You are on page 1of 9

CITIC HEAVY INDUSTRIES CO.

LTD

PROJECT NAME- ALL HADEETHA RESOURCES LLC,AL WASHI MAJAZA COPPER PROJECT

CITIC Heavy Industries Co., Ltd


Address: 206 Jianshe Road, Luoyang, Henan, China
Please visit our website: www.citic-hic.com

LRS & MAIN MOTOR -PRE-COMMISSIONING


CHECK LIST
PROJECT NAME- ALL HADEETHA DATE-
RESOURCES LLC,AL WASHI MAJAZA
COPPER PROJECT
REF: CHIC-EH-2023-001

LRS -MKS 1000A,2200 KW, SL.NO.22214

MAIN MOTOR-MAF 630, SL.NO. - 1069488233/05/22

REPRESENTATIVE CLIENT(AHRL) REPRESENTATIVE (CITIC)

PRE-COMMISSIONING CHECK
OBSERVATIONS STATUS
LIST
LOTOTO OF BALL MILL HVS Done at Site

LIGHTNING ARRESTOR Available

Values are
Input Power Cable IR Test of All phases Tested by client
acceptable
from HVS
Found Okay
SPACE HEATER Wiring & tested

Values are
HT Motor IR of Three Phases Tested at site
acceptable
Glanding Of Panel for Control and
Done by Client
Power Cables, Sealing
Ie=0.5 ohm
Control Panel Earthing Done by Client & tested

1|Page
CITIC HEAVY INDUSTRIES CO. LTD

LRS Earthing of control panel Done by Client & tested


Pe=0.5 ohm

All Tightness of Bolts & Torque Done by Client

Continuity Test of All connection Found in order


Tested at site
along with P. E
Current carrying Conductor to Body Found in order
Tested at site
Earthing
Found in order
Auxiliary power supply for Control Circuit

okay
Brush Lifting operation

Okay
LRS Resistance R max & R min

In order
LRS VFD

In order
Rotor winding of Motor

SIGNATURE (Client)-AHRL SIGNATURE (CITIC)

2|Page
CITIC HEAVY INDUSTRIES CO. LTD

INSTALLATION CHECK LIST OBSERVATIONS STATUS


Brush Lifting okay
Tested at site

okay
Input Voltage Variations With in the limit

Found okay
Main Power Cable terminations Done by Client

Done Found In order &


Main Supply On with in limit
Done at site Checked & found
Motor Space Heater Run for 6 Hrs. working

Motor Run for 6Hrs (Without Gear Done at site All parameters are
Box & Load) in order

FIELD TEST REPORT

EARTH TESTING

REMARKS
TYPE VALUE

ACCEPTED
IE 0.5 OHM

ACCEPTED
PE 0.5 OHM

IR OF HVS CABLE
Phase Sequence found in order.
REMARKS
MODE VALUE

ACCEPTED
R-Y 475 G OHM

ACCEPTED
Y-B 418 GOHM

ACCEPTED
R-B 481 G OHM

ACCEPTED
R-AR 223 G OHM

Y-AR ACCEPTED
182 G OHM

ACCEPTED
B-AR 260 G OHM

3|Page
CITIC HEAVY INDUSTRIES CO. LTD

ROTOR IR VALUES

Phase Sequence found in order.

ACCEPTED
R- AR 524 G OHM

ACCEPTED
Y-AR 586 G OHM

ACCEPTED
B-AR 743 G OHM

SPACE HEATER FOR HT MOTOR


VOLTAGE CURRENT

R1-N 229 Vac PHASE 1 9.25 A

R2-N 229 Vac PHASE 2 9.25 A

ROTOR FIELD RESISTANCE

HT MOTOR IR & PI
LEGEND VALUE PI REMARKS

U-G 13.3 T OHM 3.48 Excellent

V-G 15.05 T OHM 2.54 Good

W-G 15.05 T OHM 2.32 Good

MOTOR PARAMETERS:
SL.NO & MAKE-MODEL NOMINAL NOMINAL KW NO. OF NS HZ STATOR
VOLATGE CURRENT POLES RESISTANCE IN
OHM
MAF 630, SL.NO. - 11000 140 A 2200 6 994 50 0.94
1069488233/05/2200
KW
NO LOAD
CURRENT-
46 A
*FRAME EARTHING MUST BE TESTED. -OKAY
*BEFORE IR TEST ALL THE SENSORS CONNECTIONS MUST BE OUT FROM TERMINAL BOX- OKAY

4|Page
CITIC HEAVY INDUSTRIES CO. LTD

MOTOR & LRS DEBUGING:

1. RMAX- 1678 OHM


2. RMIN- 0.9 OHM
3. CONDUCTIVITY- 5.89 MS/CM
4. TEMP-.23.5 DEG.C

Remarks: All Parameters are in order & performance of LRS & MOTOR are found Good.

SIGNATURE (Client)-AHRL SIGNATURE (CITIC)

5|Page
CITIC HEAVY INDUSTRIES CO. LTD

1. MAIN LUBE SYSTEM HEALTHY AND RUNNING IN AUTO MODE


2. GEAR BOX ALL PARAMETERS ARE NORMAL.
3. AUXILARIES SYSTEMS ARE FINE.
4. ALL INSTRUMENTS ARE WORKING FINE
5. MAIN MOTOR WITH BRUSH LIFTING PANEL IN AUTO MODE STARTED NORMALLY
6. LRS WORKING FINE IN AUTO MODE.
7. OPERATIONAL TRANING GIVEN TO AHRL TEAM.

SIGNATURE (Client)-AHRL SIGNATURE (CITIC)

6|Page
CITIC HEAVY INDUSTRIES CO. LTD

MM WITH GEAR BOX

TIME MM MM MM GB TEMP GB VIBRATION


VIBRATION TEMP CURRENT

DE NDE A B C AMPS SUMP LS HS LS HS

DR NDR DR NDR DR NDR DR NDR

Remarks: Main Motor +Gear Box test period from the operation of whole system found
healthy, and parameters are normal.

SIGNATURE (Client)-AHL SIGNATURE (CITIC)

7|Page
CITIC HEAVY INDUSTRIES CO. LTD

INTRUMENTS

 Mill
1. Fixed side- TE ½/3
2. Floating Side- TE 4/5/6
 Pinion
1. Floating Side
VT 009 -AXIAL
VT 008- RADIAL
TE 007
2. Fixed Side
VT 015-AXIAL
VT 014-RADIAL
TE013
 Infrared
TIA 010
TIA011
TIA012
 Gear Box
1. LOW SPEED
DE
VT017
TE 016
NDE
VT019
TE018
GB LUBE FLOW
ELETTA-40-200 L/MIN
GB PIPE FLOW
KOLBOLD-40-150 L/MIN
2. HIGH SPEED
DE
TE020
VT021
NDE
TE022
VT023

SUMP
TE024
3. MOTOR
DE
VT026
TE 036
TEO37
NDE
VT 027
TE029
STATOR- TIA 035/034/033/032/031/030

8|Page
CITIC HEAVY INDUSTRIES CO. LTD

BALL MILL MOM

1. LUBRCATION SYSTEM, GREASE SPRAY, SEAL GREASE SYSTEM STARTED IN AUTO MODE
2. RANGE & ALARMS ARE CHECKED
3. FLOW DEVIDERS SENSORS ARE INSTALLED ARE OPERATING NORMALLY.
4. MILL MAIN MOTOR STARTING CURRENT IS NORMAL AND LRS OPERATION IS OKAY
5. BRUSH LIFT PANEL IS OPARTED FORM PLC IN AUTO MODE & FOUND SATISFACTORY.
6. GEAR BOX LUBRICATION SYSTEM & MILL LUBRACTION SYSTEM ALL PARAMETERS ARE IN ORDER.
7. ALL SYSTEM OPERATION ARE FOUND SATISFACTORY

SIGNATURE (Client)-AHL SIGNATURE (CITIC)

9|Page