RFI (ROAD & STRUCTURES)

CLNHPL/NH-361/QAP/AN-H/SOILS/03

Four lanning Chakur-Loha section of NH-361 from km. 114+600 to 187+800 ( Design length 73.345 Km) under Bharatmala Pariyojna on HAM in the state
Client National Highway Authority of India
Independent Engineer M/s S.A. Infrastructure Consultant Pvt. Ltd.
Concessionaire M/s Chakur Loha Nanded highways Pvt. Ltd.
Submission Date :-08/09/2021 Inspection Date:- 09/09/2021

STRUCTURE WORK

SR No. CHAINAGE CHECKING Grade Qty. TYPE OF ACTIVITY REMARK


TIME (Cum.)

1 122+208 LHS 11.00 am Pipe Culvert head wall 1st Lift Shuttering checking

2 122+208 LHS 11.00 am M-20 Pipe Culvert head wall 1st Lifth pouring concrete

3 134+374 LHS 14.30 PM Box Culvert Haunch Shuttering checking

4 134+374 LHS 14.30 PM M-30 pouring concrete for Haunch of Box Culvert

ROAD WORK

SR NO. CHAINAGE CHECKING TIME TYPE OF ACTIVITY REMARK

1 125+080 to 125+400 Rhs 09.30 am fdd testing of Subgrade 1st Layer

2 125+500 TO 125+600 RHS 10.00 am fdd testing of Subgrade 1st Layer

3 152+000 TO 153+000 RHS 10.00 am fdd testing of OGL Layer

4 154+200 TO 154+360 LHS 10.30 am fdd testing of Emb 1st Layer

5 124+900 TO 124+990 RHS 10.30 am fdd testing of Subgrade 1st Layer

6 116+000 TO 116+600 RHS 11.00 am fdd testing of Subgrade 1st Layer

7 121+030 TO 121+140 LHS 11.30 am Level & fdd testing of Emb Top Layer

8 154+200 TO 154+360 RHS 11.30 am fdd testing of Emb 1st Layer

9 134+950 TO 134+800 LHS 11.50 am Laying, Level & FDD Testing of DLC Top
10 126+220 TO 126+400 RHS 12.00 pm Level & fdd testing of SG Top Layer

11 123+600 TO 123+750 RHS 14.00 pm Level & fdd testing of SG Top Layer

12 150+050 TO 152+000 RHS 15.00pm C&G Checking

13 144+300 TO 146+300 RHS 16.00pm C&G Checking

14 147+000 TO 148+000 RHS 16.00 pm C&G Checking


RFI (ROAD & STRUCTURES)

Four lanning Chakur-Loha section of NH-361 from km. 114+600 to 187+800 ( Design length 73.345 Km) under Bharatmala Pariyojna on HAM in the state of maharshtra
Client National Highway Authority of India
Independent Engineer M/s S.A. Infrastructure Consultant Pvt. Ltd.
Concessionaire M/s Chakur Loha Nanded highways Pvt. Ltd.
Submission Date :-09/09/2021 Inspection Date:- 10/09/2021

STRUCTURE WORK

CHECKING Qty.
SR No. CHAINAGE SIDE TIME Grade (Cum.) TYPE OF ACTIVITY REMARK

ROAD WORK

SR NO. CHAINAGE SIDE CHECKING TIME TYPE OF ACTIVITY REMARK

1 117+600 to 117+700 LHS 10.00 am fdd testing of Subgrade 1st Layer

2 149+900 to 150+050 RHS 10.00 am C&G Checking

3 117+500 to 117+600 LHS 10.30 am Level & fdd testing of Emb Top Layer

4 124+400 to 124+650 RHS 11.00 am fdd testing of Subgrade 2nd Layer

5 154+900 to 155+420 LHS 11.00 am fdd testing of EMB 3rd layer

6 154+900 to 155+420 LHS 11.30 am fdd testing of EMB 2nd layer

7 114+800 to 115+000 RHS 11.30 am Excavation up to EMB bottom

8 125+880 to 126+200 RHS 12.00 pm Level & fdd testing of Subgrade Top Layer

9 132+800 to 132+940 LHS 2.00 pm fdd testing of Subgrade 2nd Layer

10 133+820 to 134+330 LHS 4.00 pm Level & fdd testing of GSB Top Layer

11 123+750 to 124+000 RHS 4.30 pm Level & fdd testing of Subgrade Top Layer

12 154+900 to 155+420 RHS 4.30 pm fdd testing of EMB 3rd layer


RFI (ROAD & STRUCTURES)

Four lanning Chakur-Loha section of NH-361 from km. 114+600 to 187+800 ( Design length 73.345 Km) under Bharatmala Pariyojna on HAM in the state of maharshtra
Client National Highway Authority of India
Independent Engineer M/s S.A. Infrastructure Consultant Pvt. Ltd.
Concessionaire M/s Chakur Loha Nanded highways Pvt. Ltd.
Submission Date :-10/09/2021 Inspection Date:- 14/09/2021

STRUCTURE WORK

CHECKING Qty.
SR No. CHAINAGE SIDE Grade TYPE OF ACTIVITY REMARK
TIME (Cum.)

ROAD WORK

SR NO. CHAINAGE SIDE CHECKING TIME TYPE OF ACTIVITY REMARK

1 114+700 to 114+800 RHS 10.00 am Excavation up to EMB bottom

2 114+800 to 115+000 RHS 10.30 am fdd testing of OGL

3 117+600 to 117+700 LHS 11.00 am fdd testing of Subgrade 2nd Layer

4 154+900 to 155+420 LHS 11.00 am fdd testing of EMB 4th layer

5 154+900 to 155+420 RHS 11.30 am fdd testing of EMB 4th layer

6 116++000 to 116+600 RHS 11.30 am fdd testing of Subgrade 2nd Layer

7 116+760 to 116+960 RHS 2.00 pm Level & fdd testing of Subgrade Top Layer

8 153+300 to 153+760 RHS 3.00 pm fdd testing of EMB Ist layer

9 115+600 to 115+700 RHS 3.30 pm fdd testing of EMB Ist layer

10 154+400 to 154+600 LHS 4.00 pm fdd testing of Subgrade Ist Layer

11 114+700 to 114+800 RHS 4.00 pm fdd testing of OGL

12 114+800 to 115+000 RHS 4.30 pm fdd testing of EMB Ist layer


RFI (ROAD & STRUCTURES)

Four lanning Chakur-Loha section of NH-361 from km. 114+600 to 187+800 ( Design length 73.345 Km) under Bharatmala Pariyojna on HAM in the state of mahars
Client National Highway Authority of India
Independent Engineer M/s S.A. Infrastructure Consultant Pvt. Ltd.
Concessionaire M/s Chakur Loha Nanded highways Pvt. Ltd.
Submission Date :-12/09/2021 Inspection Date:- 13/09/2021

STRUCTURE WORK

SR No. CHAINAGE SIDE CHECKING Grade Qty. TYPE OF ACTIVITY REMARK


TIME (Cum.)

1 142+200 RHS 9.00 am Shuttering checking of Mould for RE Panel

2 122+208 LHS 9.00 am cheking of laying NP4 Hume pipe in HPC

3 142+200 RHS 9.30 am Pouring concrete in RE panel Mould

4 123+216 RHS 1.00 pm Shuttering checking pcc for Headwall of HPC

5 123+216 RHS 2.00 pm M-15 Pouring concrete pcc for Headwall of HPC

6 122+208 LHS 3.00 pm Shuttering checking Headwall 2nd lift for HPC

7 133+777 LHS 4.00 pm Shuttering checking for pcc of Box culvert

8 123+957 RHS 4.00 pm Shuttering checking pcc of Headwall for HPC

9 123+957 RHS 4.30 pm M-15 Pouring concrete for pcc Headwall of HPC

10 133+777 LHS 5.00 pm M-15 Pouring concrete for pcc of Box culvert

ROAD WORK

SR NO. CHAINAGE FROM CHAINAGE TO SIDE CHECKING TIME TYPE OF ACTIVITY REMARK

1 127+740 128+060 LHS 10.00 am fdd testing of EMB 4th layer

2 154+200 154+360 LHS 10.30 am fdd testing of EMB 2nd Layer

3 144+600 144+700 RHS 11.00 am cheking Excavation upto Emb Bottom

4 154+200 154+360 RHS 11.00 am fdd testing of EMB 2nd Layer

5 154+400 154+600 LHS 12.00 pm fdd testing of Subgrade 2nd Layer

6 154+900 155+420 LHS 4.00 pm fdd testing of EMB 5th layer

7 154+900 155+420 RHS 4.30 pm fdd testing of EMB 5th layer


RFI (ROAD & STRUCTURES)

Four lanning Chakur-Loha section of NH-361 from km. 114+600 to 187+800 ( Design length 73.345 Km) under Bharatmala Pariyojna on HAM in the state of maharshtra
Client National Highway Authority of India
Independent Engineer M/s S.A. Infrastructure Consultant Pvt. Ltd.
Concessionaire M/s Chakur Loha Nanded highways Pvt. Ltd.
Submission Date :-14/09/2021 Inspection Date:- 15/09/2021

STRUCTURE WORK

CHECKING Qty.
SR No. CHAINAGE SIDE Grade TYPE OF ACTIVITY REMARK
TIME (Cum.)

1 162++996 RHS 6.30 am M-35 Pouring concrete for RCC of VUP Abutment Raft A1

2 142+200 RHS 9.30 am Shuttering checking of mould for RE Panel

3 142+200 RHS 9.30 am M-35 Pouring concrete in RE panel mould

4 155+181 LHS 2.00 pm Shuttering checking & alignment of pcc,Headwall for HPC

5 155+181 LHS 2.30 pm M-15 Pouring concrete of pcc for HPC

6 155+181 RHS 2.00 pm Shuttering checking & alignment of pcc,Headwall for HPC

7 155+181 RHS 2.00 pm M-15 Pouring concrete of pcc for HPC

8 155+210 RHS 3.00 pm Shuttering checking pcc for HPC

9 155+210 RHS 3.30 am M-15 Pouring concrete for pcc with headwall for HPC

ROAD WORK

SR NO. CHAINAGE FROM CHAINAGE TO SIDE CHECKING TIME TYPE OF ACTIVITY REMARK

1 115+840 116+600 RHS 10.00 am fdd testing of Subgrade 1st Layer

2 116+140 116+760 RHS 4.00 pm Level & fdd testing of Subgrade Top Layer

3 115+200 115+400 LHS 11.00 am cheking Excavation upto Emb Bottom

4 115+200 115+400 RHS 11.00 am cheking Excavation upto Emb Bottom


5 114+660 114+840 RHS 12.00 pm fdd testing of EMB 2nd layer

6 114+860 115+140 RHS 3.00 pm fdd testing of EMB 2nd layer

7 154+900 155+160 LHS 10.30 am Level & fdd testing of EMB Top Layer

8 154+900 155+160 RHS 10.30 am Level & fdd testing of EMB Top Layer

9 155+220 155+420 LHS 4.30 pm fdd testing of EMB 5th layer

10 155+220 155+420 RHS 4.30 pm fdd testing of EMB 5th layer

11 185+800 186+000 LHS 10.00 am fdd testing of EMB 2nd layer


RFI (ROAD & STRUCTURES)

Four lanning Chakur-Loha section of NH-361 from km. 114+600 to 187+800 ( Design length 73.345 Km) under Bharatmala Pariyojna on HAM in the state of
maharshtra
Client National Highway Authority of India
Independent Engineer M/s S.A. Infrastructure Consultant Pvt. Ltd.
Concessionaire M/s Chakur Loha Nanded highways Pvt. Ltd.
Submission Date :-15/09/2021 Inspection Date:- 16/09/2021

STRUCTURE WORK

CHECKING Qty.
SR No. CHAINAGE SIDE Grade TYPE OF ACTIVITY REMARK
TIME (Cum.)

1 142+200 RHS 9.30 am Shuttering checking of mould for RE Panel

2 142+200 RHS 9.30 am M-35 Pouring concrete in RE panel mould

3 155+181 LHS 2.00 pm Shuttering checking & alignment of pcc,Headwall for HPC

4 155+181 LHS 2.30 pm M-15 Pouring concrete of pcc for HPC

5 155+181 RHS 2.00 pm Shuttering checking & alignment of pcc,Headwall for HPC

6 155+181 RHS 2.00 pm M-15 Pouring concrete of pcc for HPC

7 155+210 RHS 3.00 pm Shuttering checking pcc for HPC

8 155+210 RHS 3.30 am M-15 Pouring concrete for pcc with headwall for HPC

9 128+524 LHS 4.30 pm Shuttering checking & Reinforcement of Raft for VUP

10 128+524 RHS 4.30 pm Shuttering checking & Reinforcement of Raft for VUP

11 122+208 LHS 10.00 am M-20 Pouring concrete for headwall & Encasing for HPC

12 124+397 RHS 12.00 pm fdd testing of foundation of Headwall of HPC

13 126+201 RHS 2.00 pm Pouring concrete of pcc for Box culvert


ROAD WORK

SR NO. CHAINAGE FROM SIDE CHECKING TIME TYPE OF ACTIVITY REMARK

1 152+400 RHS 10.00 am cheking Excavation upto Emb Bottom

2 154+200 LHS 4.00 pm fdd testing of EMB 3rd layer

3 154+200 RHS 4.00 pm fdd testing of EMB 3rd layer

4 127+800 LHS 3.00 pm fdd testing of EMB 5th layer

5 125+500 RHS 3.00 pm fdd testing of SG 2 nd layer

6 116+000 RHS 12.00 pm Level & fdd testing of SG Top Layer

7 115+200 LHS 11.00 am cheking Excavation

8 115+200 RHS 11.00 am cheking Excavation

9 114+660 RHS 12.00 pm fdd testing of EMB 3rd layer

10 114+860 RHS 3.00 pm fdd testing of EMB 3rd layer

11 115+600 RHS 10.00 am fdd testing of EMB Ist layer