/555 checking of Toe wall PCC HPC 97+056 RHS 2 4.5 0.5
NH-39/STR/556 checking of Toe wall casting HPC 97+056 RHS 2 4.5 0.3
541 NH-39/STR/557 Reinforcement & Shuttering Checking for slab P2-A2 Span (ROB-2) ROB-2 169+221 LHS
NH-39/STR/558 checking of Toe wall PCC HPC 96+750 LHS 2 4.5 0.5
NH-39/STR/559 checking of Toe wall casting HPC 96+750 LHS 2 4.5 0.3
NH-39/STR/560 Shuttering checking pouring of PCC M15 grade concrete for toe wall 153+190 153+450 RHS 260.00 1.15
NH-39/STR/561 Shuttering checking pouring of Raft M15 grade concrete for toe wall 153+190 153+450 RHS 260.00 1.00
NH-39/STR/562
NH-39/STR/563 Reinforcement & Shuttering Checking for slab P2-A2 Span (ROB-2) ROB-2 169+221 LHS
NH-39/STR/564 Reinforcement & Shuttering checking pouring of M35 for outer & inner wall Final lift (MNB) 155+800 RHS 2 21.22 0.48
NH-39/STR/564 155+800 RHS 2 21.22 0.35
549 NH-39/STR/565 Reinforcement & Shuttering checking pouring of M35 for Raft (MNB) 155+800 RHS 1 21.22 16.65
550 NH-39/STR/566 Shuttering checking pouring of wall M15 grade concrete for toe wall 153+190 153+450 RHS 260.00 0.45
551 NH-39/STR/566 Shuttering checking pouring of M15 for Bed PCC (MNB) 155+800 RHS 1 21.22 16.65
NH-39/STR/567 checking of Appron & Stone Pitching work HPC 96+750 LHS 1 20 3
552 NH-39/STR/568 checking of Appron & Stone Pitching work HPC 97+056 RHS 1 20 3
NH-39/STR/569
553 NH-39/STR/569
554 NH-39/STR/570 Reinforcement & Shuttering Checking for slab P2-A2 Span (ROB-2) ROB-2 169+221 LHS
555 NH-39/STR/571
556 NH-39/STR/572
557 NH-39/STR/573 Reinforcement & shuttering Checking Pouring of Concrete M35 VUP final lift (MCW) VUP 169+006 RHS 2 12.00 0.83
558 NH-39/STR/574
559 NH-39/STR/575
560 NH-39/STR/576
561 NH-39/STR/577 Reinforcement & Shuttering Checking for slab P2-A2 Span (ROB-2) ROB-2 169+221 LHS
562 NH-39/STR/578 Reinforcement & Shuttering checking pouring of M35 for outer & inner wall 1st lift (MNB) 155+800 LHS 2 21.22 0.48
563 NH-39/STR/578 155+800 LHS 2 21.22 0.35
564 NH-39/STR/580
565 NH-39/STR/581
566 NH-39/STR/582
567 NH-39/STR/583
568 NH-39/STR/584 Reinforcement & Shuttering Checking for Dirtwall A2 side (ROB-2) ROB-2 169+221 LHS
569 NH-39/STR/585 Checking Pouring of Concrete M-35 Dirtwall A2 Side (ROB-2) ROB-2 169+221 LHS
NH-39/STR/586 checking of Toe wall PCC HPC 93+219 LHS 2 4.5 0.5
NH-39/STR/587 checking of Toe wall casting HPC 93+219 LHS 2 4.5 0.3
572 NH-39/STR/588 checking of Appron & Stone Pitching work HPC 93+219 LHS 1 20 3
573 NH-39/STR/589 checking of Appron & Stone Pitching work HPC 95+318 RHS 1 20 3
574 NH-39/STR/590 checking of Appron & Stone Pitching work HPC 96+104 LHS 1 20 3
NH-39/STR/591 checking of Toe wall PCC HPC 97+056 LHS 2 4.5 0.5
NH-39/STR/592 checking of Toe wall casting HPC 97+056 LHS 2 4.5 0.3
NH-39/STR/593 checking of Toe wall PCC HPC 170+252 RHS 2 4.5 0.5
RFI SUMMARY (STRUCTURE)
NH-39/STR/620 Reinforcement & Shuttering checking pouring of M35 for outer & inner wall Final lift (MNB) 155+800 LHS 2 21.22 0.48
NH-39/STR/620 155+800 LHS 2 21.22 0.35
NH-39/STR/621 Checking of Curtain wall Bed PCC 183+660 LHS 1 12 1.4
NH-39/STR/622 Shuttering Checking &Pouring M15 for Curtain wall 183+660 LHS 1 12 0.9
NH-39/STR/623 Checking of Curtain wall Bed PCC 184+438 RHS 1 12 1.4
NH-39/STR/624 Shuttering Checking &Pouring M15 for Curtain wall 184+438 RHS 1 12 0.9
NH-39/STR/625 Shuttering checking pouring of M15 for Bed PCC (MNB) 155+800 LHS 1 21.22 16.65
NH-39/STR/626 Reinforcement & Shuttering checking pouring of M35 for Raft (MNB) 155+800 LHS 1 21.22 16.65
NH-39/STR/627
NH-39/STR/628 checking of Appron & Stone Pitching work HPC 169+324 RHS 1 20 3
NH-39/STR/629
NH-39/STR/630
NH-39/STR/631 checking of Toe wall PCC HPC 169+804 RHS 2 4.5 0.5
NH-39/STR/632 checking of Toe wall casting HPC 169+804 RHS 2 4.5 0.3
NH-39/STR/633
NH-39/STR/634
NH-39/STR/635
NH-39/STR/636
NH-39/STR/637
NH-39/STR/638
NH-39/STR/639
NH-39/STR/640
NH-39/STR/641
NH-39/STR/642
NH-39/STR/643
NH-39/STR/644
NH-39/STR/645
NH-39/STR/646
NH-39/STR/647
NH-39/STR/648
NH-39/STR/649 checking of Appron & Stone Pitching work HPC 169+804 RHS 1 20 3
NH-39/STR/650 checking of Appron & Stone Pitching work HPC 170+252 LHS 1 20 3
NH-39/STR/651 checking of Appron & Stone Pitching work HPC 171+160 RHS 1 20 3
NH-39/STR/652 checking of Appron & Stone Pitching work HPC 171+676 LHS 1 20 3
NH-39/STR/653 Checking of Curtain wall Bed PCC 184+438 LHS 1 12 1.4
NH-39/STR/654 Shuttering Checking &Pouring M15 for Curtain wall 184+438 LHS 1 12 0.9
NH-39/STR/655 Checking of Curtain wall Bed PCC 185+062 RHS 1 12 1.4
NH-39/STR/656 Shuttering Checking &Pouring M15 for Curtain wall 185+062 RHS 1 12 0.9
NH-39/STR/657 Checking of Curtain wall Bed PCC 185+062 LHS 1 12 1.4
NH-39/STR/658 Shuttering Checking &Pouring M15 for Curtain wall 185+062 LHS 1 12 0.9
NH-39/STR/659
NH-39/STR/660
NH-39/STR/661
NH-39/STR/662
NH-39/STR/663
NH-39/STR/664
RFI SUMMARY (STRUCTURE)
MARY (STRUCTURE)
Details of Remar
Height Qty Unit Inspection ks
Date
27/12/21
27/12/21
27/12/21
27/12/21
27/12/21
27/12/21
27/12/21
27/12/21
27/12/21
27/12/21
22/12/21
22/12/21
22/12/21
22/12/21
22/12/21
22/12/21
22/12/21
22/12/21
22/12/21
22/12/21
17/12/21
17/12/21
17/12/21
17/12/21
17/12/21
17/12/21
17/12/21
17/12/21
10/12/21
10/12/21
10/12/21
0.150 34.50 Cum 11/12/21
0.150 17.25 Cum 11/12/21
0.150 25.88 Cum 11/12/21
11/12/21
11/12/21
0.400 80.00 Cum 12/12/21
0.400 40.00 Cum 12/12/21
0.400 60.00 Cum 12/12/21
0.150 34.50 Cum 12/12/21
0.150 21.56 Cum 12/12/21
12/12/21
12/12/21
12/12/21
12/12/21
12/12/21
12/12/21
12/12/21
12/12/21
1.000 90.00 Cum 13/12/21
19/01/22
19/01/22
0.900 8.505 Cum 20/01/22
Cum 20/01/22
20/01/22
20/01/22
20/01/22
1.000 135.000 Cum 21/01/22
1.000 117.000 Cum 21/01/22
1.000 47.250 Cum 21/01/22
0.150 108.750 Cum 21/01/22
0.150 127.500 Cum 21/01/22
1.000 9.075 Cum 21/01/22
1.000 9.075 Cum 21/01/22
0.400 42.000 Cum 21/01/22
0.400 8.250 Cum 21/01/22
0.400 7.920 Cum 21/01/22
Cum 21/01/22
Cum 21/01/22
Cum 21/01/22
21/01/22
0.300 217.500 Cum 22/01/22
0.300 255.000 Cum 22/01/22
0.900 6.075 Cum 22/01/22
1.000 9.075 Cum 22/01/22
1.000 9.075 Cum 22/01/22
Cum 22/01/22
Cum 22/01/22
Cum 22/01/22
22/01/22
22/01/22
22/01/22
22/01/22
0.150 112.500 Cum 23/01/22
Cum 23/01/22
Cum 23/01/22
Cum 23/01/22
Cum 23/01/22
Cum 23/01/22
Cum 23/01/22
23/01/22
0.300 225.000 Cum 24/01/22
0.900 6.683 Cum 24/01/22
0.900 6.683 Cum 24/01/22
0.400 0.000 Cum 24/01/22
0.400 217.500 Cum 24/01/22
MARY (STRUCTURE)
Details of Remar
Height Qty Unit Inspection ks
Date
Cum 24/01/22
MARY (STRUCTURE)
Details of Remar
Height Qty Unit Inspection ks
Date
Cum 24/01/22
Cum 24/01/22
Cum 24/01/22
0.1 0.45 Cum 29-1-22 6
0.3 0.81 Cum 30-1-22 6
0.1 0.45 Cum 29-1-22 6
0.3 0.81 Cum 30-1-22 6
24/01/22
Cum 25/01/22
Cum 25/01/22
Cum 25/01/22
Cum 25/01/22
Cum 25/01/22
Cum 25/01/22
Cum 25/01/22
0.1 0.45 Cum 29-1-22 6
0.3 0.81 Cum 30-1-22 6
0.1 0.45 Cum 29-1-22 6
0.3 0.405 Cum 30-1-22 6
0.1 1.68 cum 25/01/22
2.5 27 Cum 25/01/22
Cum 27/01/22
Cum 27/01/22
Cum 27/01/22
Cum 27/01/22
Cum 27/01/22
Cum 27/01/22
Cum 27/01/22
Cum 27/01/22
Cum 27/01/22
Cum 27/01/22
0.1 1.68 cum 27/01/22
2.5 27 Cum 27/01/22
0.1 1.68 cum 27/01/22
2.5 27 Cum 27/01/22
0.1 1.68 cum 27/01/22
2.5 27 Cum 27/01/22
27/01/22
Cum 27/01/22
Cum 27/01/22
Cum 27/01/22
Cum 27/01/22
0.1 0.45 Cum 27/01/22 6
0.3 0.81 Cum 27/01/22 6
0.1 0.45 Cum 27/01/22 6
0.3 0.81 Cum 27/01/22 6
0.1 0.45 Cum 27/01/22 6
0.3 0.81 Cum 27/01/22 6
MARY (STRUCTURE)
Details of Remar
Height Qty Unit Inspection ks
Date
0.1 0.45 Cum 27/01/22 6
0.3 0.81 Cum 27/01/22 6
0.1 0.45 Cum 27/01/22 6
0.3 0.81 Cum 27/01/22 6
09/02/22
09/02/22
0.1 0.45 Cum 26-1-22 6
0.3 0.81 Cum 27-1-22 6
2/21/2022
2/21/2022
2/24/2022
0.15 25.88 cum 31-01-22 6
0.40 60.00 cum 02-01-22 6
1.00 67.50 cum 02-02-22 6
0.1 0.45 Cum 2/2/2022 6
0.3 0.81 Cum 3/2/2022 6
0.1 0.45 Cum 2/2/2022 6
0.3 0.81 Cum 3/2/2022 6
25-02-22
25-02-22
26-02-22
26-02-22
0.1 0.45 Cum 2/2/2022 6
0.3 0.81 Cum 3/2/2022 6
27-02-22
MARY (STRUCTURE)
Details of Remar
Height Qty Unit Inspection ks
Date
02-03-22
02-03-22
02-03-22
02-03-22
0.1 0.45 Cum 2/2/2022 6
0.3 0.81 Cum 3/2/2022 6
0.1 0.45 Cum 4/2/2022 6
0.3 0.81 Cum 5/2/2022 6
0.1 0.45 Cum 6/2/2022 6
0.3 0.81 Cum 7/2/2022 6
03-03-22
0.3 18 Cum 7/2/2022 6
0.3 18 Cum 8/2/2022 6
0.3 18 Cum 8/2/2022 6
03-03-22
03-03-22
1.20 23.76 Cum 8/2/2022 6
1.20 23.76 Cum 9/2/2022 6
1.20 23.76 Cum 10/2/2022 6
1.65 33.26 cum 09-02-22 6
1.65 24.51 cum 09-02-22 6
0.1 0.45 Cum 8/2/2022 6
0.3 0.81 Cum 9/2/2022 6
04-03-22
0.1 0.45 Cum 8/2/2022 6
0.3 0.81 Cum 9/2/2022 6
0.15 44.85 cum 02-07-22 6
0.40 104.00 cum 02-08-22 6
05-03-22